Homeowner Loses Suit against Architect and Contractor of Resold Home
June 14, 2011 —
CDJ STAFFThe California Court of Appeals in the case of Kizor v. Architects ruled that Mr. Kizor could not make construction defect claims against the architect and contractor of his home, as the defects had caused significant damage to the former owners, and it was they, not Kizor, who could have asserted those claims.
The background of the case was that John and Miranda Redig hired BRU Architects to design a home. During construction in 2000, they wrote to the roofing supplier complaining about leaks. The leaks were caulked, but the roof continued leaking during rains. The Redigs sold their house to Kizor in 2002, with an addendum to the sale contract protecting themselves from liability for further problems with the roof. “Seller has no responsibility for the condition of the roof and stucco and buyer absolves seller of any liability in connection therewith.”
In 2006, Kizor sued the architects, contractor, and subcontractor. The defendants moved for summary judgment which was granted. Kizor appealed, and in this current court case, appeal was denied.
Read the court’s decision
Read the court decisionRead the full story...Reprinted courtesy of
Microsoft Said to Weigh Multibillion-Dollar Headquarters Revamp
September 17, 2015 —
Dina Bass & Hui-Yong Yu - BloombergMicrosoft Corp. is considering a multibillion-dollar revamp of its headquarters campus in suburban Seattle, seeking to foster more collaboration among employees and attract young engineers, according to people with knowledge of the plans.
The software giant has hired architecture firm Skidmore, Owings & Merrill LLP as part of the effort at its Redmond, Washington, offices, said the people, who asked not to be named because the plans aren’t public. Skidmore Owings designed Dubai’s Burj Khalifa, the world’s tallest building, and is helping Microsoft with a makeover of its much smaller campus in Mountain View, California.
Microsoft hasn’t yet decided whether to move forward with the Redmond overhaul, said one of the people familiar with the matter.
Reprinted courtesy of
Dina Bass, Bloomberg and
Hui-Yong Yu, Bloomberg
Read the court decisionRead the full story...Reprinted courtesy of
Be Strategic When Suing a Manufacturer Under a Warranty with an Arbitration Provision
October 02, 2023 —
David Adelstein - Florida Construction Legal UpdatesI’ve said this before, and I’ll say it again: arbitration is a creature of contract. If you don’t want to arbitrate, don’t agree to an arbitration provision as the means to resolve your dispute. Now, with that said, there are times you may not have a choice. An arbitration provision in a warranty from a manufacturer of a product is an example. If you are procuring the product, you are agreeing to the terms of the express warranty. Manufacturers are not negotiating their product warranty on a case-by-case basis considering they are not typically the ones selling the product directly to the end user. This does not mean that is a bad thing. It just means if you elect to sue the manufacturer directly for an alleged product defect or under the terms of the warranty, you should read the warranty and consider the strategic aspect that suing the manufacturer will have on your case.
In SICIS North America, Inc. v Sadie’s Hideaway, LLC, 48 Fla.L.Weekly D1581c (Fla. 1st DCA 2023), an owner elected to sue a tile manufacturer, a general contractor, the architect, and a window and door company. One of the arguments the owner raised was that exterior tiles installed were defective. The tiles were procured by the general contractor. The owner sued the general contractor under various theories and sued the tile manufacturer for breaches of warranty and negligence. The general contractor asserted a crossclaim for indemnification against the tile manufacturer. The tile manufacturer moved to compel the owner’s claim and the general contractor’s crossclaim to arbitration since there was an arbitration provision in the warranty documents and the general contractor’s indemnification claim arose from that transaction. The trial court denied the motion to compel arbitration. On appeal, the appellate court reversed:
First, because [the owner] was suing [the tile manufacturer] based upon the written warranty, it was bound by the arbitration provision contained in [the general contractor’s] agreement with [the tile manufacturer]. As the Florida Supreme Court has explained, “[W]hen a plaintiff sues under a contract to which the plaintiff is not a party . . . we will ordinarily enforce an arbitration clause contained in that contract, absent some other valid defense. . . .” . [The owner] had no valid defense against arbitration, a fact which it apparently realized when it voluntarily dismissed its express warranty claim after the notice of appeal and initial brief were filed.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Be Careful How You Terminate: Terminating for Convenience May Limit Your Future Rights
January 19, 2017 —
Brett M. Hill - Ahlers & Cressman, PLLC BlogMany construction contracts contain a termination clause that allows a contractor to be terminated either for convenience or for cause. Termination for convenience and termination for cause clauses have been discussed previously on the blog
here,
here and
here. The distinction between a termination for convenience or for cause is an important one.
