Texas Court Requires Insurer to Defend GC Despite Breach of Contract Exclusion
December 19, 2018 —
Ashley L. Cooper - Saxe Doernberger & Vita, P.C.In Mt. Hawley Insurance Co. v. Slay Engineering, et al.,1 a Texas federal court ruled in favor of a general contractor, finding that its insurer had a duty to defend it in a construction defect case filed by the owner. The decision adds more clarity to the interpretation of the subcontractor exception to the “Damage to Your Work” exclusion as well as the Breach of Contract exclusion, which has been the subject of several cases coming out of Texas over the past decade.
Read the court decisionRead the full story...Reprinted courtesy of
Ashley L. Cooper, Saxe Doernberger & Vita, P.C.Ms. Cooper may be contacted at
alc@sdvlaw.com
Enforceability Of Subcontract “Pay-When-Paid” Provisions – An Important Update
June 15, 2020 —
Patrick McNamara - Porter Law GroupA California Court of Appeals opinion published earlier this month brings a change to payment bond claims brought by unpaid subcontractors and suppliers. The decision (Crosno Construction, Inc. v. Travelers Casualty and Surety Company of America) places limitations on a payment bond surety’s ability to rely on subcontract “pay-when-paid” language, stating that a payment provision typically found in subcontracts is contrary to the “reasonable time” statutory requirement and will not be enforced. This represents a major shift in California construction payment bond claim rights.
Plaintiff Crosno Construction, Inc. (“Crosno) was a subcontractor to general contractor Clark Brothers (“Clark”), who was principal on a public works payment bond issued by Travelers. The owner was a public agency district (“District.”) Crosno had completed most of its subcontract work when a dispute between District and Clark arose, causing the project to stop. Crosno then sought payment through a payment bond claim against Travelers. Travelers denied the claim, relying on the subcontract’s payment provisions and asserting the defense that it had no obligation to pay on the bond claim because the litigation between Clark and the District had not yet reached its conclusion.
Subcontract. The subcontract between Clark and Crosno contained a “pay-when-paid” provision stating that Clark would pay Crosno within a reasonable time after receiving payment from the District. In defining “a reasonable time,” the subcontract language provided that the time for payment “in no event shall be less than the time [Clark] and [Crosno] require to pursue to conclusion their legal remedies against [District] or other responsible party to obtain payment.”
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at
pmcnamara@porterlaw.com
Thank Your Founding Fathers for Mechanic’s Liens
August 04, 2015 —
Craig Martin – Construction Contract AdvisorYep, our founding fathers, Thomas Jefferson and James Madison specifically, Craig Martin, Construction Attorney Lamson Dugan & Murray LLPwere responsible for proposing the first mechanic’s lien laws in the United States. Mechanic’s liens were not a new concept when the first law was passed in the United States; France, Spain and other countries already had them. But, in England, where landownership was limited to the upper classes, the concept of giving a tradesman an interest in the land for his labors was a truly foreign concept.
The Early Years—Pre Mechanic Lien
In the 1700s, there was no right to a mechanic’s lien. The possession of land was never deemed to be changed by its improvement and the laborer or material supplier was held to have acquired no right of lien in the property. The only remedy the laborer or material supplier had was to bring an action against the land owner. If the laborer or material supplier obtained a judgment, he would acquire the lien of a judgment creditor. A Treatise on the law of Mechanics’ Liens on Real and Person Property, 1893.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Wake County Justice Center- a LEED Silver Project done right!
October 01, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaYesterday evening, I had the privilege of attending the Triangle USGBC’s “Talk & Walk” at the Wake County Justice Center. The 576,996 square foot Justice Center was completed 6 months early and over 30 million under budget. (The final cost, including soft costs, came in at ~$141,000,000). Now that’s what I call a LEED project done right!
Interestingly, the County did not endeavor for a LEED Silver rating– the plan was to aim for a Certification. However, as the process unfolded, the Team kept meeting the goals and points for a Silver certification without any appreciable additional costs.
The end result? An “iconic but energy efficient building,” according to Tim Ashby, current Wake County Facilities Project Manager. Tim was initially involved in the Project while working at O’Brien Atkins, which served as the architecture firm for the Project under the direction of Architect Andrew Zwiacher.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Insureds' Experts Insufficient to Survive Insurer's Motion for Summary Judgment
October 17, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe magistrate recommended that insurer's motion for summary judgment be granted due to the insureds' expert's inability to present genuine issues of material fact. Walker v. Century Sur. Co., 2023 U.S. Dist. LEXIS 142408 (E.D. Texas July 17, 2023).
