"Abrupt Falling Down of Building or Part of Building" as Definition of Collapse Found Ambiguous
October 23, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court predicted the California Supreme Court would find the definition of collapse, calling for the abrupt falling down or caving in of a building or part of a building, to be ambiguous. Hoban v. Nova Cas. Co., 2018 U.S. Dist. LEXIS 139116 (N.D. Cal. Aug. 15, 2018).
The insureds' bowling center had two roof trusses that helped support the roof. The truss failures caused the building ceiling, overhead monitors, and disco ball to drop approximately six to ten inches, and also caused ceiling tiles and a layer of insulation to fall from the ceiling. A general contractor, named Tom Powers, and the county building inspector inspected the damage. The building inspector immediately ordered the business closed until necessary repairs could be completed. Powers was hired to shore up the roof support system to prevent a complete collapse. Thereafter, the insureds were able to re-open the bowling alley.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Drastic Rebuild Resurrects Graves' Landmark Portland Building
September 14, 2020 —
Nadine M. Post - Engineering News-RecordFifteen minutes into a 105-minute job interview for the $195-million overhaul of the long-troubled Portland Public Service Building in Oregon’s largest city, owner’s rep Mike Day threw a curve ball to the unwitting design-build team of Howard S. Wright Construction Co. and architect DLR Group. Already hard at work solving Day’s first faux crisis scenario—a budget buster that threatened the viability of the makeover of the notoriously dysfunctional landmark—they had to regroup.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Is Solar the Next Focus of Construction Defect Suits?
June 28, 2013 —
CDJ STAFFThere’s been a rapid growth in the sale of solar panels, and that’s lead some industry observers to wonder if manufacturers have been cutting back on quality. Current use of solar is six times what it was in 2008, with more than forty percent of that in the last year. The growth shows no sign of stopping, either. The Solar Energy Industry Association expects the amount of power generated by solar to increase by more than two-thirds in 2013.
With the oversupply, some fear that companies are relaxing their quality control. The New York Times found that there were widespread problems of defective units in solar cells, chiefly those manufactured in China. The Times article noted that at two solar plants in Spain, defect rates reached 34.5 percent.
Some industry observers disagree. The Insurance Journal quoted Andy Klump, the CEO of Clean Energy Associates, a Shanghai firm that provides quality assurance in the solar industry, who said that if a business had a 34 percent failure rate, “they would be out of business in a heartbeat.” Mr. Klump described the Times article as “not realistic.”
If the Times is right, Scott Turner, a construction insurance attorney, feels that the industry should ready itself for “a wave of large lawsuits.” Turner feels that “this litigation wave could make the battles over liability and insurance coverage for Chinese drywall seem like a small claims dispute.”
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Housing Starts Top Forecast on Single-Family Homes
December 17, 2015 —
Victoria Stilwell – BloombergNew-home construction in the U.S. rebounded in November, led by gains in single-family dwellings that signal the residential real estate industry will continue to support growth in the world’s largest economy.
Housing starts climbed 10.5 percent to a 1.17 million annualized rate from a 1.06 million pace in October, figures from the Commerce Department showed Wednesday in Washington. The median estimate of 81 economists surveyed by Bloomberg was for a 1.13 million rate. Work began on the most stand-alone houses since January 2008, and permits for similar projects reached an eight-year high.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, Bloomberg
DC Circuit Issues Two Important Clean Air Act and Administrative Law Decisions
December 16, 2019 —
Anthony B. Cavender - Gravel2GavelThe U.S. Court of Appeals or the District of Columbia has recently issued two important rulings on the Clean Air Act in particular and administrative law in general: California Communities Against Toxics, et al., v. EPA and Murray Energy Corporation v. EPA.
