Protecting and Perfecting Your Mechanics Lien when the Property Owner Files Bankruptcy
June 19, 2023 —
William L. Porter - Porter Law GroupIntroduction/Overview of the Mechanics Lien Law
The California mechanics lien is a powerful tool for contractors, subcontractors and materials suppliers to secure payment of unpaid construction debts. A contractor, subcontractor or materials supplier is allowed to record a mechanics lien on real property, based on the value added to the property by the claimant during the construction process.
The recorded mechanics lien provides the claimant with legal right to force the sale of the improved real property and thereby obtain the funds necessary to pay the delinquent debt. Under the usual procedure, the first step is the recording of mechanics lien with County Recorder’s office in the County where the property is located. A lawsuit to foreclose on the lien must then be filed in the County Superior Court of that County, within ninty (90) days after the mechanics lien is recorded. The goal of the lawsuit is to obtain a judgment for foreclosure on the mechanics lien by way of a forced sale of the property. The net proceeds of the sale will be used to pay the unpaid construction debt secured by the recorded mechanics lien, assuming that sale proceeds exceed the amount of senior liens and encumbrances.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
How Fort Lauderdale Recovered a Phished $1.2M Police HQ Project Payment
May 13, 2024 —
Richard Korman - Engineering News-RecordJan. 25th was a happy day for the city of Fort Lauderdale, Fla., as Mayor Dean Trentalis and Police Chief William Schultz announced in a press conference the recovery of a $1.162-million electronic payment meant for Moss Construction that had been stolen in September via an email phishing fraud.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
SE 2050 Is In Quixotic Pursuit of Eliminating Embodied Carbon in Building Structures
January 23, 2023 —
Nadine M. Post - Engineering News-RecordWalking to work one November morning, structural engineer Chris Jeseritz was buoyed by a Nelson Mandela quotation on a digital sign on the side of a Seattle office tower: “A winner is a dreamer who never gives up.”
Reprinted courtesy of
Nadine M. Post - Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
St. Mary & St. John Coptic Orthodox Church v. SBS Insurance Services, Inc.
January 18, 2021 —
Michael Velladao - Lewis BrisboisIn St. Mary & St. John Coptic Orthodox Church v. SBS Insurance Services, Inc., ----Cal.App.5th--- (November 23, 2020), the California First District Court of Appeal reversed the trial court's entry of judgment in favor of SBC Insurance Services ("SBC") regarding a claim for water damage sustained by a residence owned by St. Mary & John Coptic Church ("St. Mary") under property coverage afforded by a policy issued by Philadelphia Indemnity Insurance Company ("Philadelphia"). The policy was procured by SBC on behalf of St. Mary. Philadelphia denied coverage of the claim based on the vacancy exclusion in its policy, but entered into a settlement and loan receipt agreement, whereby St. Mary gave Philadelphia the right to control litigation in St. Mary’s name against SBC or third parties who might be liable for the loss in exchange for a loan of money to repair and remediate the damage sustained by the residence. The loan was to be repaid out of any recovery made against SBC or third parties. After a bench trial, the trial court found in favor of SBC and held that the vacancy exclusion was ambiguous. Essentially, the exclusion did not apply to the time period prior to the time St. Mary purchased the residence, such that the 60-day vacancy requirement could not be satisfied. The trial court reasoned that since St. Mary did not have an insurable interest in the property before it purchased the property, the 60-day requirement did not include the period before such residence was purchased and St. Mary held an insurable interest.
The parties’ dispute arose of out of the Pope of the Coptic Church requesting St. Mary to purchase a home to be used as his papal residence in the Western United States. St. Mary also intended to use the home as a residence for visiting bishops. The home was purchased on May 28, 2015. As part of the purchase, SBC placed the home under St. Mary’s commercial policy, rather than purchasing a separate homeowner’s policy for the residence. Subsequently, the home sustained water damage due to a broken pipe. The water damage was discovered on July 24, 2015, 57 days after the inception of the Philadelphia policy and the loss. St. Mary tendered the property loss to Philadelphia, which denied coverage of the claim based on the reasoning that the home had been vacant for 60 consecutive days prior to the loss. Subsequently, St. Mary filed suit against SBC after securing the loan receipt agreement with Philadelphia based on the argument that the vacancy exclusion barred coverage of the claim and SBC breached its duty of care by not securing the proper coverage of the home. The trial court entered judgment in favor of SBC finding that the vacancy exclusion did not apply to bar coverage of the loss, such that SBC did not breach its duty of care owed to St. Mary as its broker.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Velladao, Lewis BrisboisMr. Velladao may be contacted at
Michael.Velladao@lewisbrisbois.com
Arizona Supreme Court Clarifies Area Variance Standard; Property Owners May Obtain an Area Variance When Special Circumstances Existed at Purchase
October 19, 2017 —
Nick Wood, Adam Lang, Noel Griemsmann, & Brianna Long – Snell & Wilmer Real Estate Litigation BlogIn Pawn 1st v. City of Phoenix, the Arizona Supreme Court rejected a Court of Appeals rule that would have unduly restrained alienation of property in Arizona. The Court of Appeals found that the City of Phoenix Board of Adjustment acted beyond its authority when it granted an area variance to a pawn shop where the special circumstances causing a need for the variance existed before the pawn shop purchased the property. Under Arizona law, boards of adjustment cannot grant an area variance where the special circumstances requiring the variance are self-imposed. The Court of Appeals adopted a rule that knowledge of special circumstances at the time of purchase made the special circumstances self-imposed, foreclosing the purchaser’s ability to obtain a variance. This rule would have severely restricted property purchasers’ ability to obtain area variances in Arizona and by extension likely strained property transactions.
