Florida Court Gives Parties Assigned a Subrogation Claim a Math Lesson
August 04, 2021 —
Lian Skaf - The Subrogation StrategistAlthough the focus of most subrogation cases is usually on proving liability, determining the appropriate measure of damages is just as important. Sometimes turning on a nuanced argument for recoverability, an adverse holding can significantly boost or reduce the total damages in a case. The Court of Appeal of Florida, Fourth District (Court) recently decided such an issue in a case involving subrogation, holding that the defendants owed much more than they originally anticipated.
In Five Solas v. Ram Realty Servs., No. 4D19-2211 2021, 2021 Fla. App. LEXIS 7546, the Court reviewed the appropriate setoff in damages that the defendants were entitled to when measuring the recoverable damages. The Court reversed the lower court’s holding, which held that the defendants were entitled to a setoff that limited the jury’s award to $104,481.75. Instead the Court held that the defendants were only entitled to a setoff equal to the excess recovery over replacement cost.
The case involves, among other things, property damage sustained by building owner Five Solas (Owner) and its lessee William Price, P.A. from a collapsed wall originating from the property of the defendants, Ram Realty Services, LLC and Sodix Fern, LLC d/b/a Alexander Lofts (collectively referred to as Defendants). Owner’s carrier, Foremost Insurance Company (Foremost), paid out its policy limit of $430,518.25 to Owner for damage to the building. Owner then pursued its claim against the tortfeasors for the remaining damages not paid by its carrier.[1] Foremost also pursued a subrogation claim, but settled its subrogation claim with Defendants, assigning its subrogation rights to Defendants.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
Appreciate The Risks You Are Assuming In Your Contract
February 10, 2020 —
David Adelstein - Florida Construction Legal UpdatesAPPRECIATE THE RISKS YOU ARE ASSUMING IN YOUR CONTRACT. Otherwise, those risks will come back and bite you in the butt. This language is not capitalized for naught. Regardless of the type of contract you are entering into, there are risks you will be assuming. You need to appreciate those risks because there may be insurance you can obtain to cover that risk.
For instance, exculpatory provisions (or get-out-of-jail provisions) in contracts are enforceable if they are unambiguous. “Such provisions are deemed to be unambiguous and enforceable when the language unequivocally demonstrates a clear and understandable intention for the defendant to be relieved from liability such that an ordinary and knowledgeable person will know what he or she is contracting away.” Pillay v. Public Storage, Inc., 44 Fla.L.Weekly D2744c (Fla. 4th DCA 2019).
An example of an exculpatory provision can be found in the public storage rental contract found in Pillay that read:
(1) ALL PERSONAL PROPERTY IS STORED BY OCCUPANT AT OCCUPANT’S SOLE RISK.
(2) Owner and Owner’s agents . . . will not be responsible for, and Tenant releases Owner and Owner’s agents from any responsibility for, any loss, liability, claim, expense, damage to property . . . including without limitation any Loss arising from the active or passive acts, omission or negligence of Owner or Owner’s agents.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Developer Transition – Washington DC Condominiums
June 29, 2017 —
Nicholas D. Cowie - Maryland Condo Construction Defect Law BlogDeveloper transition is the process by which governance over a condominium unit owners’ association (“condominium association”) is transferred from condominium developer to unit owner control. Below is an overview of the legal requirements in the District of Columbia that govern this transition process as well as a “transition checklist” for unit owner-elected boards of directors that have recently transitioned from developer control.
TRANSITION LAW OVERVIEW
PERIOD OF DEVELOPER CONTROL
A developer initially controls a condominium association because it owns all unsold units in the newly created condominium. As such, the condominium developer has the controlling votes associated with majority ownership and can appoint its own employees as the initial members of the board of directors and thereby control how the association conducts its affairs. This is referred to as the “period of developer control,” during which the condominium developer makes all decisions on behalf of the condominium association.
The developer also creates a condominium association’s governing documents allowing it to dictate, subject to applicable law, the procedures and time periods under which control over the association’s board of directors is ultimately transferred to the unit owners.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas D. Cowie, Cowie & Mott, P.A.Mr. Cowie may be contacted at
ndc@cowiemott.com
Faulty Workmanship Exclusion Does Not Bar Coverage
November 18, 2011 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined that the Faulty Workmanship Exclusion only barred coverage for damages arising from problems with the property under construction itself and not to losses incurred to correct damage from accidents during construction. See 1756 First Associates, LLC v. Continental Casualty Co., 2011 U.S. Dist. LEXIS 117100 (S.D.N.Y. Oct. 3, 2011).
