Bill Wilson - Construction Law ZoneBusiness relationships often begin before parties execute a written agreement containing the terms and conditions by which the relationship will be governed. With little more than a Letter of Intent (“LOI”) or Letter of Award (“LOA”) one party is typically pressured to begin investing time and money to start preliminary work on a project. If such LOI or LOA contains nothing more than an agreement to agree later, the performing party should minimize its investment until the later agreement is executed. A recent court decision in New York confirmed the danger to the performing party under “agreement to agree” provisions.
In Permasteelia North America Corp. v. JDS Const. Group, LLC, 2022 WL 2954131 (N.Y. Sup. CT. 7/22/22), the plaintiff subcontractor allegedly performed $1.9 million worth of preliminary work under nothing more than a LOA with an agreement to agree provision. Issues arose, and the parties never entered any later written agreement. The general contractor refused to pay the plaintiff anything for its preliminary work. In response, the plaintiff filed suit against the general contractor asserting four counts: foreclosure of its lien, breach of contract, unjust enrichment, and account stated. All four counts were based on an alleged oral “handshake deal” for subcontract work for the project. The general contractor’s LOA stated that neither party would be bound “unless and until the parties actually execute a subcontract.” During discovery, the plaintiff admitted that neither party intended to enter into any contract until its potential terms were negotiated, reduced to writing, and signed. Moreover, the plaintiff only offered one set of meeting minutes and a few project agendas to support its alleged “handshake deal.” Once these necessary undisputed facts were confirmed, the defendant moved for summary judgment on all four counts.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Business Interruption Claim Granted in Part, Denied in Part
February 16, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe court granted portions of the business interruption claim, while denying other portions. Phoenix Ins. Co. v. Infogroup, Inc., 2015 U.S. Dist. LEXIS 162810 (S. D. Iowa Nov. 30, 2015).
Phoenix insured Infogroup's business buildings and personal business property, including data and data processing equipment. In late May 2011, warnings were issued of possible flooding from the Missouri River. On June 1, 2011, Infogroup moved and relocated its business operations and data centers away from the river and did not intend to return to the facilities. On July 19, 2011, Phoenix advanced $500,000 to Infogroup for anticipated claims under the policy. On August 22, 2011, heavy rain left surface water in the parking lot at Infogroup's facilities. Infogroup claimed that it suffered minor property damage during July and August, 2011, including damage to an uninterruptable power source and damage to a server.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Be Proactive Now: Commercial Construction Quickly Joining List of Industries Vulnerable to Cyber Attacks
June 15, 2017 —
Jeffrey M. Dennis & Nathan Owens – Newmeyer & Dillion LLPCommercial contractors have long faced their own unique business risks - labor and material shortages, delay claims, bonding issues, and defects in workmanship. But, in today's ever-evolving cyber world, it is imperative that contractors understand they are vulnerable to risks beyond finishing a project on time and on budget. As we are seeing more and more each day, cyber threats impact all businesses, including the construction industry, and the failure to protect against these threats will cost your company millions in damages and reputational harm.
UNDERSTANDING CYBER THREATS
Traditionally, cyber threats are thought of as the theft of employee and customer information over the internet. Given the construction industry is the largest employer in the world, the need to protect this information is obvious. The release or loss of personnel or consumer data could lead to extensive liability under a variety of potential claims, including statutory fines. In addition to securing confidential information, companies have to protect against outside agents accessing control of a company’s security protocols, equipment or encrypting files using malicious software. The recent “WannaCry” attack demonstrates that no business is immune from cyber attacks.
EXAMPLES OF RELATED BREACHES
For those that think these scenarios do not happen, here are two examples of these types of breaches:
* In May 2013, Chinese hackers stole floor plans, server information, and security system designs from an Australian prime contractor. Fearing the risks of compromised physical and network security, the contractor incurred additional costs of $132.6 million in project delays and costs to rework the various components that had been stolen.
* Then, in December 2014, a German governmental office reported that a steel mill suffered massive damage when malware prevented a blast furnace from being properly shut down. Hackers gained access to key technology within the company, which eventually allowed them to control the production line.
