U.S. Supreme Court Oral Arguments: Maritime Charters and the Specter of a New Permitting Regime
February 24, 2020 —
Anthony B. Cavender - Gravel2GavelEarlier this month, the Supreme Court heard oral arguments in two important environmental cases—one that could change the approach to routine maritime charters and another that could introduce a potentially punishing permitting regime via a CWA citizen suit.
Cleaning the Delaware: CITGO Asphalt Refining Company v. Frescati Shipping Company
The CITGO case involves a large oil spill into the Delaware River, and who bears financial responsibility for the cleanup. CITGO chartered an oil tanker to bring Venezuelan crude oil to CITGO’s New Jersey refinery located on the Delaware River. The tanker struck a submerged and abandoned anchor within yards of the refinery, and a large and expensive oil spill resulted. In accordance with the Oil Pollution Act, both the shipper, Frescati Shipping Company, and the United States, paid for the immediate oil spill response, and CITGO was later sued for a large share of these costs based on the fact that it entered into a charter with Frescati, which obliged CITGO to provide a “safe berth.” The U.S. Court of Appeals for the Third Circuit held that CITGO was liable under the principles of maritime law, meaning that CITGO was strictly liable for the spill even if no one knew that the anchor was present on the floor of the river or lurking in the waters of the Delaware River. CITGO has argued that this result is unfair and poses a threat to the maritime shipping industry if it is held to be strictly liable for this spill. It appears that this is may well be the majority rule that is applied when interpreting these routinely entered maritime charters. The Court’s decision will be immensely important to the shipping industry.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Miller Law Firm Helped HOA Recover for Construction Defects without Filing a Lawsuit
July 16, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to a press release published on the PR Newswire, The Miller Law Firm “recovered $910,000 for the 1635 California Owners' Association for construction defects without ever filing a complaint.” William Nagle, Special Master & Mediator, facilitated the settlement “a year after putting the builder on notice under SB 800, California’s Right to Repair Law.”
“Independent forensic expert inspections revealed building standard violations ranging from improperly installed gutters resulting in water intrusion in the units project wide, active leaks, standing water and inadequate gutters resulting in staining and efflorescence on the garage walls, balcony, and tile grout, discoloration and extensive cracking in the stucco project wide, inadequate weather stripping with evidence of condensation staining at windows, window frames and adjacent paint, inadequate ventilation, and ADA violations including loose glass guardrails and in regards to accessible rooftop common areas,” according to the press release.
“This case settled prior to any formal mediation and I credit the diligence of both the Association and builder counsel,” Nagle stated. “Tom Miller is one of the most knowledgeable and respected plaintiffs' lawyers in the construction defect area. And I compliment both counsel on their preparation and cost-effective handling of the case in reaching a fair and reasonable result for their respective clients."
Read the court decisionRead the full story...Reprinted courtesy of
Background Owner of Property Cannot Be Compelled to Arbitrate Construction Defects
November 07, 2012 —
CDJ STAFFIn Truppi v. Pasco Engineering, John Quattro sued Property Management Contractors, Inc. over construction defects in William Truppi’s home. All parties are named in the suit. The California Court of Appeals ruled that Property Management Contractors, Inc. (PMCI) could not compel Mr. Quattro to arbitration.
The background of the case involves two houses built in Encinitas, California by PCMI: one for Mr. Truppi at 560 Neptune, and one for Mr. Quattro at 566 Neptune. Both contracts contained an arbitration provision. Mr. Quattro signed the contract for his residence and Mr. Truppi signed the other. Mr. Quattro then sued PCMI and its principal, William Gregory. Mr. Quattro claimed to be the true contracting party for the 560 Neptune residence and a third party beneficiary of the contract Mr. Truppi signed, and stated that PCMI was aware of this.
PCMI in a demurrer stated that Quattro “had only a ‘prospective beneficial interest in the property upon its eventual sale or lease.’” Mr. Quattro amended his complaint to account for the issues raised by PCMI. The court rejected PCMI’s demurrer to the amended complaint.
Finally, PCMI and Gregory asserted that Quattro was “not the real party in interest” and could not sue. PCMI continues to assert that Quattro lacks standing, but their attorney sent Quattro an e-mail stating, “While my client disputes that you are a party, and that you lack standing to assert the claim, to the extent you do so I believe you are obligated to proceed by way of arbitration.”
