Don’t Kick the Claim Until the End of the Project: Timely Give Notice and Preserve Your Claims on Construction Projects
December 10, 2015 —
Christopher G. Hill – Construction Law MusingsFor this week’s Guest Post Friday, we welcome
Tara L. Chadbourn. Tara is an attorney with
ReavesColey PLLC in Chesapeake, VA, where she concentrates her practice on construction law, litigation and commercial litigation. Tara counsels owners, contractors, subcontractors and materials suppliers in various government and commercial construction matters. Tara can be reached at tara.chadbourn@reavescoley.com.
You may have experienced and have certainly heard of the scenario in which a contractor waits to address a claim as part of project closeout, only to realize the applicable deadline has already passed. While there may have been discussions about claims during the course of the project, contractors cannot rely upon oral conversations about outstanding claims. Instead, contractors must be vigilant in satisfying notice requirements and preserving claims. While entitlement must still be proven, a contractor’s chances of recovery increase greatly if the contractor abides by notice requirements and consciously preserves claims in the following ways.
Contractors Must Acquaint Themselves with Contractual Notice Provisions:
Many prime and subcontract agreements contain stringent notice provisions that require the contractor to give notice within a certain time period or else the claim is expressly waived. The deadline for notice is often only a few days after the occurrence giving rise to the claim or the contractor becoming aware of the claim. To avoid waiver, contractors must carefully review their contracts for provisions requiring notice of a claims for adjustment for a variety of situations to include unforeseen site conditions, trade sequencing changes, project delay or scope of work changes.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Western Specialty Contractors Branches in San Francisco and Cleveland Take Home Top Industry Honors
January 03, 2022 —
Western Specialty Contractors(St. Louis, MO, Dec. 21, 2021) Western Specialty Contractors Branches in San Francisco, CA and Cleveland, OH are ending the year's fourth quarter on a high note, with each receiving a top industry award.
In October, Western's San Francisco Branch was named a 2021 International Concrete Repair Institute (ICRI) Project of the Year Award Finalist (Historic Category) for renovation and repurposing of the SMUD Museum of Science and Curiosity in Sacramento, CA. Western's Cleveland Branch was honored in December with the Institute of Real Estate Management (IREM) Northern Ohio Chapter's Industry Partner of the Year Award.
About Western Specialty Contractors
Family-owned and operated for more than 100 years, Western Specialty Contractors is the nation's largest specialty contractor in masonry and concrete restoration, waterproofing and specialty roofing. Western offers a nationwide network of expertise that building owners, engineers, architects, and property managers can count on to develop cost-effective, corrective measures that can add years of useful life to a variety of structures including industrial, commercial, healthcare, historic, educational and government buildings, parking structures, and sports stadiums. Western is headquartered in St. Louis, MO with 30 branch offices nationwide and employs more than 1,200 salaried and hourly professionals who offer the best, time-tested techniques and innovative technology. For more information about Western Specialty Contractors, visit www.westernspecialtycontractors.com.
Read the court decisionRead the full story...Reprinted courtesy of
Another Defect Found on the Bay Bridge: Water Leakage
February 11, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to the San Francisco Chronicle, the eastern span of the Bay Bridge has dealt with alleged “defective welds” and “cracked steel rods,” and now there are reports of leakage. The Chronicle stated that rainwater “is dripping into the steel structure beneath the road deck on the suspension stretch of the span, which,” according to Caltrans “is supposed to be watertight.”
Water corrosion on a bridge could cost $6.4 billion, the San Francisco Chronicle claimed. Caltrans said that they “are going to have teams of engineers and inspectors there this weekend to assess the problem.”
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Motion for Summary Judgment in Collapse Case Denied
November 10, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe court denied the insurer's motion for summary judgment seeking to establish it did not breach the policy when denying coverage for the collapse of basement walls. Belz v. Peerless Ins. Co., 2016 U.S. Dist. LEXIS 118900 (D. Conn. Sept. 2, 2016).
The Belzes purchased their home in 2001. Prior to the purchase, they were aware of notable cracking in the basement walls. An engineer was hired to inspect the cracking and determined the cracks did not threaten the structural integrity of the home.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
New Jersey Law regarding Prior Expert’s Testimony
April 15, 2014 —
Beverley BevenFlorez-CDJ STAFFMary Pat Gallagher writing for the New Jersey Law Journal reported that “[l]awyers who track down an opposing expert's testimony from prior cases must disclose that fact during discovery but need not say whether they plan to use it in cross-examining the expert at trial, a New Jersey appeals court says.” In Dalton v. Crawley, the Appellate Division held that “[d]ecisions about cross-examination ‘involve the attorney's mental processes, so they are inherently work product.’”
The issue began when “one of the defense lawyers, Michael McGann, figured out from the deposition questions Mahoney directed at one of his experts that he had transcripts of testimony from earlier cases,” according to the New Jersey Law Journal. “Hit with a notice to produce the transcripts, [Plaintiff attorney Brian] Mahoney refused, saying they were ‘attorney work product and we will not be telling you what we have developed regarding this expert.’"