The Battle of the Memos: Seitz Makes Way for Wehrum
In the California Communities case, decided on August 20, 2019, the court held, in a 2 to 1 decision, that a petition to review a change in EPA policy announced in an agency memorandum which reversed an agency policy announced nearly 25 years ago in another agency memo must be rejected because the memo at issue was not a “final agency action” subject to the Administrative Procedure Act (APA). In 1995, the “Seitz Memo,” which interpreted Section 112 of the Clean Air Act and addresses the regulation and control of hazardous air pollutants from stationary sources, stated that once a source of toxic emissions is classified as “major,” the facility remains subject to regulation as a major source even if the facility makes changes to the facility to limit its potential to emit such toxics below the major source threshold. Then, in 2018 under a new administration, the “Wehrum Memorandum” was issued which reversed this policy and its interpretation of the law. (Both memos were issued without any kind of advance notice or opportunity to comment.) If a source takes steps to limit its potential to emit, then it may be regulated as an area source, and subject to less rigid regulation. The court majority held that the Wehrum Memo was not a final agency action and was not subject to judicial review when it was measured against both prongs of the “finality test” devised by the Supreme Court in the cases of Bennet v. Spear, 520 US 154 (1997) and US Army Corps of Engineers v. Hawkes, 136 S. Ct. 1807 (2016). While the memo undoubtedly represented the consummation of the agency’s decision-making process, the memo had no direct and appreciable legal consequences, and not therefore being a final action, the case must be dismissed. Judge Rogers filed a strong dissenting opinion.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
UPDATE - McMillin Albany LLC v. Superior Court
June 05, 2017 —
Richard H. Glucksman, Glenn T. Barger, & David A. Napper - CGDRB News & PublicationsThe matter has been fully briefed since last year and the construction industry anxiously awaits the California Supreme Court's highly anticipated decision regarding McMillin Albany LLC v. Superior Court (2015) 239 Cal.App.4th 1132. Numerous amicus briefs have also been filed including one by the Association of Southern California Defense Counsel, with the immediate past president of the organization, CGDRB's Glenn T. Barger, Esq., listed as the attorney of record. The Supreme Court will consider the issue of whether the Right to Repair Act (SB800) is the exclusive remedy for all defect claims arising out of new residential construction sold on or after January 1, 2003, thereby resolving the split of authority presented by the Fifth Appellate District's holding in McMillin Albany, which outright rejected the Fourth Appellate District's holding in Liberty Mutual Insurance Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98, on this particular issue. Oral argument is still pending and CGDRB will continue to closely monitor the progress of this case. Stay tuned.
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard H. Glucksman,
Glenn T. Barger and
David A. Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Barger may be contacted at gbarger@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Judgment on the Pleadings Based Upon Expected Injury Exclusion Reversed
October 30, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe appellate court reversed the trial court's granting of a judgment on the pleadings based upon the expected injury exclusion in a homeowner's policy. Allstate Indemn. Co. v. Contreras, 2018 Ill. App. LEXIS 170964 (Ill. Ct. App. July 20, 2018).
Alejandra Contreras owned Jasmine's Day Care. Her husband, Adan Contreras, was not an employee of the Day Care. Alejandra and Adan had a homeowner's policy which provided day care liability coverage through an endorsement.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Indemnity Provision Provides Relief to Contractor; Additional Insured Provision Does Not
January 06, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe court found that the contractor was entitled to relief under the contractual indemnity provision, but not the policy's additional insured clause. Chatelain v. Fluor Daniel Constr. Co., 2015 La. App. LEXIS 2257 (Ct. App. La. Nov. 10, 2015).
Following Hurricanes Katrina and Rita, FEMA retained Fluor Enterprises, Inc. as a contractor to transport and install FEMA trailers. Fluor entered a Blanket Ordering Agreement (BOA) with Bobby Reavis Contracting, Inc. to transport and install the trailers. The BOA provided Reavis would defend and indemnify Fluor from all liability arising from the subcontractor's work. Reavis also agreed to name Fluor as an additional insured under its CGL policy.
Reavis installed a FEMA trailer for Connie Chatelain. Ms. Chatelain was injured when she fell exiting her FEMA trailer. She sued Fluor and Reavis. Fluor tendered the suit to Reavis and Reavis' insurer, Guilford Insurance Company. The tender was rejected and Fluor filed a third-party action demanding indemnification, reimbursement of all legal expenses and damages for insurer misconduct.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com