Bad Faith and a Partial Summary Judgment in Seattle Construction Defect Case
February 10, 2012 —
CDJ STAFFThe US District Court of Washington has issued a ruling in the case of Ledcor Industries v. Virginia Surety Company, Inc. Ledcor was the builder of a mixed-use real estate project in Seattle called the Adelaide Project. Ledcor purchased an insurance policy from Virginia Surety covering the project. After the completion of the project, Ledcor received complaints of construction defects from the homeowners, which they forwarded to Virginia Surety.
Virginia Surety denied coverage on several grounds. Absent any lawsuit, Virginia claimed that there was “not yet any duty to defend or indemnify.” Further, as the policy commenced ten days after work on the project was substantially completed, Virginia cited a provision in the policy that excluded coverage for damage that occurred before the policy began. As problems included water intrusion, Virginia noted an exclusion for fungal damage. Finally, Virginia noted that it was not clear whether damage was due to Ledcor’s own actions.
The homeowners sued over the construction defects. Ledcor settled these suits before trial. In this, they were defended by, and settlements were paid by American Home, another of Ledcor’s insurers. Ledcor claims that Virginia Surety acted in bad faith by denying coverage and by its failure to investigate the ongoing nature of the work at the project.
The judge determined that Virginia Surety acted in bad faith when it invoked the fungus exclusion. Virginia noted that fungal damage “‘would have been’ referenced in the list of construction defects,” however, the HOAs claimed only “water stains” and “water damage,” and made no mention of mold or fungus. The court found that Virginia Surety “was not entitled to deny coverage simply because it may have suspected that mold or fungus damage existed.” The court noted that further proceedings would be needed to determine what portion of the settlement Virginia is obligated to pay.
The court found that there were matters of fact to be determined on the further issues in the case. The judge wrote that although Virginia acted in bad faith in invoking the fungus exclusion, it still had to be determined if they were in breach of contract by failing to defend Ledcor. Ledcor still needs to show that the damages claimed by the HOA were due to work actually covered by Virginia Surety.
Ledcor made an additional claim that Virginia Surety violated Washington’s laws concerning the insurance industry. Here, the court noted that the improper exclusion for fungus issues “constitutes a per se unfair trade practice.” Six other claims were made under this law. The court found that Virginia Surety did not misrepresent “pertinent facts or insurance policy provisions.” It also issued its denial letter promptly, satisfying the fifth provision. However, Virginia Surety did violate the second provision, in that it failed “to acknowledge and act reasonably promptly upon communications with respect to claims.” Two other issues could not be determined.
Judge Martinez’s decision granted a summary judgment to Ledcor on the issue of bad faith. An additional summary judgment was granted that Virginia Surety violated Washington’s Insurance Fair Conduct Act. Judge Martinez did not grant summary judgment on any of the other issues Ledcor raised.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Confidence Among U.S. Homebuilders Little Changed in January
January 28, 2015 —
Bloomberg News(Bloomberg) -- Confidence among U.S. homebuilders hovered in January close to a nine-year high, indicating the residential real estate market is poised to expand this year.
While the National Association of Home Builders/Wells Fargo builder sentiment gauge fell to 57 this month from 58 in December, readings greater than 50 mean more respondents report good market conditions, according to figures issued from the Washington-based group Tuesday. The median forecast in a Bloomberg survey called for 58.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg News
Insurer's Motion for Summary Judgment on Business Interruption Claim Denied
September 12, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's motion to cap a potential business interruption claim after the insured failed to provide documentation was denied. Lake Charles Instruments Inc. v. Scottsdale Ins. Co., 2022 U.S. Dist. LEXIS 116802 (W.D. La. July 2, 2022).
Plaintiff operated a business that was damaged during Hurricane Laura on August 27, 2020, and subsequently by Hurricane Delta on October 9, 2020. Plaintiff had a commercial property policy issued by Scottsdale that provided business income coverage of up to $500,000.
After Hurricane Laura, plaintiff submitted a claim. Plaintiff requested an advance. Scottsdale paid $50,000 on the business interruption (BI) claim while reserving rights to require full compliance with the policy, including submission of appropriate documentation. Scottsdale continued to request documentation, but none was received. Plaintiff also failed to provide documentation for its BI claim after Hurricane Delta. When documentation was finally provided, Scottsdale disputed that the documentation showed a BI claim that exceeded policy limits. Scottsdale determined the BI claim was below the policy limits.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
California Reinstates COVID-19 Supplemental Paid Sick Leave
February 21, 2022 —
Jessica L. Daley - Newmeyer DillionOn February 9, 2022, Governor Newsom signed California Legislature Senate Bill 114 (SB 114), which reinstates supplemental paid sick leave for qualifying reasons relating to COVID-19.