If a contractor is terminated for convenience, the rights of the party who has terminated the contractor for convenience could be limited in the future. This is specifically true as to any defects in the terminated contractor’s work that are discovered after the termination for convenience.
This issue was addressed in an Oregon Court of Appeals case where a general contractor attempted to recover costs incurred in correcting a terminated subcontractor’s work after the subcontractor was terminated for convenience. Shelter Prods. v. Steel Wood Constr., Inc., 257 Or. App 382 (2013). In that case, the subcontractor sued the general contractor for its termination expenses. The general contractor asserted an offset/backcharge claim for damages incurred by the general contractor in correcting the subcontractor’s defective work. The general contractor had incurred the costs after it had terminated the subcontractor. The general contractor did not notify the subcontractor that its work was defective and did not give the subcontractor an opportunity to cure before the repairs were completed.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers & Cressman, PLLCMr. Hill may be contacted at
bhill@ac-lawyers.com
Carroll Brock of Larchmont Homes Dies at Age 88
November 05, 2014 —
Beverley BevenFlorez-CDJ STAFFHomebuilder Carroll Brock, "whose family-owned company built thousands of Larchmont Homes in the Sacramento region, died Oct. 31 of natural causes in his sleep, his son Steve said," according to the obituary in the Sacramento Bee. "Under Mr. Brock, who was named Sacramento general manager in 1967, Larchmont Homes built nearly 15,000 houses in more than 30 subdivisions of modest ranch-style homes aimed mostly at first-time buyers."
Mr. Brock served on the board of the National Association of Home Builders, was past president of the North State Building Industry Association, and had been appointed to the California state Board Standards Commission. Furthermore, he was inducted into the California Building Industry Association Hall of Fame in 1991. Mr. Brock served the community through his work in the Sacramento Area Commerce and Trade Commission as well as the Sacramento Metropolitan Chamber of Commerce. He volunteered his time to the Salvation Army as well as offering construction assistance and expertise to the Fair Oaks Presbyterian Church.
“My dad was a humble leader,” his son told the Sacramento Bee. “As successful as he was at building homes, he felt just as strongly about serving others.”
Read the court decisionRead the full story...Reprinted courtesy of
Mediation Scheduled for Singer's Construction Defect Claims
February 11, 2013 —
CDJ STAFFA judge has scheduled mediation and trial over the claims of Rihanna that her Beverley Hills home suffers from construction defects. The singer claims that the previous owners, Adriana and Heather Rudomin, did not disclose construction defects which lead to flooding from water leaks in January 2010.
The Rudomins did not appear at the February 7th hearing, and the judge fined them $500. They will be required to explain their absence on March 12. The mediation will begin on May 7. The trial has been scheduled for February 24, 2014, and is expected to last three weeks.
Read the court decisionRead the full story...Reprinted courtesy of
Not to Miss at This Year’s Archtober Festival
October 15, 2014 —
Carrie Hojnicki – BloombergNew York architecture fanatics everywhere can rejoice: Archtober has arrived. In its fourth annual iteration, the monthlong festival throws a spotlight on the importance of architecture and design in the five boroughs, calling special attention to the city’s rich built history and exciting future. In addition to a lineup of lectures, openings, and workshops, the American Institute of Architects (AIA) New York Chapter–sponsored initiative highlights a “Building of the Day,” with on-site tours led by the architects themselves.
Here are five events not to miss this Archtober.
1. AIA’s New York chapter puts its own spin on the architecture tour: a boat ride. Guides from the AIA will share their wisdom as the cruise circles the tip of Manhattan, passing architectural marvels aplenty. October 3, 10 am and 1:30 pm, Classic Harbor Line
Read the court decisionRead the full story...Reprinted courtesy of
Carrie Hojnicki, Bloomberg
Boston Water Main Break Floods Trench and Kills Two Workers
October 27, 2016 —
Justin Rice – Engineering News-RecordTwo workers died in Boston on Friday afternoon after a water main break flooded the trench where they were working, according to the Boston Fire Dept.
Read the court decisionRead the full story...Reprinted courtesy of
Justin Rice, Engineering News-RecordMr. Rice may be contacted at