More on the VCPA and Construction
February 01, 2023 —
Christopher G. Hill - Construction Law MusingsI have posted before regarding the intersection between the Virginia Consumer Protection Act (VCPA) and construction contracting in regard to residential construction projects. A case out of the Eastern District of Virginia District Court further discusses this intersection as it relates to design contracts that also include the procurement and installation of certain design elements post-design. The basic facts of Marcus v Dennis are as follows:
In October of 2018, Defendant Marlene Dennis, the owner of Marlene Dennis Design, LLC (“MDD”), operating out of Virginia, entered into a contract to provide design services and the procurement and installation of certain design elements for the Plaintiffs, Gregory and Jamie Marcus, at their Maryland home. The Marcuses agreed to $175 per hour to Dennis with a cap of a total of $100,000.00 for design consultation and furniture selection and procurement. The Marcuses also agreed that they would pay no more than $250,000.00 for furnishings, rugs, artwork, decorative lighting, and accessories. In November 2020, Dennis sent an invoice for $68,000.00 and informed the Plaintiffs that the total contract fees would be more than the $100,000.00 cap. After paying $124,722.41 in design fees, the Plaintiffs received an invoice for $255,5560.72 in January of 2021. Despite the cap of $250,000.00, the Plaintiffs wired $255,000.00 to Dennis while requesting the backup invoices for the material charges. After much effort and a threat of litigation, the Plaintiffs received documents from Dennis showing that Dennis inflated the costs of the materials prior to passing the costs along to the Marcuses. The Plaintiffs’ home was unfurnished and empty as of April 10, 2021, and the Marcuses had to hire and pay another design team over $85,000.00 to finish Dennis’ work. Needless to say, the Marcuses sued both Dennis and her firm for breach of contract, breach of fiduciary duty, and for violation of the VCPA. Dennis moved to dismiss the Complaint.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Construction Defect Fund Approved for Bankrupt Las Vegas Builder
February 11, 2013 —
CDJ STAFFA federal bankruptcy judge has given his approval to a fund set up to settle potential construction defect claims as a Las Vegas home builder, America West Development, works its way out of bankruptcy. The U.S. Trustee had objected to the trust fund's structure, and claimed that it was insufficiently independent from America West. Judge Mike Nakagawa found no legal objections to the trust.
The trust will be initially funded from $1.5 million of the $10 million that Lawrence Canarelli will be paying to buy back the company he founded. Construction defect claims against the company could possibly reach $20.9 million. The Las Vegas Review-Journal reports that the fund "could pick up funding from certain legal claims and insurance.
Read the court decisionRead the full story...Reprinted courtesy of
Floors Collapse at Russian University in St. Petersburg
February 27, 2019 —
The Associated Press - BloombergSt. Petersburg, Russia (AP) -- Part of the roof and several floors of university building in Russia's second-largest city collapsed Saturday, but officials say there were no casualties.
The Emergencies Ministry said the collapse at the Saint Petersburg National Research University of Information Technologies, Mechanics and Optics took place as construction work was underway. An investigation into criminal violation of construction safety has been opened.
Read the court decisionRead the full story...Reprinted courtesy of
The Associated Press, Bloomberg
Nebraska Court Ruling Backs Latest Keystone XL Pipeline Route
September 30, 2019 —
Tom Ichniowski - Engineering News-RecordAdvocates of the Keystone XL oil pipeline have won a victory in their long effort to construct the project, as the Nebraska Supreme Court upheld a state commission's 2017 finding that supported the project's latest route alignment through the state.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Ichniowski, ENRMr. Ichniowski may be contacted at
ichniowskit@enr.com
Texas Shortens Cut-Off Date for Suits Against Homebuilders Who Provide a 6-Year Written Warranty
June 26, 2023 —
Kim Altsuler - Peckar & Abramson, P.C.Summary of the new law as it pertains to builders of new homes:
The existing 10-year statute of repose for builders of new homes (the ultimate cut-off date for filing suit) has been shortened to 6 years if the builder provides a 1-2-6 written warranty (1-year workmanship and materials; 2-year plumbing, electrical and HVAC; 6-year structural).
