Wisconsin Supreme Court Holds Fire Damage Resulted from Single Occurrence
November 21, 2018 —
Brian Margolies - TLSS Insurance Law BlogIn its recent decision in Secura Ins. v. Lyme St. Croix Forest Co., LLC 2018 WI 103 (Oct. 30, 2018), the Wisconsin Supreme Court had occasion to consider whether a forest fire that caused damage to several homes and properties should be considered a single or multiple occurrences.
Secura insured Lyme St. Croix Forest Company under a general liability policy. Of relevance was the policy’s $500,000 sublimit of coverage for property damage due to fire arising from logging or lumbering operations, subject to a $2 million general policy aggregate limit. Lyme St. Croix sought coverage under the policy for a fire that resulted from its logging equipment. The fire lasted for three days, burning nearly 7,500 acres and causing damage to numerous homes and businesses.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Margolies, Traub Lieberman Straus & Shrewsberry LLPMr. Margolies may be contacted at
bmargolies@tlsslaw.com
HHMR Celebrates 20 Years of Service!
October 18, 2021 —
David M. McLain – Colorado Construction LitigationI remember it (almost) like it was yesterday. It was September of 2001, and I was a third-year associate at Long & Jaudon, practicing with the construction litigation group. After a long weekend away, I received word that the firm had just announced that it would cease providing legal services. Long & Jaudon, which formed in 1967, had been a stalwart of Colorado’s defense bar, counting among its number some of the finest and most well-respected defense attorneys in the state. To learn that the firm would be shutting its doors was devastating. I would be out of a job.
Soon after L&J’s announcement, Dave Higgins, one of that firm’s senior partners, inquired as to whether I would be interested in starting a new firm focused on supporting Colorado’s construction industry and its insurers. Instead of riding into the sunset of retirement, Dave wanted to leave a legacy. That legacy is Higgins, Hopkins, McLain & Roswell. Shortly after the sprout of the idea, I spent an afternoon at a picnic table in Cheesman Park with Dave Higgins, Steve Hopkins, and Sheri Roswell, sketching out an idea for a new law firm. Twenty years later, HHMR is still here, still serving Colorado’s construction industry and its insurers, and still embodying the principles of service and stewardship upon which the firm was founded.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
“Details Matter” is the Foundation in a Texas Construction Defect Suit
March 01, 2012 —
CDJ STAFFThe Court of Appeals of Texas has ruled in the case of Barzoukas v. Foundation Design. Mr. Barzoukas contracted with Heights Development to build a house. He subsequently sued Heights Developments and “numerous other defendants who participated in the construction of his house.” Barzoukas eventually settled with all but two defendants, one who went bankrupt and Foundation Design, the defendant in this case. In the earlier phase, Barzoukas made claims of “negligence, negligent misrepresentation, fraud, fraudulent inducement, conspiracy, and exemplary damages in connection with the foundation.”
Foundation Design had been hired to install 15-foot piers to support the foundation. The engineer of record, Larry Smith, sent a letter to Heights Development noting that they had encountered hard clay stone when drilling. Smith changed the specifications to 12-foot piers. Initially, the City of Houston called a halt to work on the home when an inspector concluded that the piers were too shallow. Heights Development later convinced the city to allow work to continue. Subsequently, experts concluded that the piers were too shallow.
Foundation Design filed a motion for summary judgment. The trial court granted this, “without specifying the basis for its ruling.” Barzoukas contends the court was in error. Foundation Design contends that “Barzoukas failed to proffer competent evidence establishing that their conduct proximately caused damages.” Further, they did not feel that Smith’s letter gave “rise to viable claims for fraud and fraudulent inducement.”
One problem the court had was a lack of evidence. The court noted that “the purported subcontract is entirely missing” in the pleadings. The court has no contract between Bazourkas and Heights Development, nor one between Heights Development and either Foundation Design or Smith. The court underscored the importance of this, writing, “details matter.” They found that “the details are largely missing here.” Without the contract, the court found it impossible to determine if “Smith or an entity related to him agreed to indemnify Heights Development for damages arising from Smith’s negligent performance.”
As the material facts are in dispute, the appeals court found that there were no grounds for a summary judgment in the case. “Pointing to the existence of a contract between Heights Development and Barzoukas, or to the existence of a subcontract, is the beginning of the analysis ? not the end.”
Foundation Design and Smith also claimed that Barzoukas’s expert did not proffer competent evidence and that the expert’s opinions were conclusory. The trial court did not rule on these claims and the appeals court has rejected them.
Finally, Barzoukas made a claim that the trial court should not have rejected his argument of fraud and fraudulent inducement. Here, however, the appeals court upheld the decision of the lower court. “Barzoukas did not present evidence supporting an inference that Smith or Foundation Design made a purposeful misrepresentation.
The court remanded the case to the trial court for reconsideration. One member of the panel, Judge Charles Seymore, upheld the entire decision of the trial court. He dissented with the majority, finding that the economic loss rule foreclosed the claim of negligence.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Who is Responsible for Construction Defect Repairs?