Employers may recall SB 95, which expired on September 30, 2021, and was substantially similar to SB 114. Like its predecessor, SB 114 applies to employers with 26 or more employees and provides up to 80 hours of supplemental paid sick leave to full-time employees who are unable to work (including telework) for a reason relating to COVID-19. While this legislation goes into effect on February 19, 2022, it will retroactively apply back to January 1, 2022 and remain in effect until September 30, 2022.
REASONS FOR LEAVE – TWO PERIODS
Unlike SB 95, SB 114 breaks the total possible 80 hours of COVID-19 Supplemental Paid Sick Leave (CSPL) for full-time employees into two 40-hour periods.
Read the court decisionRead the full story...Reprinted courtesy of
Jessica L. Daley, Newmeyer DillionMs. Daley may be contacted at
jessica.daley@ndlf.com
Are Contracting Parties Treated the Same When it Comes to Notice Obligations?
June 25, 2019 —
G. Scott Walters - Smith CurrieOverview
Experienced project delivery team members know too well the importance of timely and proper notice during a construction project. Ideally, contractual notice provisions, and any penalties for non-compliance, should apply equally to all of the contracting parties. For example, failure to comply with a notice provision concerning contract changes could bar a party from pursuing claims. And, untimely or improper notice can, likewise, prevent certain defenses to claims.
Nowhere is notice more scrutinized than in the federal government contracting arena. Recently, the United States Court of Federal Claims issued two separate decisions involving the same construction project and the same parties and dealing with two specific aspects of notice in the federal government contracting process. The court’s decisions on the notice issues may, at first, appear to contradict each other or to favor one party over the other. A closer look at these two decisions reveals that notice requirements, in the context of federal government construction contracts, can come in multiple forms and notice is not a “one size fits all” proposition.
Read the court decisionRead the full story...Reprinted courtesy of
G. Scott Walters, Smith CurrieMr. Walters may be contacted at
gswalters@smithcurrie.com
Transportation Officials Make the Best of a Bumpy 2020
January 18, 2021 —
Jim Parsons & Aileen Cho - Engineering News-RecordThe year 2020 provided a bumpy budgetary ride for all modes of transportation, and some industry insiders don’t expect airport and transit ridership to return to pre-pandemic levels for years. Agencies are taking lessons learned, coupled with hopes for the new Biden administration, to carry on as best they can.
Reprinted courtesy of
Jim Parsons, Engineering News-Record and
Aileen Cho, Engineering News-Record
Ms. Cho may be contacted at choa@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Predicting the Future of Texas’s Grid Is a Texas-Sized Challenge
June 27, 2022 —
Nathaniel Bullard - BloombergA little more than a year after a paralyzing winter freeze, the Texas power market just experienced the stress of extreme heat. Last week, power prices in Houston briefly jumped above $5,000 per megawatt-hour as high temperatures coincided with a number of generators being offline for maintenance.
Yet a few days earlier, power prices in west Texas had been negative $883 dollars per megawatt-hour, because at the time wind generation was abundant and demand was low.
“Dynamic” is one way to describe the price swings within the Electric Reliability Council of Texas (Ercot), the grid that provides the majority of the state’s power. “Jarring” or “terrifying” might be other words for it, particularly for those buying power in the spot market.
Read the court decisionRead the full story...Reprinted courtesy of
Nathaniel Bullard, Bloomberg
Five Keys to Driving Digital Transformation in Engineering and Construction
January 02, 2019 —
Rob Phillpot - Construction ExecutiveEngineering and construction companies increasingly find themselves navigating an era of disruptive and transformative change driven by technology. And with the industry going strong and construction employment recently reaching a 10-year high, more companies recognize that it is time to embrace the efficiencies digital transformation brings, in large part to protect or enhance their competitive position.
A report from the Global Industry Council notes that modern technology is moving to the strategic center of E&C business models as part of an evolutionary process.
Reprinted courtesy of
Rob Phillpot, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of