The New Jersey Law Journal declared that the “ruling means both sides will have to indicate what transcripts they have gathered for use—giving the name of each expert as well as the name and docket number of the prior cases where those experts testified. “
Read the court decisionRead the full story...Reprinted courtesy of
Fifth Circuit Requires Causal Distinction for Ensuing Loss Exception to Faulty Work Exclusion
August 29, 2022 —
Avery J. Cantor & William S. Bennett - Saxe Doernberger & VitaIn Balfour Beatty v. Liberty Mutual Ins. Co., the 5th Circuit Court of Appeals provided valuable insight on coverage available through ensuing loss exceptions to faulty work and design exclusions in builder’s risk insurance policies. In Balfour Beatty, the Court held that, in order to establish coverage through an ensuing loss exception, the ensuing loss must be causally distinct from the original excluded loss.1
Balfour Beatty, serving as general contractor for construction of a commercial office building in Houston, Texas, subcontracted with Milestone for steelwork on the project. As part of this work, Milestone welded a 2-inch metal plate to external tubing on the eighteenth floor of the building. While welding the plate in place, welding slag fell down the side of the building, damaging exterior glass windows on the floors below.
Balfour Beatty and Milestone, along with the developer, sought coverage for the damage to the windows under their builder’s risk policy, issued by Liberty Mutual. Liberty Mutual denied coverage, claiming that the damage was excluded by the policy’s “Defects, Errors, and Omissions” exclusion. The insureds sued, arguing that the ensuing loss exception to this exclusion would carve back coverage because the damage to the windows constituted an “ensuing loss.”
Reprinted courtesy of
Avery J. Cantor, Saxe Doernberger & Vita and
William S. Bennett, Saxe Doernberger & Vita
Mr. Cantor may be contacted at ACantor@sdvlaw.com
Mr. Bennett may be contacted at WBennett@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Toolbox Talk Series Recap – Arbitration Motion Practice
August 07, 2023 —
Michael Zehner - The Dispute ResolverIn the June 22, 2023 edition of the Toolbox Talk Series,
Adrian Bastianelli, Peckar & Abramson, P.C., and
Brian Cashmere, Williams Mullen, moderated by Jennifer Millender of the American Arbitration Association (“AAA”), discussed motion practice in arbitration. Specifically, they offered advice on how to choose the right issue for a motion, how to get approval for a motion, how to write the motion, and how to get the arbitrator to grant it. They also discussed the pros and cons of motion writing in arbitration settings.
1. How to choose the “right issue” for a motion in arbitration
The panel discussed what type of issues can, or should, be brought up in a motion in arbitration. Cashmere stated that a clear and concise issue is best for this type of review. For example, statute of limitations, notice, or contract interpretation issues may make great summary judgment or partial summary judgment motions. Essentially, an issue that the arbitrator may resolve via primarily a question of law is more likely to succeed. Bastianelli warned against submitting just any “available” motion, as the practice may turn the arbitrator against you. Both panelists mentioned the need to consider strategy before filing a motion—ask, “how will filing this motion help or hurt reachingArbi final resolution.” Cashmere noted that sometimes the threat of bringing the issue to a hearing can put pressure on the adverse party in a way that is favorable to your client’s goals; possibly even more so than actually submitting the issue.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Zehner, BBG Construction LawMr. Zehner may be contacted at
mzehner@bbglaw.com
A Tort, By Any Other Name, is Just a Tort: Massachusetts Court Bars Contract Claims That Sound in Negligence
March 20, 2023 —
Gus Sara - The Subrogation StrategistIn University of Massachusetts Building Authority v. Adams Plumbing & Heating, Inc., 2023 Mass. App. Unpub. LEXIS 28, 102 Mass. App. Ct. 1107, the Appeals Court of Massachusetts (Appeals Court) considered whether the lower court properly held that the plaintiff’s breach of contract and indemnification claims were time-barred by the statute of repose because they sounded in tort. The Appeals Court held that while the six-year statute of repose only applies to tort claims, they can also bar claims for breach of contract and indemnification if they sound in tort. The Appeals Court affirmed the lower court’s ruling, finding that the plaintiff’s breach of contract and indemnification claims were just negligence claims disguised as non-tort claims.
In 2013 and 2014, the University of Massachusetts (UMass) retained various contractors to renovate the dining hall for one of its campus buildings, which included the installation of new ductwork for the kitchen’s exhaust system. The dining hall opened for service in September 2014. In the Spring of 2018, it was discovered that the ductwork for the kitchen had collapsed. Further investigation revealed other deficiencies with the exhaust system. On December 1, 2020, UMass filed a lawsuit against various contractors, asserting negligence, breach of contract, and indemnification. The breach of contract claims alleged breach of express warranties.
Read the court decisionRead the full story...Reprinted courtesy of