Developers Celebrate Arizona’s Opportunity Zones
May 24, 2018 —
Patrick J. Paul - Snell & Wilmer Real Estate Litigation BlogPresident Trump’s Tax Cuts and Jobs Act passed by Congress in December included a new community development program designed to promote investment in low income urban and rural communities. These “Opportunity Zones” provide that every Governor may nominate up to 25% of qualifying low-income Census tracts for consideration in the program which provides substantial reductions on capital gains taxes with the greatest benefits to those holding their investments for a period of at least 10 years.
States were required by March 21st to submit nominations or request a 30 day extension to subsequently submit. The Treasury Department in turn has 30 days from the date of submission to designate the nominated zones. On April 9, 2018, the Treasury Department and the IRS formally dedicated opportunity zones in 18 states including Arizona. The Department will make future designations as submissions by the states that have requested an extension are received and certified.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick J. Paul, Snell & WilmerMr. Paul may be contacted at
ppaul@swlaw.com
Under Privette Doctrine, A Landowner Delegates All Responsibility For Workplace Safety to its Independent Contractor, and therefore Owes No Duty to Remedy or Adopt Measures to Protect Against Known Hazards
September 29, 2021 —
Krsto Mijanovic, Jeffrey C. Schmid & John M. Wilkerson - Haight Brown & BonesteelIn Gonzalez v. Mathis (2021 WL 3671594) (“Gonzalez”), the Supreme Court of California held that a landowner generally owes no duty to an independent contractor or its workers to remedy or adopt other measures to protect them against known hazards on the premises. The Court applied the Privette doctrine which establishes a presumption that a landowner generally delegates all responsibility for workplace safety to its independent contractor. (See generally Privette v. Superior Court (1993) 5 Cal.4th 689; SeaBright Ins. Co. v. US Airways, Inc. (2011) 52 Cal.4th 590.) As such, the independent contractor is responsible for ensuring that the work can be performed safely despite a known hazard on the worksite, even where the contractor and its workers are unable to take any reasonable safety precautions to avoid or protect themselves from the known hazard.
In Gonzalez, the landowner, Mathis, had hired an independent contractor, Gonzalez, to clean a skylight on his roof. To access the skylight, Gonzalez needed to utilize a narrow path between the edge of the roof and a parapet wall. While walking along this path, Gonzalez slipped and fell to the ground, sustaining serious injuries. Gonzalez alleged this accident was caused by several dangerous conditions on the roof, including a slippery surface, a lack of tie-off points to attach a safety harness, and a lack of a guardrail. Gonzalez was aware of all of these hazards prior to the accident.
Reprinted courtesy of
Krsto Mijanovic, Haight Brown & Bonesteel,
Jeffrey C. Schmid, Haight Brown & Bonesteel and
John M. Wilkerson, Haight Brown & Bonesteel
Mr. Mijanovic may be contacted at kmijanovic@hbblaw.com
Mr. Schmid may be contacted at jschmid@hbblaw.com
Mr. Wilkerson may be contacted at jwilkerson@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Quick Note: Aim to Avoid a Stay to your Miller Act Payment Bond Claim
February 23, 2017 —
David Adelstein – Florida Construction Legal UpdatesStrategy is important. This is especially true if you are trying to avoid arbitration. In a recent federal district court case, a subcontractor sued the prime contractor and the Miller Act payment bond surety. The subcontractor, however, had an arbitration provision in its subcontract with the prime contractor. The prime contractor moved to compel arbitration pursuant to the subcontract and moved to stay the subcontractor’s Miller Act payment bond claim. The last thing, and I mean the last thing, the subcontractor wanted to do was to stay its claim against the Miller Act payment bond. However, the district court compelled the subcontractor’s claim against the prime contractor to arbitration and stayed the subcontractor’s Miller Act payment bond claim pending the outcome of the arbitration. See U.S. v. International Fidelity Ins. Co., 2017 WL 495614 (S.D.Al. 2017). This is not what the subcontractor wanted.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Louisiana Couple Sues over Defects in Foreclosed Home
September 24, 2013 —
CDJ STAFFA Louisiana couple is suing over the home they bought, claiming that the sellers knew there were defects in the home, including termite damage, mold, and roof leaks. When the Eastmans bought the home, they were assured that inspectors had cleared the property.
The home had been foreclosed upon and purchased by Beverly Knoll, LLC. The Eastmans subsequently purchased the home from Beverly Knoll. After the sale, the plaintiffs hired their own inspector who found the damage and no evidence of attempts at repair.
