The Year 2010 In Review: Design And Construction Defects Litigation
February 25, 2011 —
Candace Matson, Harold Hamersmith, and Helen LauderdaleThis article is the first in a series summarizing construction law developments for 2010
1. Centex Homes v. Financial Pacific Life Insurance Co., 2010 U.S. Dist. LEXIS 1995 (E.D. Cal. 2010)
After settling numerous homeowners’ construction defect claims — and more than ten years after the homes were substantially completed — a home developer brought suit against one of the concrete fabrication subcontractors for the development seeking indemnity for amounts paid to the homeowners, as well as for damages for breach of the subcontractor’s duties to procure specific insurance and to defend the developer against the homeowners’ claims. The subcontractor brought a motion for summary adjudication on the ground the developer’s claims were barred by the ten year statute of repose contained in Code of Civil Procedure Section 337.15.
The District Court agreed the developer’s claim for indemnity was barred by Section 337.15. And it held that because the damages recoverable for breach of the subcontractor’s duty to purchase insurance are identical to the damages recoverable through the developer’s indemnity claim, the breach of duty to procure insurance claim also was time-barred. The District Court, however, allowed the claim for breach of the duty to defend to proceed. The categories of losses associated with such a claim (attorneys’ fees and other defense costs) are distinct from the damages recoverable through claims governed by Section 337.15 (latent deficiency in the design and construction of the homes and injury to property arising out of the latent deficiencies).
2. UDC — Universal Development v. CH2M Hill, 181 Cal. App. 4th 10 (6th Dist. Jan. 2010)
Indemnification clauses in construction agreements often state that one party to the agreement — the “indemnitor” — will defend and indemnify the other party from particular types of claims. Of course, having a contract right to a defense is not the same as actually receiving a defense. Any indemnitor attempting to avoid paying for defense costs can simply deny the tender of defense with the hope that when the underlying claim is resolved the defense obligations will be forgotten. In the past, when parties entitled to a defense — the “indemnitees” — had long memories and pressed to recover defense costs, indemnitors attempted to justify denying the tender by claiming their defense obligations coincided with their indemnity obligations and neither arose until a final determination was made that the underlying claim was one for which indemnity was owed.
Read the full story...
Reprinted courtesy of Candace Matson, Harold Hamersmith, and Helen Lauderdale, Sheppard Mullin Richter & Hampton LLP. Ms. Matson can be contacted at cmatson@sheppardmullin.com, Mr. Hamersmith can be contacted at hhamersmith@sheppardmullin.com, and Ms. Lauderdale can be contacted at hlauderdale@sheppardmullin.com.
Read the court decisionRead the full story...Reprinted courtesy of
BHA Has a Nice Swing: Firm Supports NCHV and Final Salute at 2017 WCC Seminar
May 03, 2017 —
CDJ STAFFBert L. Howe & Associates (BHA) is excited to announce the return of their very popular Sink a Putt for Charity at the 2017
West Coast Casualty Construction Defect Seminar. This year, participant’s efforts on the green will help benefit both the
National Coalition for Homeless Vets and
Final Salute. As in years past, sink a putt in the BHA golf challenge and win a $25 Amazon gift card, and for every successful putt made, BHA will make a $25 cash donation in the golfer’s name to be distributed equally between these two worthy organizations.
While at the booth, don’t forget to test out BHA’s industry leading data collection and inspection analysis systems. BHA has recently added video overviews to their data collection process, as well as next-day viewing of inspection data via their secured BHA Client Access Portal. Discover meaningful cost improvements that translate to reduced billing while providing superior accuracy and credibility. Also learn about BHA’s expanding market presence and full range of services in Texas, Florida, and across the Southeast United States.
Attendees can also enter to win Dodger baseball tickets or a new iPad Pro! Other BHA giveaways include USB charging blocks, pocket tape measures, multi-tools, LED flashlights, and foam stress balls.
For more information on the National Coalition for Homeless Vets, please visit: http://nchv.org/
To learn more about how Final Salute provides homeless women Veterans with safe and suitable housing, please visit: http://www.finalsaluteinc.org/
Read the court decisionRead the full story...Reprinted courtesy of
Focusing on Design Elements of the 2014 World Cup Stadiums
June 30, 2014 —
Beverley BevenFlorez-CDJ STAFFWhile Garret Murai on his California Construction Law blog admits that the construction of Brazil’s World Cup stadiums has been problematic (construction worker deaths, delays, and cost overruns), he focused on the design work: “…there’s no denying that the venues are stunning, and for a country known for its beauty as well as beauties (think the Girl From Ipanema), dare I say even sexy.”
For instance, Murai described the Estadio do Maracana (constructed in 1950 and renovated in 2013) as looking “a bit like the front of the USS Enterprise.” He goes onto explain how the stadium was originally constructed for the 1950 World Cup, and “famous” attendees include Frank Sinatra and the Pope.
Read the court decisionRead the full story...Reprinted courtesy of
Motion to Dismiss COVID Claim Granted in Part, Denied in Part
February 06, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's motion to dismiss the insured's claim for business losses due to COVID-19 was granted in part, denied in part. SRL v Zurich Am. Ins Co., 2022 U.S. Dist. LEXIS 210058 (N.D. Ill. Nov. 21, 2022).