August 24, 2017 —
Laura Parsons-CDJ STAFFAn appellate court has ruled that the sponsor and not the condo board is responsible for repairing construction defects at 50 Madison Avenue, a multi-story apartment building in New York City across from Madison Square Park, Habitat reported. Plaintiff’s Simon and Ludmilla Lorne have brought upon three lawsuits in a legal battle lasting a decade.
The first came in 2007, two years after the Lorne’s purchased their $3 million seventh-floor apartment. At that time, the sponsor offered to repair the concrete slab under the hardwood floors that had not been properly leveled. However, the Lorne’s and the condo board disagreed about who and how the repairs would be accomplished. The second lawsuit wherein the court ruled that repairing the construction defects was the responsibility of the sponsor occurred in 2009. However, the Lorne’s sued the board yet again in 2015, citing failure to maintain and repair the building. Since the 2015 suit was based on the same allegations as the 2007 suit, it was dismissed by the judge.
Read the court decisionRead the full story...Reprinted courtesy of
On Rehearing, Fifth Circuit Finds Contractual-Liability Exclusion Does Not Apply
November 26, 2014 —
Tred R. Eyerly – Insurance Law HawaiiOn rehearing, the Fifth Circuit determined that the contractual-liability exclusion did not apply to bar coverage for damage caused by the insured contractor to the home it constructed. Crownover v. Mid-Continent Cas. Co., 2014 U.S. App. LEXIS 20727 (5th Cir. Oct. 29, 2014).The court withdrew its prior opinion, summarized here.
Arrow Development, Inc. contracted with the Crownovers to construct a home. The contract had a warranty-to-repair clause, which, in paragraph 23.1, provided that Arrow would "promptly correct work . . . failing to confirm to the requirements of the Contract Documents." After the Crownovers moved in, cracks began to appear in the walls and foundation of the home. Additional problems with the heating, ventilation, and air conditioning ("HVAC") caused leaking in the exterior lines and air ducts inside the home. To compensate for defects in the HVAC system, the system's mechanical units ran almost continuously in order to heat or cool the home. Because they were overburdened, the mechanical units had to be replaced. The Crownovers paid several hundred thousand dollars to fix the problems with the foundation and HVAC system.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Winners Announced in Seattle’s Office-to-Residential Call for Ideas Contest
July 10, 2023 —
Ryanne Mathisen - Ahlers Cressman & Sleight PLLCOn June 7, 2023, the City of Seattle announced three winners of its Office to Residential: Call for Ideas contest for which it received a total of 13 submissions. Hybrid Architecture, LLC, took first place; Gensler, Seattle Office Project Team took second; and the Miller Hull Partnership took third. Seattle’s Department of Construction and Inspections will study the submissions and determine what legislative and regulatory modifications would be necessary to support and further these proposals and other future office-to-residential conversion projects.
Seattle will also be holding a series of exhibitions over the coming weeks where project submissions will be available to the public. On June 14, 2023, from 5:30 PM to 7:30 PM, a reception will be hosted by the Seattle Architecture Foundation and the City at the American Institute of Architects. The gallery will also be open to the public from 10:00 AM to 5:00 PM on June 21, 28, and July 5. After June 14, 2023, those interested can access contest submissions at the
project website.
Seattle’s primary goal with this contest was to provide a vision for the future of downtown and begin charting a concrete path to getting there. Since working from home has become more common following the COVID-19 pandemic, vacancy rates in many office buildings have risen sharply, while housing availability and affordability remain ongoing issues. If Seattle can show a realistic—and profitable—path to converting commercial office spaces into residences, it would be addressing both problems, killing two birds with one stone.
Read the court decisionRead the full story...Reprinted courtesy of
Ryanne Mathisen, Ahlers Cressman & Sleight PLLCMs. Mathisen may be contacted at
ryanne.mathisen@acslawyers.com
Insurer Awarded Summary Judgment on Collapse Claim
January 06, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe Eleventh Circuit agreed with the insurer that there was no coverage for a collapse under the policy. S.O. Beach Corp. v. Great Am. Ins. Co.,2019 U.S. App. LEXIS 32569 (11th Cir. Oct. 31, 2019).
S.O. Beach Corporation and Larios on the Beach, Inc ("Larios") owned a building in Miami Beach. Sometime between march 4, 2012 and April 10, 2013, Larios discovered that parts of the first three floors of its building had caved in to varying degrees. The primary cause of the collapse was a wooden support beam that had severely rotted. Larios found a broken pipe that was gushing water onto the beam, causing deterioration. Larios was forced to evacuate the building until the damage was repaired.
Larios submitted a claim under its all-risk policy with Great American. The policy required that a collapse an "abrupt falling down or caving in of a building or any part of a building" to be covered. Before a coverage decision was made, Larios sued for breach of contract. The parties filed cross-motions for summary judgment. The district court granted Great American's motion and denied Larios' motion.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Wendel Rosen’s Construction Practice Group Receives “Tier 1” Ranking by U.S. News and World Reports
November 10, 2016 —
Garret Murai – California Construction Law BlogWendel Rosen’s Construction Practice Group has received a “Tier 1” ranking by U.S. News and World Reports in its 2017 Best Law Firms rankings and the firm as a whole has been named one of the “Best Law Firms.” This is the fourth consecutive year that Wendel Rosen’s Construction Practice Group has achieved a “Tier 1” ranking.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com