The underlying case involved a pawn shop that was proposed in southeast Phoenix. After the property purchaser obtained approval for a required use permit (for a pawn shop) and a variance (for a 500 foot residential setback) from the City of Phoenix Board of Adjustment, a competing pawn shop filed a special action arguing that the variance was a use variance, not an area variance, beyond the board of adjustment’s authority.
Reprinted courtesy of Snell & Wilmer attorneys
Nick Wood,
Adam Lang,
Noel Griemsmann and
Brianna Long
Mr. Wood may be contacted at nwood@swlaw.com
Mr. Lang may be contacted at alang@swlaw.com
Mr. Noel may be contacted at ngriemsmann@swlaw.com
Ms. Brianna may be contacted at bllong@swlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
When is a “Notice of Completion” on a California Private Works Construction Project Valid? Why Does It Matter for My Collection Rights?
January 27, 2020 —
William L. Porter - Porter Law GroupWhat is a Notice of Completion?
A “notice of completion” is a document recorded by the owner of property where construction work was performed. Specifically, it is recorded at the Office of the County Recorder in the County where the work was performed. The notice of completion tells the world at large that the construction project is complete. It also triggers the deadlines for those who have not been paid to make their claims for payment.
Is an Owner of a California Private Works Project Required to Record a Notice of Completion?
No, there is no requirement that an owner of a California private works construction project record a Notice of Completion. However, there are consequences which depend on whether an Owner elects to record the notice or not.
For My Collection Rights, Why Does it Matter Whether a Notice of Completion Has Been Recorded?
The date of recording of a valid notice of completion sets the deadline for those who have not been paid for work performed and materials supplied to a California construction project to pursue such important collection remedies as the “mechanics lien”, the “stop payment notice” and the “payment bond claim.” These are very powerful collection remedies for those who have not been paid. If the deadline to pursue these remedies is missed by a claimant, then the claimant’s right to pursue these remedies is also missed. One of these remedies, the mechanics lien, will enable the claimant to sell the owner’s property where the work was performed in order to get paid.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Insurer Must Defend Insured Against Construction Defect Claims
November 14, 2018 —
Tred R. Eyerly - Insurance Law HawaiiFinding various exclusions inapplicable, the Federal District Court ruled that the insurer owed a defense to the general contractor based upon Texas law. Mt. Hawley Ins. Co. v. Slay Engineering, 2018 U.S. Dist. LEXIS 139363 (W.D. Texas Aug. 15, 2018).
Huser Construction had a CGL policy issued by Mt. Hawley Insurance Company. Huser contracted to design and construct a municipal sports complex with the City of Jourdanton. The project consisted of four baseball fields, a softball field, parking lots and swimming pool. Huser subcontracted with Cody Pools, Inc. to design and build the swimming pool. Huser also subcontracted with Q-Haul, Inc. to perform earth work, grading and storm drainage work at the site.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Domtar Update
June 11, 2014 —
Robert M. Caplan – White and Williams LLPOn May 29, 2014, the Pennsylvania Supreme Court granted allocatur—i.e., the permission to appeal—in the controversial subrogation case, Liberty Mutual Ins. Co. v. Domtar Paper Co., 77 A.3d 1282 (Pa. Super. Ct. 2013). In its order granting the relief to Liberty Mutual, a workers’ compensation insurer, the Supreme Court set forth the narrow issue to be decided on appeal: “Does Section 319 of the Pennsylvania Workers’ Compensation Act, 77 P.S. § 671, allow the employer/insurer to step into the shoes of the insured employee to subrogate against the tortfeasor?”
In Domtar, Liberty Mutual was caused to incur approximately $35,000 in compensation benefits which it paid on behalf of George Lawrence, an employee of Liberty Mutual’s insured, for injuries he sustained in a work-related accident. Mr. Lawrence chose not to file an independent personal injury lawsuit. As a result, in order to recover its lien interests, Liberty Mutual sued the third parties responsible for causing Mr. Lawrence’s work-related injuries directly, having become subrogated to the rights of Mr. Lawrence by virtue of Liberty Mutual’s workers’ compensation expenditure on his behalf.
Read the court decisionRead the full story...Reprinted courtesy of
Robert M. Caplan, White and Williams LLPMr. Caplan may be contacted at
caplanr@whiteandwilliams.com