Michigan Court of Appeals Remands Construction Defect Case
February 14, 2022 —
Tred R. Eyerly - Insurance Law HawaiiAfter its prior decision holding there was no coverage for faulty workmanship was remanded by the Michigan Supreme Court, the Court of Appeals remanded to the trial court. Skanska United States Bldg. v. M.A.P. Mech. Contrs., 2021 Mich. App. LEXIS 7336 (Mich. Ct. App. Dec. 28, 2021). The post summarizing the Supreme Court decision is here.
Skanska USA Building was the construction manager on a renovation project at a medical center. Skanska subcontracted the heating and cooling portion of the project to defendant M.A.P. MAP held a CGL policy from Amerisure. Skanska and the medical center were named as additional insureds.
MAP installed a steam boiler and related piping for the heating system. When completed, the heating system did not function properly. MAP installed some of the expansion joints backwards, causing damage to concrete, steel, and the heating system.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Affirmed: Nationwide Acted in Bad Faith by Failing to Settle Within Limits
July 19, 2017 —
Bethany Barrese – Saxe Doernberger & Vita, P.C.The Eleventh Circuit recently affirmed that Nationwide acted in bad faith by refusing to settle a claim against its insured for the policy limits, exposing the policyholder to an excess verdict.1
The case arose out of a 2005 automobile accident where Seung Park, who was insured by Nationwide, struck and killed another driver, Stacey Camacho. Shortly after the accident, Ms. Camacho’s estate issued a time-limited demand for the full limits of the policy Nationwide issued to Mr. Park, $100,000, to settle the case. After the deadline to respond to the demand expired, Nationwide rejected the demand and made a counteroffer. A settlement could not be reached and a wrongful death suit was filed against Mr. Park, resulting in a massive jury verdict of $5.83 million.
Following the jury verdict, Mr. Park assigned his rights against Nationwide to Ms. Camacho’s estate, which then filed claims for negligence and bad faith failure to settle against Nationwide. The case was tried to a jury, which found in favor of the estate.
Read the court decisionRead the full story...Reprinted courtesy of
Bethany Barrese, Saxe Doernberger & Vita, P.C.Ms. Barrese may be contacted at
blb@sdvlaw.com
Property Insurance Exclusion: Leakage of Water Over 14 Days or More
July 10, 2018 —
David Adelstein - Florida Construction Legal UpdatesThe recent opinion of Whitley v. American Integrity Ins. Co. of Florida, 43 Fla.L.Weekly D1503a (Fla. 5th DCA 2018), as a follow-up to this article on the property insurance exclusion regarding the “constant or repeated seepage or leakage of water…over a period of 14 or more days,” is a beneficial opinion to insureds.
In this case, the insured had a vacation home. A plumbing leak occurred that caused water damage to the home. The plumbing leak occurred during a period of time that lasted approximately 30 days. For this reason, the property insurer denied the claim per the exclusion that the policy does not cover loss caused by repeated leakage of water over a period of 14 or more days from a plumbing system. Summary judgment was granted by the trial court in favor of the insurer based on this exclusion.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Architect Sues School District
November 20, 2013 —
CDJ STAFFSFL+A Architects is suing the Marlboro County, South Carolina School District over $690,000 that the architect claims is owed to it by the school district. The firm did design work for the Blenheim Elementary Middle School, which opened in January.
The architectural firm contends that the school district refused to pay for anything outside of basic services and failed to pay the full amount on those either.
Read the court decisionRead the full story...Reprinted courtesy of
UPDATE - McMillin Albany LLC v. Superior Court
June 05, 2017 —
Richard H. Glucksman, Glenn T. Barger, & David A. Napper - CGDRB News & PublicationsThe matter has been fully briefed since last year and the construction industry anxiously awaits the California Supreme Court's highly anticipated decision regarding McMillin Albany LLC v. Superior Court (2015) 239 Cal.App.4th 1132. Numerous amicus briefs have also been filed including one by the Association of Southern California Defense Counsel, with the immediate past president of the organization, CGDRB's Glenn T. Barger, Esq., listed as the attorney of record. The Supreme Court will consider the issue of whether the Right to Repair Act (SB800) is the exclusive remedy for all defect claims arising out of new residential construction sold on or after January 1, 2003, thereby resolving the split of authority presented by the Fifth Appellate District's holding in McMillin Albany, which outright rejected the Fourth Appellate District's holding in Liberty Mutual Insurance Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98, on this particular issue. Oral argument is still pending and CGDRB will continue to closely monitor the progress of this case. Stay tuned.
