Is a Text a Writing?
June 10, 2024 —
Michael Yelle - Ahlers Cressman & Sleight PLLCIs a text message a writing? Project communication is constantly evolving, and text messages are an increasingly common way teams share pictures, video, and provide project updates. When texting is part of the communication flow on a project, contractors and owners might text approvals for extra work, notices of changed conditions, or other information that could be a basis for a change order.
In a text exchange about a compensable event, the notice, reply, and approval are all saved on the phone. But contracts often contain specific requirements for a contractor or subcontractor to request changes and authorization to proceed may be specifically required in writing.
For example, the Associated General Contractors of Washington – 2018 Standard Subcontract says the “Subcontractor shall make no claims for extras unless the same shall be agreed upon
in writing by Contractor prior to performance of any such extra work.” (emphasis added).
The AGC subcontract doesn’t define “writing,” so the subcontractor and contractor might wonder if a text message exchange about a potentially compensable event was an “agreement in writing.”
Read the court decisionRead the full story...Reprinted courtesy of
Michael Yelle, Ahlers Cressman & Sleight PLLCMr. Yelle may be contacted at
michael.yelle@acslawyers.com
Employee Screening and Testing in the Covid-19 Era: Getting Back to Work
August 10, 2020 —
Aaron C. Schlesinger & Shannon D. Azzaro - Peckar & AbramsonCurrently Available Workplace Protocols for Employers
Employers seeking to minimize the risk of COVID-19 transmission in the workplace should consider from among the three currently available protocols: Written Questionnaires; Temperature Checks; and Viral or Diagnostic Testing.
When implementing a screening or testing protocol, employers should explain the following in writing to employees: (1) the specific screening process or test utilized by the employer; (2) employee compliance expectations and any consequences for a refusal to participate; (3) how employee privacy will be protected; (4) if screening, the general benchmarks that indicate the employee has “passed” (e.g., temperature below 100.4ºF, per CDC guidelines); and (5) the outcome of an unsuccessful screen or test (e.g., being sent home from the workplace). Employers must also ensure that those administering the screening and/or testing are properly trained, and that appropriate written acknowledgements are obtained from employees consenting to the applicable protocol.
Reprinted courtesy of
Aaron C. Schlesinger, Peckar & Abramson and
Shannon D. Azzaro, Peckar & Abramson
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Ms. Azzaro may be contacted at sazzaro@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
DC District Court Follows Ninth Circuit’s Lead Dismissing NABA’s Border Wall Case
April 10, 2019 —
Anthony B. Cavender - Gravel2GavelOn February 14, the U.S. District Court for the District of Columbia dismissed the complaint of the National American Butterfly Association (NABA) alleging that the U.S. Government’s border wall preparation and law enforcement activities at NABA’s National Butterfly Center, located in South Texas along the Rio Grande River, violated federal environmental laws (National Environmental Policy Act (NEPA)) and the Endangered Species Act (ESA)) as well as NABA’s constitutional rights. The case is National American Butterfly Association v. Nielsen, et al.
On January 25, 2017, the President issued an Executive Order to the Secretary of the Department of Homeland Security (Secretary) to “take all appropriate steps to immediately plan, design, and construct a physical wall along the southern border” with Mexico. A few weeks later, the Secretary issued a memorandum to the U.S. Customs and Border Enforcement to implement the Executive Order. The land occupied by the NABA has been affected by these actions, as well as other actions taken by the Secretary pursuant to her authority under the Illegal Immigration Reform and Immigrant Responsibility Act (IIRIRA), located at 8 U.S.C. § 1103.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Contract Change # 10: Differing Site Conditions (law note)
March 28, 2018 —
Melissa Dewey Brumback - Construction Law in North CarolinaPreviously, the A201 required a Contractor to provide notice to the Owner and Architect within 21 days after discovery of unforeseen site conditions. This notification is required prior to the conditions being disturbed, so as to allow the Design Team the ability to evaluate the site and determine the compensability of any such differing conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North Carolina
2020s Most Read Construction Law Articles
January 25, 2021 —
ConsensusDocs2020 was . . . well . . . well it was memorable. Among many other things, construction was recognized as essential and ConsensusDocs published industry firsts in addressing prefabricated construction and lean for design-build, as well as 8 comprehensively revised performance and payment bonds. We also saw unprecedented readership of our construction law newsletter. As we celebrate the end of 2020 and wish you a happy new year, we continue a new a tradition of recognizing the below most read construction law articles of the year.
