Ohio Supreme Court Case to Decide Whether or Not to Expand Insurance Coverage Under GC’s CGL Insurance Policies
August 14, 2018 —
David Suggs – Bert L. Howe & Associates, Inc.According to W. Matthew Bryant of Saul Ewing Arnstein & Lehr LLP, the Ohio Supreme Court will be deciding whether or not a general contractor's commercial general liability ("CGL") insurance policy may provide coverage for damage caused by a subcontractor's defective construction work.
Bryant explained the status quo in Ohio: “Since 2012, Ohio has followed the rule that a CGL policy would not cover damage caused by a contractor to the contractor's own work.” That could change depending on how the Ohio Supreme Court rules in an upcoming case: “The Ohio Supreme Court will decide whether to affirm or overturn Ohio Northern University v. Charles Construction Services, Inc., 77 N.E.3d 538 (Ohio Ct. App. 2017) ("ONU"), an Ohio Court of Appeals decision holding that CGL coverage may exist for property damage caused by faulty work performed by the subcontractor of an insured general contractor.”
Read the court decisionRead the full story...Reprinted courtesy of
'Major' Mass. Gas Leak Follows Feds Call For Regulation Changes One Year After Deadly Gas Explosions
October 21, 2019 —
Johanna Knapschaefer - Engineering News-RecordA natural gas leak in explosive range forced Lawrence, Mass. residents to evacuate their homes early on Sept. 27, according to electric utility National Grid, which cut power to more than 1,300 customers to avoid another disaster like last year's natural gas explosions and fires in Lawrence and two other towns north of Boston. The leak came just days after federal officials called for changes to national pipeline regulations as they released a final report on the causes of the Sept. 13, 2018, disaster.
Read the court decisionRead the full story...Reprinted courtesy of
Johanna Knapschaefer, ENRENR may be contacted at
ENR.com@bnpmedia.com
The Harmon Hotel Construction Defect Trial to Begin
October 29, 2014 —
Beverley BevenFlorez-CDJ STAFFThe trial involving the Las Vegas Harmon Hotel, which is currently being demolished piece by piece due to construction defects, is ready to begin six years after the defects were first discovered, reported the Las Vegas Review-Journal. It’s an unusual case for multiple reasons. The trial is expected to last a year, and the number of attorneys involved in the case required chairs to be removed from the galley to accommodate lawyer tables, which are wired with monitors and microphones. In addition, “two 80-inch monitors are being installed for the jury.”
The Las Vegas Review-Journal further reported that “each party will have its own technology team to display the more than 3 million digitally stored pieces of evidence.” Michael Doan, the court’s information technology director, told the Las Vegas Review-Journal that the “paper list of that evidence fills more than 100 document-storage boxes.”
The case “involves more than $400 million in damage claims.” Construction on the Harmon Tower was stopped after a “structural engineer hired by MGM Resorts determined the building was unsafe and could topple if an earthquake of a magnitude of 7.7 were to hit Las Vegas.”
Read the court decisionRead the full story...Reprinted courtesy of
Another Way a Mechanic’s Lien Protects You
September 14, 2020 —
Christopher G. Hill - Construction Law MusingsHere at Construction Law Musings, we have discussed mechanic’s lien law in Virginia on multiple occasions. We have discussed everything from the very picky nature of the perfection and enforcement of these liens to the changes that the Virginia General Assembly periodically makes to these requirements and how to defend against such liens.
While the steps taken and content of a Virginia mechanic’s lien will be strictly construed by the Virginia courts, when perfected properly, a mechanic’s lien can and will put you as a construction company seeking payment in a better position than if no lien were recorded. The direct benefit is that you now hold a lien on the property on which you performed work that takes a priority (read will be paid before) any mortgage or other lien on that structure. In other words, if you, the bank, or the owner seeks to sell the property through foreclosure or otherwise, mechanic’s lien holders generally get paid first. While there are exceptions to be explored with an experienced Virginia construction attorney, this is the general rule and the power of a mechanic’s lien.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Preparing the Next Generation of Skilled Construction Workers: AGC Workforce Development Plan
November 08, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPIn August, Associated General Contractors (AGC) and Autodesk released the results of their 2017 Construction Workforce Shortage Survey. Of the more than 1,600 survey respondents, 70 percent said they are having difficulty filling hourly craft positions. Craft worker shortages are the most severe in the West, where 75 percent of contractors are having a hard time filling those positions, followed by the Midwest where 72 percent are having a hard time finding craft workers, 70 percent in the South and 63 percent in the Northeast.