The court did not cover the issue of Quattro’s standing in the case, only if he could be compelled to arbitration. The court affirmed the lower court’s finding that Quattro could not be compelled to arbitrate the construction defect claim as neither he nor Gregory signed the contract in an individual capacity. Further, the court noted that PCMI and Gregory “denied the existence of an agreement between themselves and Quattro on the 560 contract,” and cannot compel arbitration on a non-existent agreement. And while non-signatories can, in some situations be compelled to arbitrate, the court found that “these cases are inapplicable because here they seek to have the alleged third party beneficiary (Quattro) compelled by a nonsignatory (Gregory).” The arbitration clause in question “expressly limited its application to persons or entities that signed the 560 contract.”
As Mr. Quattro was not a signatory to that agreement, the court found that he could not be held to its arbitration provision.
Read the court decisionRead the full story...Reprinted courtesy of
D.R. Horton Earnings Rise as Sales and Order Volume Increase
May 07, 2015 —
John Gittelsohn – BloombergD.R. Horton Inc., the largest U.S. homebuilder by revenue, said fiscal second-quarter earnings rose as sales increased in a sign of growing demand for new homes.
Net income climbed to $147.9 million, or 40 cents a share, for the three months ended March 31 from $131 million, or 38 cents, a year earlier, the Fort Worth, Texas-based company said Wednesday in a statement. The average of 15 analyst estimates was 38 cents a share, according to data compiled by Bloomberg.
“The spring selling season at D.R. Horton is off to a strong start,” Chairman Donald R. Horton said in the statement. “Our increasingly diverse product offerings are enabling us to expand our industry-leading market share.”
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, BloombergMr. Gittelsohn may be contacted at
johngitt@bloomberg.net
Superintendent’s On-Site Supervision Compensable as Labor Under Miller Act
March 13, 2023 —
David Adelstein - Florida Construction Legal UpdatesA recent Miller Act payment bond decision out of the District of Columbia Circuit Court of Appeals, U.S. f/u/b/o Civil Construction, LLC v. Hirani Engineering & Land Surveying, PC, 58 F.4th 1250 (D.C. Circ. 2023), dealt with the issue of whether a subcontractor’s superintendent constitutes recoverable “labor” within the meaning of the Miller Act and compensable as a cost under the Miller Act that typically views labor as on-site physical labor.
The issue is that the Miller Act covers “[e]very person that has furnished labor or material in carrying out work provided for in a contract.” Civil Construction, supra, at 1253 quoting 40 U.S.C. s. 3133(b)(1). The Miller Act does not define labor. The subcontractor claimed labor includes actual superintending at the job site. The surety disagreed that a superintendent’s presence on a job site constitutes labor as the superintendent has to actually perform physical labor on the job site to constitute compensable labor under the Miller Act.
The subcontractor argued its subcontract and the government’s quality control standards required detailed daily reports that verified manpower, equipment, and work performed at the job site. It further claimed its superintendent had to continuously supervise and inspect construction activities on-site: “[the] superintendent had to be on-site to account for, among other things, hours worked by crew members, usage and standby hours for each piece of equipment, materials delivered, weather throughout the day, and all work performed. These on-site responsibilities reflected the government’s quality control standards, under which the superintendent as ‘the most senior site manager at the project, is responsible for the overall construction activities at the site…includ[ing] all quality, workmanship, and production of crews and equipment.” Civil Construction, supra, at 1253-54.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Housing Buoyed by 20-Year High for Vet’s Loans: Mortgages
July 23, 2014 —
Prashant Gopal and Jody Shenn – BloombergDuring his third deployment in Afghanistan, Air Force Staff Sgt. Claude Hunter was so eager to return to the U.S. and buy a house that he signed a contract for a property that his agent showed him over Skype.
Hunter got back in time to close the deal, paying $219,000 in May for the four-bedroom Waldorf, Maryland, house that he financed with a U.S. Department of Veterans Affairs mortgage. It didn’t require a down payment.
“On Facebook, my friends have started posting: ‘I got my VA loan, I got my house,’” said Hunter, 31. “Everybody is just ready. A lot of them have done their jobs overseas and are coming home.”