The ConsensusDocs Team.
5.
Level 10 Construction v. Sea World LLC: Can Force Majeure Save Sea World?
By:
Jamey B. Collidge Associate,
Troutman Pepper.
4.
The Designer’s Pre-bid Standard Of Care In A Design-Build Project
By:
Joshua A. Morehouse Associate,
Peckar & Abramson P.C. Read the court decisionRead the full story...Reprinted courtesy of
No Damage for Delay? No Problem: Exceptions to the Enforceability of No Damage for Delay Clauses
October 18, 2021 —
Chris Broughton, Jones Walker LLP - ConsensusDocsIntroduction:
Under a no-damage-for-delay clause, the owner is not liable for any monetary damages resulting from delays on the project. In lieu of monetary recovery, the contractor’s remaining remedy is a non-compensatory time extension. These clauses are common at the contractor-subcontractor interface as well.
While no-damage-for-delay clauses are enforced in most jurisdictions, some states, either by statute or case law, have limited the enforceability of no-damage-for-delay clauses. Other states have also limited the enforceability of these clauses on state government contracts, and a select few have outlawed them on all projects regardless if they are publicly or privately owned. Additionally, for subcontractors on federal projects, the Miller Act may provide a way to avoid no-damage-for-delay and recover against the general contractor’s payment bond.
This article provides an overview of no-damage-for-delay clauses and the exceptions to enforcement of these clauses. However, due to the consequences of a no-damage-for-delay clause, it is important to know the terms of your contract and the law that governs your project.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Broughton, Jones Walker LLPMr. Broughton may be contacted at
cbroughton@joneswalker.com
Know Whether Your Course of Business Operations Are Covered Or Excluded By Your Insurance
December 27, 2021 —
David Adelstein - Florida Construction Legal UpdatesIt is a good idea to know what your insurance covers and does not cover. This way, if your course of business has you performing a certain (risky) operation, you know whether that operation is covered or excluded under your policy. If you are not sure, discuss with your insurance broker — this is important. There is little value performing an operation that is NOT covered by your insurance policy, as you are now performing a risk that is not covered by insurance. If you know it is not covered by insurance you may elect to change your operations or see if there is insurance to cover the risk. Below is a case study of this occurrence dealing with a commercial automobile liability policy where an insured’s operations using a crane mounted to a super duty truck was not covered under their automobile liability policy.
In People’s Trust Ins. Co. v. Progressive Express Ins. Co., 46 Fla. L. Weekly D262a (Fla. 3d DCA 2021), homeowners hired a company to install a shed. The company hired another company to deliver and install the shed using a crane; the company used a crane mounted to a Ford F-750 super duty truck. This company improperly operated the crane resulting in the shed falling and damaging the homeowner’s roof. The homeowners submitted a claim to their property insurer and their property insurer subrogated to their rights and sued. The company operating the crane’s commercial automobile liability insurer denied coverage, and thus, denied the duty to defend. As a result, a
Coblentz-type agreement was entered into where the company operating the crane consented to a judgment in favor of the property insurer (subrogee) and assigned its rights under its commercial automobile liability policy to the property insurer. The property insurer then sued the automobile liability carrier for coverage. The trial court granted summary judgment in favor of the automobile liability insurer finding there was no coverage and this was affirmed on appeal. Why?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Substantial Completion Explained: What Contractors & Owners Should Know
January 17, 2022 —
Travis Colburn - Ahlers Cressman & SleightA project’s Substantial Completion date is a critical construction milestone for contractors and owners. Depending on the contract, the date of Substantial Completion has project-specific contractual and statutory consequences.
Substantial Completion is an “event” – there is no universal definition of the term. It is generally understood to be (1) a point in time (2) when work performed by the contractor is sufficiently complete (3) where it can be used or occupied for the owner’s intended purpose. The date of Substantial Completion is generally established at the time of contract formation (either as a negotiated or a contract set date), and that date may be adjusted over the course of a project to account for excusable delays.
As a construction professional, your attorney should review and tailor any written agreement to your project-specific needs and risk tolerances prior to execution. Savvy construction professionals often start with standard form agreements promulgated by the American Institute of Architects (“AIA”), the Design-Build Institute of America (“DBIA”), or the Engineers Joint Contract Document Committee (“EJCDC”) as the basis for their construction contracts. The AIA, DBIA, and EJCDC standard forms each contains contract provisions relating to when and what happens once Substantial Completion has occurred, subject to any agreed-to, project-specific deviations.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com