Utah Supreme Court Allows Citizens to Block Real Estate Development Project by Voter Referendum
June 10, 2019 —
Sean M. Mosman & Mark O. Morris - Snell & Wilmer Under ConstructionThe Utah Supreme Court recently decided Baker v. Carlson, 2018 UT 59, which considered a developer’s ongoing effort to build a mixed-use, part-residential and part-commercial development on the site of the long-defunct Cottonwood Mall located in Holladay, Utah. On November 28, 2018, the Supreme Court affirmed the Third District Court’s ruling that a voter referendum to block the development was valid. This ruling calls into question the certainty of investment-backed real estate decisions in Utah and thus could carry negative implications for the Utah construction and real estate development communities.
The Cottonwood Mall opened in the early 1960s, and for several decades was a popular regional shopping destination. But the mall fell on financial hard times in the mid-1990s, and since 2007 the 57-acre lot has sat vacant. Around that time, the owner of the lot made plans to redevelop it, and asked Holladay City to rezone the site to permit mixed uses. In response, the City rezoned the lot as Regional/Mixed-Use (R/M-U). The City also created a process to control the development of an R/M-U zone, requiring prospective builders to first submit a site development master plan—which sets forth guidelines for the overall development and design of the site—to the City for approval. After the City approves a master plan, the developer must enter into a development agreement with the City, giving the developer certain rights and addressing other development-related issues.
Reprinted courtesy of
Sean M. Mosman, Snell & Wilmer and
Mark O. Morris, Snell & Wilmer
Mr. Mosman may be contacted at smosman@swlaw.com
Mr. Morris may be contacted at mmorris@swlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Golden State Commits to Going Green – Why Contractors Will be in High Demand to Build the State’s Infrastructure
November 28, 2018 —
Karla Pascarella & Alexa Magrath - Peckar & Abramson, P.C.On September 10, 2018 California’s Governor took an ambitious stance on environmental policy and signed Senate Bill 100 (“SB100”). The bill accelerates several Renewables Portfolio Standards (“RPS”) deadlines previously established by former Governor Arnold Schwarzenegger. The bill’s most notable effect—it requires that 100 percent of California’s electricity come from renewable and zero-carbon sources by 2045. California is the second state in the nation to pass such legislation; Hawaii passed a similar bill in 2015.
The passage of this bill could not be timelier as wildfires, drought, and record high temperatures continue to make national headlines. California, as it often does, has taken a contrarian position as the federal government attempts to reinvigorate the coal mining industry in America. Coal and other fossil fuels used to produce energy increase air pollution and deplete necessary ozone. California has been experimenting and utilizing renewable energy technology since as early as 1997. According to the California Energy Commission, by the end of 2017 California generated approximately 32 percent of its energy from renewable sources.
Reprinted courtesy of
Karla Pascarella, Peckar & Abramson, P.C. and
Alexa Magrath, Peckar & Abramson, P.C.
Ms. Pascarella may be contacted at kpascarella@pecklaw.com
Ms. Magrath may be contacted at amagrath@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Jobsite Safety Should Be Every Contractors' Priority
December 09, 2019 —
Ray Reese - Construction ExecutiveAny general contractor understands the range of factors that go into building and sustaining a successful jobsite: hiring the right team, maintaining cutting-edge equipment, ensuring constant communication with clients and effectively leveraging the newest building technologies, just to name a few.
But any good general contractor understands that there is one factor that should always be considered as top priority: jobsite safety.
The health and wellbeing of a project’s team is paramount for obvious reasons, and it isn’t a lighthearted matter. Injuries and fatalities have too often been a piece of our industry’s story. In 2017 alone, there were 971 reported deaths on construction sites, which accounted for 20% of total worker fatalities, according to a report from the Occupational Safety and Health Administration. Of these 971 fatalities, 582 were the result of construction’s “fatal four”—falls, workers being struck by objects, electrocutions and workers being caught between equipment. For members of the industry, these are difficult numbers to read and to process; yet, it is extremely important to consider the injuries and lives lost when we take into consideration the seriousness of jobsite safety.
Often, general contractors’ and superintendents’ greatest challenge isn’t being convinced of the necessity of jobsite safety practices in protecting employees or the value of safety in creating a productive work environment. Instead, the focus should be providing industry leaders tips on exactly how to improve safety measures on their own jobsites. Understanding that safety is everyone’s responsibility is paramount.