Excelsior owned and managed the Westin Excelsior Rome, a luxury hotel in Rome. The hotel suffered business income losses with the onset of the pandemic.While the hotel was not forced to close, its bookings decreased to virtually nothing. The Excelsior's complaint alleged that the COVID-19 virus was present in and around the hotel as multiple guests and at least six employees tested positive for COVID-19. It further alleged that the virus attached to interior property and was in the air.
Excelsior was insured under a commercial property policy issued by Zurich. The court agreed there was no direct physical loss because no structure suffered damage. Among the coverages under the policy, however, was a "Cancellation of Bookings" provision. Zurich agreed there was coverage under this provision, but argued that Excelsior had already reached its annual limit for Cancellation of Bookings claims.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Harmon Tower Demolition on Hold
December 11, 2013 —
CDJ STAFFCityCenter has raised a scenario out of a blockbuster movie in which an earthquake causes the tower to fall onto the Cosmopolitan or the Crystals mall, leading to lawsuits, investigations, and “plummeting stock prices.” But that didn’t sway Clark County District Judge Elizabeth Gonzales from putting a hold on the demolition of the tower. FM Global, CityCenter’s insurer, has requested more time to examine the building’s problems in order to determine how to act on CityCenter’s claim of total loss.
Tutor Perini, the company that built the tower, agrees with the delay, since any monies from FM Global would reduce Tutor Perini’s liability. If FM Global denies the claim, the price for the builder would go up, should they fail at trial. That trial is now scheduled for April.
Read the court decisionRead the full story...Reprinted courtesy of
Consult with Counsel when Preparing Construction Liens
April 13, 2017 —
David Adelstein – Florida Construction Legal UpdatesAll too often entities prepare their own construction liens. Sure, it is an effective way to save a few bucks. No doubt about it. But, by doing so, you are (i) not relying on advice of counsel that is important when it comes to lien preparation and (ii) not relying on strategy that goes along with the preparation of a lien. When you are liening, the reason you are doing so is because you have not been paid. You therefore want to collateralize your nonpayment against the real property—the leverage of a construction lien. This is a very beneficial statutory tool if implemented correctly, so it only makes sense to do it “strategically” right.
A construction lien is a statutory form. So, how hard can it be? Filling out the “form” is not hard, however, there is legal significance to the information and amounts included in a lien. For instance:
- There is significance to the amount you are liening. Are you liening for disputed change order work? Are you liening for amounts unrelated to base contract work?
- There is significance to the final furnishing date. Are you liening within 90 days of performing base contract work unrelated to punchlist or warranty work?
- There is significance to date the Notice to Owner was served (if you are not in privity with the owner). Was the Notice to Owner served within 45 days of initial furnishing?
- There is significance to the legal description identified in the lien. Are you liening the right property based on the type of project you are working on?
- There can even be significance to the initial furnishing date. Assuming you are the general contractor, what was your initial furnishing date in comparison with when the Notice of Commencement was recorded? If you are not a general contractor, when was the initial furnishing date in comparison with when you served the Notice to Owner?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Mortar Insufficient to Insure Summary Judgment in Construction Defect Case
January 06, 2012 —
CDJ STAFFThe US District Court of Nevada issued a summary judgment in the case of R&O Construction Company V. Rox Pro International Group, Ltd. on December 19, 2011. The case involved the installation of stone veneer at a Home Depot location (Home Depot was not involved in the case). R&O’s subcontractor, New Creation Masonry, purchased the stone veneer from Arizona Stone. Judge Larry Hicks noted that “the stone veneer failed and R&O was forced to make substantial structural repairs to the Home Depot store.”
Rox Pro asked the court for a summary judgment, which the court granted only in part. The court looked at two issues in the case, whether the installation instructions constituted a breach of implied warranty of merchantability, and whether there was a breach of an implied warranty of fitness for a particular purpose.
Judge Hicks found that there was a breach of implied warranty of merchantability. The instructions drafted by Real Stone and distributed by Arizona Stone were not sufficient for affixing the supplied stones, according to R&O’s expert, a claim the plaintiffs dispute. “Because there is an issue of material fact concerning the installation guidelines, the court shall deny Arizona Stone’s motion for a summary judgment on this issue.”
On the other hand, the judge did not find that the instructions had any bearing as to whether R&O bought the stone, since the stone was selected by the shopping center developer. This issue was, in the view of the judge, appropriately dismissed.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Fatal Boston Garage Demolition Leaves Long Road to Recovery
April 04, 2022 —
Scott Van Voorhis - Engineering News-RecordMassachusetts' officials are bracing for a lengthy recovery process following the March 26 fatal collapse during demolition of a section of a hulking Brutalist-era parking garage in Boston. JDC Demolition was razing the Government Center structure to make way for a 410,000-sq-ft life-sciences complex, when a multistory portion near the top failed, killing 51-year-old operating engineer Peter Monsini.
Reprinted courtesy of
Scott Van Voorhis, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of