Sometimes You Just Need to Call it a Day: Court Finds That Contractor Not Entitled to Recover Costs After Public Works Contract is Invalidated
June 29, 2020 —
Garret Murai - California Construction Law BlogJanuary was a tough month in the courts for Hensel Phelps Construction Company. Hot off the heels of Hensel Phelps Construction Co. v. Superior Court, a case concerning the 10-year statute of limitations under Civil Code section 941, comes Hensel Phelps Construction Co. v. California Department of Corrections and Rehabilitation, Case No. B293427 (January 28, 2020), a bid dispute case . . .
The Tale of a Bid, a Bid Protest, and Two Cases
A. The Bid and Bid Protest
On March 15, 2015, the California Department of Corrections and Rehabilitation (CDCR) issues an Invitation for Bid for the HVAC project at the Ironwood State Prison. The deadline to submit bids was April 30, 2015. Hensel Phelps Construction Co. submitted a timely bid and was determined to be the “apparent low bidder” with a bid of $88,160,000.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
California Construction Bill Dies in Committee
July 21, 2011 —
CDJ STAFFAB 20, which its sponsor, Linda Halderman (R-Fresno), stated would discourage class action lawsuits against builders and protect jobs in the construction industry, has died in committee. Although the Business Journal reported in June that Haldeman was promoting the bill during a talk in her district and the bill is still on her web site, the California Assembly reports that the bill failed in committee on March 15, 2011. It is possible that the bill could be reconsidered, but the Assembly Committee on Judiciary sees the bill as responding to issues quieted by SB 800 which gives builders the right to repair alleged defects before any suit can be filed.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: Recent Legal Developments at Supreme and Federal Appeals Courts
December 18, 2022 —
Anthony B. Cavender - Gravel2GavelThis is a review of initial Supreme Court and Federal Appeals Courts oral arguments and other matters in October 2022.
Oral Arguments at the Supreme Court
Michael Sackett, et ux., v. Environmental Protection Agency
The Supreme Court’s 2022 term began on October 3, 2022, with this important oral argument. For many years, the petitioner has encountered EPA opposition to the construction of a home on his property located near a lake in Idaho. The agency insists that the land is subject to federal regulatory jurisdiction, in that a Clean Water Act permit will be needed before work can proceed. Several courts have already weighed in on this issue; whether the land in question is considered a regulated “wetlands” pursuant to the “significant nexus” test developed by the Court in the Rapanos case decided in 2006. The oral argument was fairly long and spirited. The justices appear to believe that the “significant nexus” is unworkable because in many instances it provides little or no guidance to landowners as to whether their property may be subject to federal jurisdiction, and thus subject to civil and even criminal penalties. Justice Kavanaugh remarked that “this case is going to be important for wetlands throughout the country and we have to get it right.” Later, Justice Gorsuch lamented the fact that implementing a test for federal jurisdiction under the Clean Water Act test is so difficult to apply: “If the federal government doesn’t know [if a property is adjacent to navigable water and is regulated,] “does a reasonable landowner have any idea.” The issue is very difficult to resolve, and the Congress has indicated that is has no interest in entering this regulatory thicket.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
DEP Plan to Deal with Noxious Landfill Fumes Met with Criticism
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFResidents of Roxbury, New Jersey have dealt with hydrogen sulfide fumes coming from the Fenimore landfill, which gives off a rotten-egg smell and many say have “made them or their children sick,” according to New Jersey Online. The Department of Environmental Protection (DEP) announced their plan to fix the situation, which is to “first dig more wells at Fenimore, to help feed noxious gasses into the oxidizer and scrubber system the agency has credited with radically reducing smells over the last several months.”
But no one seems to be satisfied with the plan, according to New Jersey Online: “Not state Sen. Anthony R. Bucco, who authored a bill to enable a state takeover of the site last year. Not the Roxbury Township Council. Not the activist group created to respond to Fenimore issues. Not one of the state's most vocal environmental organizations. And not the site's owner, who has been in multi-pronged litigation with the state for months.”
Roxbury’s mayor, Jim Rilee, stated, “The council and I will continue to demand that the DEP show us compelling data that supports its conclusions and that its plan is based only on what is best for Township residents," as quoted by New Jersey Online.
Read the court decisionRead the full story...Reprinted courtesy of
Lease-Leaseback Battle Continues as First District Court of Appeals Sides with Contractor and School District
August 17, 2017 —
Garret Murai - California Construction Law BlogEarlier, we wrote about Davis v. Fresno United School District (2015) 237 Cal.App.4th 261, a Fifth District California Court of Appeals decision that sent shock waves through the school construction industry and raised questions regarding the use of California’s lease-leaseback method of project delivery (Education Code sections 17400 et seq.).
California’s lease-leaseback method of project delivery provides an alternative project delivery method for public school districts than the usual design-bid-build method of project delivery. Under the lease-leaseback method of project delivery, a school district leases its property to a developer, who in turn builds a school facility on the property and leases it back to the school district. One of the benefits of the lease-leaseback method of project delivery is that school districts do not need to come up with construction funds to build school facilities since they pay for the construction over time through their lease payments to the developer. Critics, however, argue that because lease-leaseback projects do not need to be competitively bid, they are ripe for cronyism between developers and school districts.