Extended time to bring suit if written claim presented during the period of repose:
If a written claim for damages, contribution, or indemnity is presented to the builder during the applicable limitations period and the 6-year statute of repose applies, the time to sue is extended one year from the date the claim is presented. In practical effect, this means that if a written claim is presented and the statute of repose expires before suit is filed, suit may still be filed provided it is within one year of the date the written claim was made.
When the new law goes into effect:
The new law is effective as of June 9, 2023 and applies to suits commenced on or after that date. However, if the contract under which the claim is brought was entered into before June 9, 2023, the former 10-year version of the statute of repose applies. In other words, the statute applies to contracts entered into on or after June 9, 2023, if the contract has at least a 1-2-6 warranty.
Read the court decisionRead the full story...Reprinted courtesy of
Kim Altsuler - Peckar & Abramson, P.C.Ms. Altsuler may be contacted at
kaltsuler@pecklaw.com
Touchdown! – The Construction Industry’s Winning Audible to the COVID Blitz
February 08, 2021 —
Bill Shaughnessy, Jones Walker, LLP - ConsensusDocsCOVID-19 has changed the way we live, work, play football, and build. As with all of society (and our football leagues and teams), the construction industry was impacted over the last year through the implementation of new safety protocols in response to COVID-19. While some construction projects were delayed or put on hold, much of the construction industry was fortunate to continue to build throughout the pandemic. Building under COVID-19 safety protocols led contractors to “call an audible” in order to make up for lost time and to save costs. In doing so, many contractors started incorporating or expanding the use of under-utilized tools, resources, capabilities, and technology such as pre-fabrication, and modular construction, while at the same time reexamining planning methods, monitoring critical schedule activities, and ways to better execute construction.
In many ways, the effects of COVID-19 safety protocols and measures implemented by contractors in the past year have led to more efficient and cheaper construction projects now and for the future. So, it is not surprising as we turn our calendars to 2021 that contractors can expect these tools, resources, and technologies to be utilized more in the years ahead, even once the pandemic subsides. This article highlights some of the “positive” effects of COVID-19 on projects and highlights several ways contractors attempted to increase efficiency and reduce costs in response to the pandemic.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Shaughnessy, Jones Walker, LLPMr. Shaughnessy may be contacted at
bshaughnessy@joneswalker.com
Haight Attorneys Selected to 2018 Southern California Rising Stars List
June 13, 2018 —
Haight Brown & Bonesteel LLPHaight proudly announces that Partner Michael C. Parme and attorneys Frances Ma and Kristian B. Moriarty have been selected to the 2018 Southern California Rising Stars list.
Super Lawyers, a Thomson Reuters business, is a rating service that lists outstanding lawyers from a wide range of practice areas who have attained a high-degree of peer recognition and professional achievement. The selection process is multi-phased and includes independent research, peer nominations and peer evaluations.
Read the court decisionRead the full story...Reprinted courtesy of
Haight Brown & Bonesteel LLP
New Jersey Appellate Decision Reminds Bid Protestors to Take Caution When Determining Where to File an Action
March 13, 2023 —
Brian Glicos & Nicholas J. Zaita - Peckar & Abramson, P.C.On February 21, 2023, the New Jersey Appellate Division held that University Hospital is not a “state administrative agency” and, therefore, the Appellate Division does not have original jurisdiction to determine the merits of an action commenced by an unsuccessful bidder to challenge the award of a contract. In re Protest of Contract for Retail Pharmacy Design, Constr., Start-up & Operation, Request for Proposal No. UH-P20-006, A-1667-20, 2023 WL 2125002 (N.J. Super. Ct. App. Div. Feb. 21, 2023).
Pursuant to Rule 2:2-3(a)(2) of New Jersey’s Rules of Court, final decisions or actions of any state administrative agency or officer may be appealed directly to the Appellate Division as of right. Accordingly, where an unsuccessful bidder chooses to challenge the award of a contract issued by, for example, the New Jersey Department of Transportation, the unsuccessful bidder must file its action directly with the Appellate Division. On the other hand, where an unsuccessful bidder wishes to challenge a contract award made by a local municipality (among a slew of other public entities), the Superior Court Law Division maintains original jurisdiction over the dispute.
Reprinted courtesy of
Brian Glicos, Peckar & Abramson, P.C. and
Nicholas J. Zaita, Peckar & Abramson, P.C.
Mr. Glicos may be contacted at bglicos@pecklaw.com
Mr. Zaita may be contacted at nzaita@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of