The insureds' property sustained damage from Hurricane Laura. Colonial Claims inspected the property for Century and reported that a portion of the roof was damaged by the hurricane. Century paid insureds $2,212,34. Van Fisher, an engineer with Envista Forensics, then inspected the interior of the property on Century's behalf. Fisher reported that there was some covered interior damage caused by a leak from a storm-created opening in the roof. However, Fisher further reported that there was other interior damage caused by existing water leaks not attributed to the hurricane and thus not covered by the policy. Century then paid the insureds an additional $485.05 based on Fisher's inspection.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Defect Claim Did Not Harm Homeowner, Court Rules
September 30, 2011 —
CDJ STAFFThe Minnesota Court of Appeals has ruled in Creswell v. Estate of Howe, a case in which a woman bought a home and then sued the seller’s estate, both sets of real estate agents, and the homeowner’s association over construction defects. A district court ruled against her, granting summary judgment to the other parties.
After buying a townhome “as is,” Catherine Creswell claims to have shared a thought with her agent that the homeowners association was, in the words of her agent, “trying to hide something.” Later, Creswell found that a few days before her closing, the board had discussed problems with “roofs, siding and soundproofing of the townhomes.” The court noted that “it was clear from the documents that appellant [Creswell] received that the association had known about various construction defects for many years, some of which affected [her] unit.”
Creswell initially sued the estate, the man who negotiated the sale for his mother’s estate, the real estate companies and the agents involved, the homeowners association, and four board members. Later she sued for punitive damages, dropped a claim for interference with contractual relations, and dismissed her claims against the individual board members. The court dismissed all of Creswell’s claims awarding costs to those she sued.
The appeals court has affirmed the decision of lower court, noting that Creswell “did not provide us with any argument why the district court erred in dismissing her unjust-enrichment, breach of contract, or rescission claims against the various respondents.” Nor did she provide evidence to support her claims of “breach of duty, fraud, and violation of consumer protection statutes.”
The court noted that Creswell could not sue the homeowners association over the construction defects because she “failed to prove that she was damaged by the association’s nondisclosure.” The court noted that “there are no damages in this case,” as Creswell “was never assessed for any repairs, she had not paid anything out-of-pocket for repairs, and she has presented no evidence that the value of her individual unit has declined because of the alleged undisclosed construction defects.”
The court granted the other parties motion to dismiss and denied Creswell’s motion to supplement the record. Costs were awarded to the respondents.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Intel's $20B Ohio 'Mega-Site' is Latest Development in Chip Makers' Rush to Boost US Production
January 24, 2022 —
Jim Parsons - Engineering News-RecordIntel’s recently announced Ohio chip manufacturing complex could begin construction by the end of this year, setting the stage for a long-term, multibillion-dollar development effort many experts have likened to building a small city from scratch.
Reprinted courtesy of
Jim Parsons, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Miller Act Statute of Limitations and Equitable Tolling
July 11, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to a Miller Act payment bond claim, there is a one-year statute of limitations—“The Miller Act contains a statute of limitations provision that requires actions to ‘be brought no later than one year after the day on which the last of the labor was performed or material was supplied by the person bringing the claim.’” U.S. f/u/b/o Techniquex Specialty Flooring, Inc., v. Philadelphia Indemnity Ins. Co., 2022 WL 169070, *3 (M.D.Penn. 2022) (citing the Miller Act).
There is an argument, albeit a difficult one, to support an equitable tolling of the one-year statute of limitations. This would be an argument filed when the one-year statute of limitations expires, but there is reason for missing the statute of limitations caused typically by the overt misleading of the defendant (surety/bond-principal):
“Equitable tolling functions to stop the statute of limitations from running where the claim’s accrual date has passed.” “Equitable tolling is appropriate in three situations: (1) when the defendant has actively misled the plaintiff respecting the facts which comprise the plaintiff’s cause of action; (2) when the plaintiff in some extraordinary way has been prevented from asserting his rights; and (3) when the plaintiff has timely asserted his rights in the wrong forum.” The first ground for equitable tolling“appears to be the same, in all important respects” to equitable estoppel, which “excuses late filing where such tardiness results from active deception on the part of the defendant” and “what courts describe as ‘equitable tolling’ is encompassed by the latter two parts of our Circuit’s doctrine.” The extraordinary circumstances standard may be met “where the defendant misleads the plaintiff, allowing the statutory period to lapse; or when the plaintiff has no reasonable way of discovering the wrong perpetrated against her …”
Tehniquex, supra, at *5 (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com