In Davis, a taxpayer successfully brought suit against the Fresno Unified School District challenging the propriety of a lease-leaseback project because the entirety of the District’s “lease payments” occurred while the project was being constructed and thus, successfully argued the taxpayer, there was no “true” lease of a facility since it was under construction.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Be Mindful Accepting Payment When Amounts Owed Are In Dispute
August 29, 2022 —
Nicholas Korst - Ahlers Cressman & Sleight PLLCAfter completing work on a project, or even during a project, it is not uncommon for some portion of the contract balance and/or a claim to be in dispute. As a contractor or subcontractor, it is important to be careful what is signed (or not signed) upon receipt of any payment both during and after completion of work on a project. One of the most common documents signed related to a receipt of payment is a lien/claim release document. This can be in the form of a conditional, unconditional, progress and/or final release. The language included in the release document is critically important, especially as it pertains to disputed amounts. As a contractor or subcontractor, if there are known disputes related to amounts owing, whether it be contract balance, disputed change order(s), a delay or inefficiency claim, or any other amounts believed to be owed, it is important to include language in the lien release that expressly carves out the disputed amounts. The same should be done for disputes related to extensions of time. This allows the contractor to accept the payment and release rights for the undisputed work, but continue to reserve its right to pursue the amounts in dispute later. If disputed amounts are not carved out, those amounts may effectively be waived and the subcontractor or contractor may lose all rights to recovery.
As a subcontractor in Alaska recently learned, there are potentially other ways a contractor may waive or lose its rights to recover amounts in dispute – without even signing a waiver or release document. In Smallwood Creek, Inc. v. Build Alaska General Contracting, LLC et al., the general contractor sent the subcontractor a check described as “final payment.” The subcontractor believed it was owed more than what the general contractor had sent and refused to accept the check. Months later, the subcontractor deposited the check. The subcontractor reversed course again and attempted to repay the general contractor the amount deposited. The general contractor refused, claiming the subcontractor’s acceptance of payment constituted satisfaction of all amounts owing to the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas Korst, Ahlers Cressman & Sleight PLLCMr. Korst may be contacted at
nicholas.korst@acslawyers.com
California Supreme Court Finds that the Notice-Prejudice Rule Applicable to Insurance is a Fundamental Public Policy of the State
October 14, 2019 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Pitzer College v. Indian Harbor Ins. Co. (No. S239510, filed 8/29/19), the California Supreme Court held that California’s notice-prejudice rule is a fundamental public policy in the insurance context, supporting the application of California law under a choice of laws analysis. In addition, the Court held that the rule generally applies to consent (aka “no voluntary payments”) provisions in first party insurance policies but not to consent provisions in third party liability policies.
Pitzer College discovered soils contamination while building a new dormitory. Under pressure to complete construction before the start of the school year, Pitzer proceeded to remediate the soils, incurring $2 million in expense. Pitzer submitted a claim to Indian Harbor, which provided Pitzer insurance covering legal and remediation expenses resulting from pollution conditions discovered during the policy period.
The policy contained a notice provision requiring Pitzer to provide oral or written notice of any pollution condition to Indian Harbor and, in the event of oral notice, to “furnish … a written report as soon as practicable.” In addition, a consent provision required Pitzer to obtain Indian Harbor’s written consent before incurring expenses, making payments, assuming obligations, and/or commencing remediation due to a pollution condition. The consent provision had an emergency exception for costs incurred “on an emergency basis where any delay … would cause injury to persons or damage to property or increase significantly the cost of responding to any [pollution condition],” in which case Pitzer was required to notify Indian Harbor “immediately thereafter.” Lastly, a choice of law provision stated that New York law governed all matters arising under the policy.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractual Waiver of Consequential Damages
January 21, 2019 —
David Adelstein - Florida Construction Legal UpdatesContractual waivers of consequential damages are important, whether they are mutual or one-sided. I believe in specificity in that the types of consequential damages that are waived should be detailed in the waiver of consequential damages provision. Standard form construction agreements provide a good template of the types of consequential damages that the parties are agreeing to waive.
But, what if there is no specificity in the waiver of consequential damages provision? What if the provision just states that the parties mutually agree to waive consequential damages or that one party waives consequential-type damages against the other party? Let me tell you what would happen. The plaintiff will argue that the damages it seeks are general damages and are NOT waived by the waiver of consequential damages provision. The defendant, on the other hand, will argue that the damages are consequential in nature and, therefore, contractually waived. FOR THIS REASON, PARTIES NEED TO APPRECIATE WHAT DAMAGES ARE BEING WAIVED OR LIMITED, AND POTENTIALLY THOSE DAMAGES NOT BEING WAIVED OR LIMITED, WHEN AGREEING TO A WAIVER OF CONSEQUENTIAL DAMAGES PROVISION!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at