America’s fragile housing recovery is getting a boost from military buyers using VA mortgages as the U.S. draws down troops after more than a decade of combat in Iraq and Afghanistan. About 4.7 million full-time troops and reservists served during the wars and many are now able to take advantage of one of the easiest and cheapest paths to homeownership. The program’s share of new mortgages, at a 20-year high, is also increasing as other types of government-backed loans have grown more costly.
Mr. Gopal may be contacted at pgopal2@bloomberg.net; Ms. Shenn in New York at jshenn@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal and Jody Shenn, Bloomberg
When Subcontractors Sue Only the Surety on Payment Bond and Tips for General Contractors
August 13, 2019 —
Ira M. Schulman & Emily D. Anderson - ConsensusDocsPayment bonds have been a staple of public construction projects since 1874, when the U.S. Congress first passed the Heard Act, which required that contractors obtain payment bonds for public projects to ensure that subcontractors and material suppliers have a way to recover their damages if an upstream contractor fails to pay for work performed and materials furnished on the project. The 1874 Heard Act has since been replaced by the 1935 Miller Act, and the concept has been expanded to construction projects funded by the states through state statutes known as “Little Miller Acts.” But the structure remains the same: On most public projects where the project’s cost exceeds $100,000, the prime contractor (the bond principal) is required to obtain a payment bond from a surety equal to the contract price to guarantee to subcontractors and material suppliers (the bond obligees) that the surety will pay for labor and materials under certain statutory or contractual conditions should the contractor fail to make payment.
A surety is jointly and severally liable with the contractor to the subcontractor, which means that the subcontractor may seek recovery against either the contractor or the surety or both, and the contractor and surety will be liable for the damages together. Put another way, in most states and in federal court, an unpaid subcontractor has the right to sue only the surety on the payment bond without joining the contractor because a contract of suretyship is a direct liability of the surety to the subcontractor.1 When the contractor fails to perform, the surety becomes directly responsible at once — it is unnecessary for the subcontractor to establish that the contractor failed to carry out its contract before the obligation of the surety becomes absolute.
Reprinted courtesy of
Ira M. Schulman, Pepper Hamilton LLP and
Emily D. Anderson, Pepper Hamilton LLP
Mr. Schulman may be contacted at schulmani@pepperlaw.com
Ms. Anderson may be contacted at andersone@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Court Voids Settlement Agreement in Construction Defect Case
September 01, 2011 —
CDJ STAFFA U.S. District Court Judge in Florida has ruled in favor of a company that sought to void a settlement agreement. The case, Water v. HDR Engineering, involved claims of construction defects at Florida’s C.W. Bill Young Regional Reservoir. The Tampa Bay Water Authority attributed these to both HDR Engineering’s design and Bernard Construction Company which had built the embankment. Bernard Construction filed a complaint against their subcontractor, McDonald.
Tampa Bay Water settled with Bernard Construction and McDonald, in an agreement that set a minimum and maximum settlement, but also would “prohibit Barnard and McDonald from presenting any evidence on several claims and positions of TBW, to require Barnard to call certain witnesses at trial, to preclude Barnard and McDonald from calling other witnesses, and to restrict the filing of trial and post-trial motions.” HDR Engineering moved to void the agreement as collusive.
The judge that the agreement¬? contained “133 paragraphs of ‘Agreed Facts’ that the parties stipulated would survive any order declaring the Settlement Agreement void or unenforceable.” He characterized these as stipulating “that Barnard neither caused nor contributed to TBW’s damages.” HDR motioned that a summary judgment be given to Barnard Engineering.
The court found that “the evidence identified by TBW is patently insufficient to survive summary judgment.” Further, TBW’s expert initially held Barnard responsible for “lenses, pockets, streaks and layers within the embankment,” but then later withdrew this assigning the responsibility to HDR. Further, the court notes that, “TBW’s arguments that lenses, pockets, streaks, and layers in the soil wedge caused or contributed to its damages and that Barnard is liable for those damages have been foreclosed by the Agreed Facts.”
As TBW failed to provide sufficient evidence to withstand summary judgment, the court granted summary judgment, mooted the claim against McDonald, and terminated the agreement between TBW and the other parties.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of