Reprinted courtesy of
Ray Reese, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Reese may be contacted at
rreese@rives.com
Why Construction Law- An Update
May 07, 2015 —
Christopher G. Hill – Construction Law MusingsBack in 2009, only a year or so after my first post here at Musings, I posted on why I’m in the field of construction law. Well, a lot has happened in the over 5 years since then, not the least of which is my move to solo practice in July of 2010 and the later certification as a mediator. As I sit here, I look back at the passage of time and the events between my last thoughts on this subject and now and wonder if my thoughts have changed?
Frankly, not much has changed as far as my attitude toward the practice of construction law. Despite my kids occasionally rolling their eyes when I talk about a case of interest to me and their sometimes moniker for me as a “dirt lawyer,” I continue to find the representation of the construction professionals that I call clients and friends to be fulfilling and worthwhile. Even in the face of criticisms that we lawyers cause more problems that we solve, I firmly believe that I and other good construction lawyers can and do help avoid and anticipate more problems than I cause.
As one of the few solo construction attorneys here in the Richmond area, if anything, I am more involved in the construction community. Between my continued and even increased involvement with the AGC of Virginia and my more recent appointment to the board of the Virginia State Bar‘s Construction Law and Public Contracts Section, I have gained even more insight into the workings of the legal and business landscapes of construction. With each new piece of information gained by such involvement, I see another side to the business of construction that I may not have thought of.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Construction Law MusingsMr. Hill may be contacted at
chrisghill@constructionlawva.com
FHFA’s Watt Says Debt Cuts Possible for Underwater Homeowners
February 05, 2015 —
Clea Benson – Bloomberg(Bloomberg) -- Fannie Mae and Freddie Mac’s overseer wants to allow debt cuts for a narrow group of borrowers who owe more than their homes are worth. The trick is figuring out a way to do it without incurring costs for taxpayers.
Federal Housing Finance Agency Director Melvin L. Watt told reporters Wednesday that he is still studying the idea of reducing principal on properties with depressed values, a step backed by housing advocates and Democratic lawmakers.
Read the court decisionRead the full story...Reprinted courtesy of
Clea Benson, Bloomberg
Stuck in Seattle: The Aggravating Adventures of a Gigantic Tunnel Drill
April 01, 2015 —
Karen Weise – BloombergAbout 20 workers wearing hard hats and reflective vests clump together on the edge of a chasm near Seattle’s waterfront, peering down a hole 120 feet deep and 83 feet wide. The last men have been craned out of the pit in a yellow metal cage. Gulls squawk. A TV news helicopter hovers overhead.
A dozen journalists stand nearby on the bed of a truck. We’re here to see Bertha, one of the world’s biggest tunneling machines. Or at least a piece of her. A 240-foot crane is about to haul a 540,000-pound steel shield out of the ground, 20 months after Bertha started digging a highway. Almost imperceptibly, the crane starts rising.
The event, on a Thursday in mid-March, is part of a massive rescue mission to fix the $80 million machine. She broke abruptly in December 2013 after boring through just 1,000 feet, one-ninth of her job. Her seals busted, and her teeth clogged with grit and pieces of an 8-inch steel pipe left over from old groundwater tests. She stopped entirely.
Read the court decisionRead the full story...Reprinted courtesy of
Karen Weise, BloombergMs. Weise may be contacted at
kweise@bloomberg.net
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
Resolve to Say “No” This Year
January 26, 2016 —
Christopher G. Hill – Construction Law MusingsWe hear all of the time how to “get to ‘yes'” and how doing so can lead to more business and of course more business leads to more profits. Purely logical, right? Without construction owners with work for general contractors to perform and general contractors hiring subcontractors to perform that work, construction grinds to a halt and clients and friends of mine in the construction industry don’t make money. For this to happen, “yes” has to happen more often than not. So, why the title of this post?
Chalk it up to spending much if not all of my time as a construction attorney either anticipating or dealing with the Murphy’s Law ruled nature of the construction world or to the “Monday morning quarterback” nature of my profession, but I see numerous instances where not taking the job or signing the bad contract would have led to a better outcome than performing the work. What do I mean by this? I mean that as a construction company (particularly one that is lower down the “payment chain” and therefore less in control of the flow of money), you need to carefully evaluate not only the contract presented, but whether you get a good feeling about the party with whom you are contracting.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com