THE NEW WORLD OF THE IoT
In addition to these types of “traditional” hacking threats, cybersecurity risks continue to evolve and become more complicated every day. Some of these new threats are driven by the development of a phenomenon known as the Internet of things, or IoT. The IoT is most basically defined as the interconnection of devices with on / off switches to the Internet and each other. Since the IoT is estimated to be 20 billion or more devices within 3 years, and can be combined with malicious software, IoT poses one of the most challenging risks for contractors to protect against.
The technology included in today's commercial buildings clearly opens this avenue of risk. A centralized computer control center, typically employed in new buildings, controls and maintains the systems that are vital to the operation of the building, e.g., power, elevators, HVAC, lighting, and security. What happens if a hacker gains control to one of these systems, let alone all of them? What if a hacker simply utilizes an IoT attack to overwhelm a building’s computer systems? In either scenario, at a minimum, significant disruption would occur. Worse, the health and safety of those within the building could be jeopardized. A hacker may utilize ransomware in combination with an IoT attack to take over control of the building and hold it and possibly the occupants “hostage” until a ransom is paid.
The first significant IoT attack happened in October 2016 when a major web hosting company was attacked through the IoT, causing the host site to crash. The attack did not steal information, it simply caused the site to crash. But, that crash caused world-wide disruption across the Internet.
Hackers used malicious software to access a hundred thousand common household devices — web cameras, fitness trackers, DVR’s, smart TVs and even baby monitors — to flood the hosting company’s servers with incredibly high internet traffic. This attack showed that everyday items can be hacked and controlled by cyber criminals and then used against anyone else.
As we have all seen in recent news, the WannaCry cyber attack impacted businesses across the globe. Days after the attacks, hospitals were still left feeling its impact with continued appointment and planned operation cancellations, and delays in service. We should expect to see these types of attacks increasing in frequency.
PAY ATTENTION OR FACE THE CONSEQUENCES
Make no mistake about it, the stakes are incredibly high in the realm of cyber security protection. By 2021, the annual worldwide cost attributable to cyber attacks is estimated to reach the trillions of dollars. If any of these potential attacks occur, a contractor faces significant exposure, in many forms, including:
* Monetary. Cybersecurity events result in direct monetary losses in the form of notification costs, data recovery costs, and, of course, legal and public relations fees. States are also starting to impose strict standards on companies which will result in significant regulatory punishment in the cases of cyber breaches, including the added costs associated with agency investigations, regulatory fines and consumer redress funds.
* Reputation. Perhaps more important than the monetary risk, a contractor may incur substantial reputational harm if such a breach or attack is successful. Recent data has shown that small to medium-sized companies that experience a significant cybersecurity breach go out of business within six months of the breach – due to not only high monetary costs, but severe reputational damage.
* Criminal. The recently passed New York cybersecurity regulations place potential criminal penalties on compliance personnel. Other states are likely to follow New York.
As a business leader and commercial builder, the time to act is now. While the purchase of specific cyber insurance is an important part of protecting against the risks of a cyber attack, many cyber policies contain exclusionary language embedded in the policy making coverage potentially illusory. Additional steps can and need to be taken immediately, including an honest discussion of internal cybersecurity protections, examination of risk management strategy, and the training of employees. Failure to take these important steps could result in a disastrous cybersecurity breach and the loss of millions of dollars.
Jeffrey M. Dennis currently serves as Newmeyer and Dillion’s Managing Partner and, as a business leader, advises his clients on cybersecurity related issues, introducing contractual and insurance opportunities to lessen their risk. You can reach Jeff at jeff.dennis@ndlf.com.
J. Nathan Owens is the Managing Partner for Newmeyer & Dillion’s Las Vegas office. With more than 10 years in the construction industry as a former contractor himself, Nathan understands the complex issues builders and developers face in all aspects of development and construction. You can reach Nathan at nathan.owens@ndlf.com.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit http://www.newmeyeranddillion.com/.
Read the court decisionRead the full story...Reprinted courtesy of
Policy's Operation Classification Found Ambiguous
May 21, 2014 —
Tred R. Eyerly – Insurance Law HawaiiProperty damage caused by a subcontractor's sheet piling was found to be within the policy's operation classification, which included "grading of land." Canal Indemn. Co. v. Margaretville of NSM, Inc., No. 13-13541 (11th Cir. April 15, 2014).