Tight labor market conditions are prompting firms to change the way they operate, recruit and compensate workers. Most firms report they are making a special effort to recruit and retain veterans (79 percent); women (70 percent), and African Americans (64 percent). Meanwhile, half of construction firms report increasing base pay rates for craft workers because of the difficulty in filling positions. Twenty percent have improved employee benefits for craft workers and 24 percent report they are providing incentives and bonuses to attract workers.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
“Slow and Steady Doesn’t Always Win the Race” – Applicability of a Statute of Repose on Indemnity/Contribution Claims in New Hampshire
November 24, 2019 —
Rahul Gogineni - The Subrogation StrategistIn Rankin v. South Street Downtown Holdings, Inc., 2019 N.H. LEXIS 165, the Supreme Court of New Hampshire considered, pursuant to a question transferred by the trial court, whether RSA 508:4-b, the statute of repose for improvements to real property, applies to indemnity and contribution claims. The court concluded that based upon the plain reading of the statute, it applies to indemnity and contribution claims. As noted by the court, a holding to the contrary would violate the intent of a statute of repose, which is to establish a time limit for when a party is exposed to liability.
In Rankin, after falling and injuring himself while leaving a building, John Rankin and his wife brought an action against the property owner, South Street Downtown Holding, Inc. (South Street) in 2017. South Street subsequently filed a third-party complaint against multiple parties including an architectural company, Wagner Hodgson, Inc. (Wagner), who was involved in a renovation project at the property. The project was substantially complete in 2009. Wagner responded by moving to dismiss the action, arguing that South Street’s indemnification and contribution claims were barred by the applicable statute of repose.
RSA 508:4-b specifically states,
Except as otherwise provided in this section, all actions to recover damages for injury to property, injury to the person, wrongful death or economic loss arising out of any deficiency in the creation of an improvement to real property, including without limitation the design, labor, materials, engineering, planning, surveying, construction, observation, supervision or inspection of that improvement, shall be brought within 8 years from the date of substantial completion of the improvement, and not thereafter. (Emphasis added).
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at
goginenir@whiteandwilliams.com
Is Modular Construction Destined to Fail?
March 11, 2024 —
Aarni Heiskanen - AEC BusinessThe construction sector is a harsh environment for innovation. I’ve been following the story of one Finnish innovative contractor, Lehto Group, over the years with enthusiasm. I was saddened to hear that the group’s three significant subsidiaries joined the ranks of many Finnish contractors who have filed for bankruptcy over the last six months.
Lehto developed industrialized building concepts and had its own production facilities. The company had a promising start but eventually ran into problems. Was the industrial approach a mistake, or were other factors contributing to the firm’s fall?
Three Contributing Factors
Lehto Group’s collapse was not a surprise to its competitors, who had observed warning signs years prior. The company’s order book plummeted in 2024 despite still employing around 500 workers. Rakennuslehti, the leading construction magazine in Finland, asked three experienced industry professionals to give their views on Lehto’s failure. The interviewees spoke anonymously due to the small size of the Finnish market and the sensitive nature of commenting on a competitor’s matters.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Home Buyers Lose as U.S. Bond Rally Skips Mortgage Rates
September 03, 2014 —
Jody Shenn – BloombergPotential home buyers watching this year’s plunge in 10-year Treasury yields can be forgiven for wondering why their borrowing costs aren’t falling at the same pace.
The last time the benchmark Treasury rate fell as low as the 2.34 percent level reached last week, in June 2013, interest rates on typical mortgages were almost 0.2 percentage point less than they are now. There are a number of explanations: Yields on five-year Treasuries, which also help determine loan rates, have actually increased. And lenders that cut staff aren’t competing as aggressively by adjusting their pricing.
No matter the cause, the effect is that a potential catalyst to get the faltering U.S. housing recovery back on track is failing to materialize. With home-loan rates stagnating at about 4.1 percent during the past three months, a renewed boom in refinancing also sits just out of reach.
Read the court decisionRead the full story...Reprinted courtesy of
Jody Shenn, BloombergMs. Shenn may be contacted at