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard H. Glucksman,
Glenn T. Barger and
David A. Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Barger may be contacted at gbarger@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
New York Appellate Team Obtains Affirmance of Dismissal of Would-Be Labor Law Action Against Municipal Entities
August 12, 2024 —
Lewis Brisbois NewsroomNew York, N.Y. (July 11, 2024) - In Charlot v. City of New York, ___ A.D.3d ___, 2024 NY Slip Op 03161 (2d Dep’t 2024), New York Associate Dean Pillarella, a member of the Appellate Practice, recently obtained an affirmance of the lower court’s dismissal of the plaintiff’s action against the City of New York (“the City”) for failure to timely serve a notice of claim. New York Partner Meghan Cavalieri, a member of the Construction Practice, and her team authored and argued the initial motion to dismiss.
The plaintiff alleged to have sustained injuries as a result of a construction-site accident on December 8, 2020, on City-owned property in the course of the construction of a school by the New York City School Construction Authority. N.Y. General Municipal Law (“GML”) § 50-e(1)(a), requires service of a notice of claim within 90 days after the claim arises as a condition precedent to the commencement of a tort action. The plaintiff served no notice of claim until June 2021 and commenced an action in January 2022, alleging violations of N.Y. Labor Law §§ 240(1), 241(6), and 200. Given the plaintiff’s failure to comply with GML § 50-e(1)(a), Meghan and her team rejected the notices of claim as untimely. The plaintiff then moved for leave to deem the notices of claim timely served nunc pro tunc. In response, Meghan and her team opposed the motion and cross-moved to dismiss the action.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Anchoring Abuse: Evolution & Eradication
October 09, 2023 —
Tim Capowski & Chris Theobalt - Kahana FeldOver the past few years, the plaintiff bar has expanded its use of improper anchoring tactics. Historically, improper anchoring was seen as a risky tactic in which a plaintiff’s counsel would suggest an outrageous figure for pain and suffering during summation in the hope that the lay jury would either award it or split the difference (cut the suggested figure by half) and, either way, return an excessive or runaway verdict. Plaintiff counsel deployed the tactic infrequently through the turn of the century for fear of alienating the jury by appearing greedy.
Two interrelated factors happened to change this dynamic. First, the plaintiff bar worked extremely hard in the intervening years with great success to shed its “ambulance chaser” stereotype by marketing itself as the “protector of the vulnerable”. Second, with the rise in Reptile and punitive tactics spawned in part by the publication of the Reptile handbook, the plaintiff bar also discovered that juries were not alienated by outrageous anchors as long as they were preceded by Reptile commentary essentially to “prime” the jury to punish the defendant rather than compensate the plaintiff with its award.
This is not speculation. I recall sitting outside a courtroom with one of New York’s top plaintiff attorneys in 2006 during deliberations on a catastrophic personal injury trial, during which he conceded to me that he was worried he had asked the jury for too large a figure (it was not even eight figures). A decade later in 2016, that same attorney felt no trepidation in requesting nearly $100 million for a comparable injury. He fed the jurors a steady diet of Reptile tactics from start to finish and they dutifully awarded the requested figure. Our research confirms that this two-step strategy (Reptile + improper anchor) preceded every New York nuclear verdict returned from 2010-2022. The same is almost certainly true of most nuclear verdicts in other jurisdictions.
Reprinted courtesy of
Tim Capowski, Kahana Feld and
Chris Theobalt, Kahana Feld
Mr. Capowski may be contacted at tcapowski@kahanafeld.com
Mr. Theobalt may be contacted at ctheobalt@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Angels Among Us
June 21, 2024 —
Maggie Murphy - Construction ExecutiveIn the early morning hours of March 26, 2024, an outbound cargo ship in the Port of Baltimore unexpectedly lost power as it churned toward the Francis Scott Key Bridge. Authorities had just minutes to stop vehicular traffic before the massive vessel—985 feet long and 157 feet wide, nearly as tall as the Eiffel Tower if stood on end—crashed headlong into one of the bridge’s support piers. Quick-acting dispatchers were able to stop the flow of traffic in time, but overnight work crews filling potholes on the bridge didn’t have enough warning. Six workers lost their lives when the bridge collapsed.
On top of bringing immense grief, construction fatalities can be financially devastating to the surviving families. Enter Construction Angels, a nonprofit that provides financial assistance, grief counseling and scholarships to families of fallen construction workers. When founder Kristi Ronyak first heard news of the Key Bridge collapse, she immediately jumped into action. “We started getting calls just hours after the crash,” Ronyak says. “When I first heard the news, my heart sank, and I just started crying.