Canal issued a CGL policy to the insured. The policy had a classification limitation provision: “This insurance applies to bodily injury, property damage, personal injury, advertising injury or medical expense arising out of only those operations that are classified and shown on the Commercial General Liability Coverage Declarations . . .”
The policy's Declarations, in turn, referred to the operation classification as "Grading of Land - INCL. Borrowing, Filling or Back Filling." The policy did not define these terms.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Motion for Summary Judgment Gets Pooped Upon
December 16, 2023 —
Garret Murai - California Construction Law BlogI’ve read some crappy motions over the years, some of which opposing counsel might even attribute to me, but I don’t think I’ve ever written about poop and motions.
In Beebe v. Wonderful Pistachio & Almonds LLC, a summary judgment motion filed by a project owner sued by a construction worker for personal injuries caused by bird poop, which in turn caused a nasty fungal infection which spread to his brain, resulted in a not-so-wonderful ending for Wonderful.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
DOE Abruptly Cancels $13B Cleanup Award to BWXT-Fluor Team
February 01, 2021 —
Mary B. Powers & Debra K. Rubin - Engineering News-RecordThe U.S. Energy Dept. has cancelled a $13-billion, 10-year contract awarded just a few months ago to a team led by BWXT Technical Services and Fluor Federal Services to manage millions of gallons of radioactive waste stored underground at its Hanford, Wash., former weapons site—confirming plans for a major scope expansion and lengthy reprocurement but sharing few details.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record and
Debra K. Rubin, Engineering News-Record
Ms. Rubin may be contacted at rubind@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Rooftop Solar Leases Scaring Buyers When Homeowners Sell
June 26, 2014 —
Will Wade – BloombergDorian Bishopp blames the solar panels on his roof for costing him almost 10 percent off the value of the home he sold in March.
That’s because instead of owning them he leased the panels from SunPower Corp. (SPWR), requiring the new owner of the house to assume a contract with almost 19 years remaining. He had to shave the asking price for the house in Maricopa, Arizona, to draw in buyers unfamiliar with the financing arrangement.
Leasing is driving a boom in solar sales because most require no money upfront for systems that cost thousands of dollars. That’s made solar affordable for more people, helping spur a 38 percent jump in U.S. residential installations in the past year. Since the business model only gained currency in the past two years, the details embedded in the fine print of the deals are only starting to emerge.
Read the court decisionRead the full story...Reprinted courtesy of
Will Wade, BloombergMr. Wade may be contacted at
wwade4@bloomberg.net
Federal Judge Refuses to Limit Coverage and Moves Forward with Policyholder’s Claims Against Insurer and Broker
December 07, 2020 —
Michael S. Levine & Casey L. Coffey - Hunton Insurance Recovery BlogOn November 10, 2020, a New York federal judge dismissed an insurer’s counterclaims seeking to cap its exposure under a $15 million sublimit and an order estopping the policyholder from pursuing any additional amounts.
In February 2017, Plaintiff Pilkington North America, Inc. (Pilkington), suffered between $60 and $100 million in damage from a tornado that struck its glass manufacturing factory in Illinois. Pilkington sought coverage for its loss under a commercial property and business interruption policy issued by Defendant Mitsui Sumitomo Insurance Company (MSI). Pilkington also claimed its insurance broker, Aon Risk Services Central, Inc. (Aon), is liable for faulty advice provided while brokering the policy. Aon’s negligence allegedly gave way to MSI’s fraudulent revision of the insurance policy, which caused the losses from the tornado to not be fully compensable.
Pilkington’s fraud and faulty brokering claims stem from MSI’s revision of an endorsement contained in the policy. The revision changed the wording of a windstorm sublimit. Allegedly, Aon was informed by MSI of the changes and failed to inform Pilkington that the revision would substantially reduce coverage for windstorms, including tornados.
Read the court decisionRead the full story...Reprinted courtesy of
Michael S. Levine, Hunton Andrews KurthMr. Levine may be contacted at
mlevine@HuntonAK.com