Additional Insured Not Entitled to Coverage for Named Insured's Defective Work
September 02, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Court of Appeals for the Seventh Circuit determined there was no duty to defend or to indemnify the additional insured for the named insured's defective work. St. Paul Guardian Ins. Co., et al. v. Walsh Construction Co., 99 F. 4th 1035 (7th Cir. 2024).
The City of Chicago contracted with Walsh Construction Company to manage the construction of a canopy and curtain wall system at O'Hare International Airport. Walsh entered into a contract with Carlo Steel Corporation, which in turn subcontracted with LB Steel, LLC to fabricate and install steel columns to support the wall and canopy. LB Steel listed Walsh as an additional insured in its commercial general liability policies. LB Steel's insurers were St. Paul, Travelers, and Charter Oak Fire Insurance Company.
Several years into the project, the City discovered cracks in the welds of the steel columns and sued Walsh. Walsh, in turn, sued LB Steel under its subcontract. Walsh also asked LB Steel's insurers to defend it in the City's lawsuit, but they refused to do so. Walsh eventually secured a judgment against LB Steel, but LB Steel declared bankruptcy. Walsh then sued LB Steel's insurers to recover the costs of defending against the City's lawsuit and indemnification for any resulting losses.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Appraisal Goes Forward Even Though Insurer Has Yet to Determine Coverage on Additional Claims
December 11, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe trial court's order granting the insured's motion to stay litigation and compel an appraisal was affirmed even though the insurer had not determined coverage on the insured's additional claims.Heritage Prop. & Cas. Ins. Co. v. Wellington Place HOA, 2023 Fla. App. LEXIS 6405 (Fla. Ct. App. Sept. 13, 2023).
The insured homeowner's association reported roof damage to its insurer, Heritage, after Hurrican Irma struck. Heritage agreed the damage was covered, but issued no payment because the amount of loss was less than the deductible.
The insured hired its own adjuster. The insured requested an extension of the policy's two year time limit to complete repairs because the claim was still in dispute and the insurer had not yet paid sufficient funds to allow necessary repairs. Heritage sent a revised estimate and asked the insured to send its adjuster's estimate in order to address any disputes. The insured submitted its adjuster's estimate of more than $6 million, including, for the first time, the cost to replace all the windows and sliding glass doors.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Counter the Rising Number of Occupational Fatalities in Construction
April 19, 2021 —
Joshua Jacobsen - Construction ExecutivePrior to the pandemic, the construction industry was experiencing mental and behavioral health stressors and increasing fatalities. The pandemic is contributing to these underlying conditions threatening the safety and wellbeing of the construction workforce:
- Workers in construction occupations experienced 1,066 fatalities, a 6.3% increase and the highest total since 2007. Across all industries slips, trips and falls resulted in 880 deaths, a 11.3% increase from the previous year;
- Increasing mental health challenges as evidenced by growing percentage of Americans starting therapy; and
- Rising risk of relapse to substance use disorders and especially opioid overdoses. Deaths from unintentional overdoses of non-medical drug or alcohol use while at work climbed slightly to 313, marking the seventh straight annual increase in this category.
Reprinted courtesy of
Joshua Jacobsen, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Jacobsen may be contacted at
jjacobsen@holmesmurphy.com
Construction Defect Attorneys Call for Better Funding of Court System
June 28, 2013 —
CDJ STAFFThe construction defect law firm Anderson Shoech has a solution to some of the problems with the California courts. They note that cases often work their way through the system more slowly than they did in the past, due to “unprecedented cuts of over $1 billion from the State Court budget.” Prior to the cuts, cases were resolved “within six months to a year.” Under the current conditions, those involved in a lawsuit “would be lucky if their case was heard within 18 months of filing and could expect at least two full years to pass.”
They recommend that California return to appropriately funding the court system. Failure to do so could cause business to go to states “with a functioning and predictable court system.”
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Must Pay Portions of Arbitration Award Related to Faulty Workmanship
October 21, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined that portions of an arbitration award against the insured contractor based upon faulty workmanship were covered by the policy. Wallace v. Nautilus Ins. Co., 2019 U.S. Dist. LEXIS 122219 (D. N. H. July 23, 2010).
Plaintiffs, owners of adjoining homes, hired McPhail Roofing, LLC to replace the roofs of their houses. After installation, the plaintiffs found several problems with their roofs and withheld roughly a third of the agreed-upon contract price from final payments due to McPhail. A roofing consultant found evidence of water leaking through both roofs during rainstorms. Improper installation of the shakes on the roofs allowed rain to seep through to the roof decks (the plywood underneath the roofs) and eventually into the houses. The only way to cure the installation defects was to remove and replace the roofs entirely.
Plaintiffs and McPhail went to arbitration. Plaintiffs sought compensation for the damage caused by the leaking and for the replacement costs of the roofs. McPhail sought the remaining payment under the contracts. Nautilus defended McPhail under this CGL policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Homeowners May Not Need to Pay Lien on Defective Log Cabin
July 01, 2011 —
CDJ STAFFThe Idaho Supreme Court has ruled in the case of Perception Construction Management v. Bell. The Bells hired PCM to build a log home, agreeing to play monthly invoices in full within ten days. The Bells paid the first four invoices in full, part of the fifth, and ceased payment after that. Beofre seventh invoice, the Bells terminated the contract and hired a new contractor. PCM filed a claim of lien and ceased work.