The Eastmans informed one of the defendants, Troy Duhon, who informed them that the defendants would be assuming the costs of repair. However, after the Eastmans requested $94,000 in reimbursements, the defendants declined to pay.
Read the court decisionRead the full story...Reprinted courtesy of
Bid Protests: The Good, the Bad and the Ugly (Redeux)
September 17, 2014 —
Garret Murai – California Construction Law BlogThis past week I gave a presentation on a panel entitled “Bid Protests: The Good, the Bad and the Ugly” before my local bar association. Thanks to those who attended, my co-presenters and the bar association for sponsoring.
Rather than letting my notes gather dust I thought I would share some of the highlights.
What is a bid protest?
A bid protest is the procedure by which a bidder protests the rejection of its bid or award of a public works contract to another bidder.
A bid protest may occur in one of two situations: (1) A public entity rejects the bid of an apparent low bidder and the apparent low bidder protests the rejection; or (2) A public entity awards the contract to the apparent low bidder and another bidder protests the award.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Kronick Moskovitz Tiedemann & GirardMr. Murai may be contacted at
gmurai@kmtg.com
ASCE Statement on Calls to Suspend the Federal Gas Tax
June 27, 2022 —
Tom Smith, Executive Director, American Society of Civil Engineers (ASCE)WASHINGTON, D.C. –
ASCE strongly opposes the recent announcement from the Biden Administration to suspend the current 18.4 cents-per-gallon federal gasoline tax for three months. Even at the same modest figure of 18 cents per gallon for over 25 years since 1993, the motor fuel tax has represented a reliable federal revenue source for communities to fix and modernize their network of roads, bridges, and transit systems.
Suspending the gas tax would result in the loss of billions in revenue from the Highway Trust Fund (HTF), significantly diminishing much of the progress made in the Bipartisan Infrastructure Law at a time when Americans expect improvements to the nation's roads, bridges, and transit systems. Replacing this lost revenue with funds from other sources is not a viable long-term solution and sets a damaging precedent. Encouraging states to follow suit will compound this bad idea and further exacerbate our nation's infrastructure funding challenges. Our transportation system, including roadways, bridge spans, and transit networks, can't rely on novel, unpredictable funding.
Further, there is little guarantee that motorists will see any real relief at the pump. Gas holidays aren't price controls; the manager at the gas station still gets to set their price. Oil producers have benefited significantly in the past from previous state-level gas tax holidays. There is no mechanism to ensure that these "savings" are passed on to consumers, but there is a virtual guarantee of disrupting transportation dollars and the HTF. While it sounds like an enticing solution when pocketbooks are strained, Congress knows that a variety of factors, including plain supply and demand, affect the prices that people see at fuel stations.
Now is the time to build on the momentum of the Bipartisan Infrastructure Law which, for the first time in decades, takes significant steps to revitalize our nation's aging infrastructure, improve public safety, strengthen our economy, and deliver well-paying jobs.
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Building's First Collapse, But Disputed Facts on Second Collapse
January 10, 2018 —
Tred R. Eyerly – Insurance Law Hawaii While building's first collapse was not covered, there were disputed facts regarding the second collapse, leading to a reversal of the order granting summary judgment to the insurer on both collapses. Intergroup Int'l Ltd. v. Cincinnati Ins. Cos, 2017 Ohio app. LEXIS 5099 (Ohio Ct. App. Nov. 22, 2017). Intergroup bought a building after it was inspected. While leaks on the roof were repaired and a roof truss that was sagging was replaced, the inspector found the roof to be in good shape.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at te@hawaiilawyer.com
COVID-19 Damages and Time Recovery: Contract Checklist and Analysis
April 27, 2020 —
Patrick J. Greene, Jr. - Peckar & AbramsonThis Alert explores the contract provisions and related rights that are likely to govern time and compensation adjustments for COVID-19 impacts. As parties begin analyzing such rights, this is intended to serve as a useful guide and checklist.
Analysis of relevant contract provisions should start with careful consideration of the specific impacts that have been experienced and the causes of those impacts. The nature of the impact (delay, extra work, disruption, etc.) and the causes of such impacts (owner direction, government order, etc.) will generally govern the analysis and resulting course of action. Listing or creating a matrix of impacts and their causes may be an effective working tool.
Essentially, there are five primary impacts that will likely require critical analysis under the relevant contract provisions, and notably, more than one impact may be present:
a) complete or partial suspension of work,
b) additional work or requirements,
c) added cost,
d) delay, and
e) disruption.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick J. Greene, Jr., Peckar & AbramsonMr. Greene may be contacted at
pgreene@pecklaw.com