A tower crane collapsed at the construction site, causing damage. First Associates tendered the claim to its insurer, Continental. Continental reimbursed First Associates for certain costs arising from damage to and cleanup of the construction site and building stemming from the crane collapse. Continental refused, however, to reimburse First Associates for costs associated with construction delays resulting from the collapse.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
County Sovereign Immunity Invokes Change-Order Ordinance
December 20, 2017 —
Lizbeth Dison - AHC Contruction Law BlogThe recent case of Fulton County v. Soco Contracting Company, Inc. addresses two very interesting questions for local government attorneys. First, can a county ordinance bolster a defense of sovereign immunity against a contractor’s claims? Second, can a county waive sovereign immunity by failing to respond to Requests for Admission?
Facts:
County hired Contractor to construct a facility near the airport. The contract provided that change orders must satisfy a county ordinance, which required approval by the Board of Commissioners. But in emergency situations, the County Manager could approve change orders, as long as the contractor executes a proposed modification and the purchasing agent approves it.
The project suffered substantial delays, which Contractor attributed to weather, design delays, delays by the County in providing decisions on changes, and delays in obtaining permits during the federal government’s shutdown. As a result of these issues, Contractor comes County changed the scope of the contract. Contractor asserted claims against County for the delays and the changes to the work. The appellate opinion addresses the change order claims.
Read the court decisionRead the full story...Reprinted courtesy of
Lizbeth Dison, Autry Hall & Cook, LLP
Brown and Caldwell Team with AECOM for Landmark Pure Water Southern California Program
May 15, 2023 —
Brown and CaldwellLOS ANGELES, May 09, 2023 — A joint venture of AECOM and Brown and Caldwell (AECOM-BC Team) has been chosen to provide program and project management support and engineering design services for the
Pure Water Southern California program, one of the largest water reuse programs in the world.
The innovative program, being developed by the Metropolitan Water District of Southern California (Metropolitan) in partnership with the Los Angeles County Sanitation Districts (Sanitation Districts), will produce up to 150 million gallons of high-quality, purified water per day for up to 15 million people.
Anticipated for water delivery by 2032 and potentially earlier, the program will reuse the largest untapped wastewater source in the region that currently flows to the ocean to increase water resiliency, enhance water quality, and fuel economic growth. It will lower Southern California’s reliance on imported water supplies from the Colorado River and Sierra Nevada and replenish groundwater basins while leveraging cutting-edge research and development to increase regional water reuse.
About Brown and Caldwell
Headquartered in Walnut Creek, California, Brown and Caldwell is a full-service environmental engineering and construction services firm with 52 offices and over 1,900 professionals across North America and the Pacific. For more than 75 years, our creative solutions have helped municipalities, private industry, and government agencies successfully overcome their most challenging water and environmental obstacles. As an employee-owned company, Brown and Caldwell is passionate about exceeding our clients’ expectations and making a difference for our employees, our communities, and our environment. For more information, visit www.brownandcaldwell.com
Read the court decisionRead the full story...Reprinted courtesy of
Update Relating to SB891 and Bond Claim Waivers
June 10, 2015 —
Christopher G. Hill – Construction Law MusingsSeveral bills were passed and will go into effect on July 1, 2015 that affect the construction industry here in Virginia. The most interesting of these was an amendment to the mechanic’s lien statutes relating to waivers of lien rights.
As I posted in March, SB891 amended the mechanic’s lien statute, Va. Code Section 43-3, to remove proactive waivers of lien and bond rights. This bill has been signed into law with a minor modification.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Affirmed: Insureds Bear the Burden of Allocating Covered Versus Uncovered Losses
September 28, 2017 —
C. Lily Schurra & K. Alexandra Byrd – Saxe Doernberger & Vita, P.C.The Second Circuit recently affirmed a district court decision that an insured bears the burden of establishing what portion of a jury verdict constitutes covered damages1.
The case arose out of claims for property damage resulting from construction defects in a homebuilding project. The homeowners fired the construction manager, J. Barrows, Inc. (“JBI”), who then sued the homeowners in state court for unpaid fees (the “Underlying Action”). The homeowners counterclaimed, alleging breach of contract and negligence. JBI’s commercial general liability insurer, Harleysville Worcester Insurance Company (“Harleysville”), agreed to defend JBI under a reservation of rights.
Reprinted courtesy of
C. Lily Schurra, Saxe Doernberger & Vita, P.C. and
K. Alexandra Byrd, Saxe Doernberger & Vita, P.C.
Ms. Schurra may be contacted at cls@sdvlaw.com
Ms. Byrd may be contacted at kab@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of