The Bells responded that PCM was in breach of contract and had failed to fulfill the contract in a workmanlike manner. They claimed construction defects and in the lien suit, sought to include testimony from an architect and a plumber reviewing PCM’s work. The court only allowed the architect to testify as to whether the amount of the lien was reasonable. No testimony was permitted from the plumber.
The Idaho Supreme Court concluded that the claims of construction defects were important to case and remanded it to the lower court for a new trial taking into evidence that Bell’s contention that PCM’s work was defective.
Read the court’s decision
Read the court decisionRead the full story...Reprinted courtesy of
Massachusetts SJC Clarifies “Strict Compliance” Standard in Construction Contracts
January 02, 2019 —
Jacob Goodelman - Gordon & Rees Construction Law BlogIn Massachusetts, it is well established that a contractor cannot recover damages from a construction contract without first showing that the contractor completely and strictly performed on all of the contract’s terms. Recently, the Massachusetts Supreme Judicial Court narrowed the rule by concluding that complete and strict performance is only required for contract terms relating to the design and construction itself. The high Court explained that non-design / non-construction contract terms are governing by “ordinary contract principles, including the traditional Massachusetts materiality rule.”
Read the court decisionRead the full story...Reprinted courtesy of
Jacob Goodelman, Gordon Rees Scully MansukhaniMr. Goodelman may be contacted at
jgoodelman@grsm.com
Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
March 05, 2015 —
William L. Porter – Porter Law Group, Inc.The “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Completion will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
What commonly occurs however is that early in the process the owner authorizes or even requires its tenant to perform beneficial tenant improvements on the property. This authorization is often set forth in a tenant lease or other written document. The dispositive factor for determining whether the Notice of Non-Responsibility will be enforceable though is that the owner knows that these improvements will be made to the property and intends that they be made, usually long before the work begins. Indeed, the owner has usually negotiated these very terms into the lease contract. The owner then mistakenly believes that once work on the property commences it has 10 days to post and record a Notice of Non-Responsibility and thereby protect itself from a mechanics lien.
The usual error is two-fold. First, the statute states that the Notice is available when the owner “did not contract for the work of improvement”. The fact though is that the owner did contract for the work of improvement. It did so through the lease contract. This is true even though the owner’s contract was not with the contractor or supplier directly. Secondly, the 10 day period to post and record the Notice begins when the owner first “has knowledge” of the work of improvement. This knowledge was of course gained when the lease was negotiated and signed, providing knowledge typically many days before the work has begun. Thus, the 10 day period can also seldom be met. The Notice of Non-Responsibility will therefore fail both rules because the owner has in fact contracted for the improvement and because he does not act within 10 days of gaining this knowledge.
The next event in the typical scenario occurs when the tenant does not pay its contractor. The contractor then has nothing to pay its subcontractors. Material suppliers also go unpaid. Mechanics liens are then recorded by the unpaid claimants, followed by foreclosure actions within ninety days thereafter. Owners will typically point to the Notice of Non-Responsibility they posted and recorded, claiming its protection. Claimants then in turn point to the lease or other evidence that the owner knew of the pending improvements and contracted in some way that the improvements be performed, often also more than 10 days before they posted the Notice. Judges generally agree with the unpaid mechanics lien claimants and the Notice of Non-Responsibility is deemed ineffective.
The fact that the Court does not enforce the Notice of Non-Responsibility under these circumstances is not an unfair result. Since the owner authorized the work to be performed and it received a substantial benefit in the form of those improvements, it is not unfair that the owner should pay for those benefits. It would be inequitable for the owner to obtain the benefit of the improvements which it authorized but for which it did not pay, while allowing those who provided the benefit to go unpaid. Moreover, without such a system in place the door would be open to owners setting up sham “tenants” who would enter into contracts to have work performed, only to disappear when the work is completed, leaving the contractor without a source of payment. The system in place as described above prevents such duplicity. Owners would do well to arm themselves with proper knowledge of when the Notice of Non-Responsibility will and will not protect them and then responsibly use the Notice of Non-Responsibility.
For the legal eagles among you, the following cases illustrate the view of the courts, consistent with the above: Baker v. Hubbard (1980) 101 Cal.App.3d 226; Ott Hardware v. Yost (1945) 69 Cal. App.2d 593 (lease terms); Los Banos Gravel Co. v. Freeman (1976) 58 Cal.App.3d 785 (common interest); Howard S. Wright Construction Co. v. Superior Court (2003); 106 Cal.App.4th 314 (participating owner).
William L. Porter of
Porter Law Group, Inc. located in Sacramento, California may be contacted at (916) 381-7868 or bporter@porterlaw.com
Read the court decisionRead the full story...Reprinted courtesy of