Inverse Condemnation and Roadwork
October 09, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPThe following case, issued yesterday by the Georgia Supreme Court, addresses the accrual of the statute of limitations on a claim of inverse condemnation based on nuisance.
Wise Bus. Forms, Inc. v. Forsyth Cnty., S22G0874, 2023 WL 6065278 (Ga. Sept. 19, 2023)
We granted certiorari in this case to clarify the standards for determining when a claim for inverse condemnation by permanent nuisance accrues for purposes of applying the four-year statute of limitation set forth in OCGA § 9-3-30 (a).
[. . .]
Permanent nuisance cases vary in relation to when the alleged harm to a plaintiff’s property caused by the nuisance becomes “observable” to the plaintiff. Forrister, 289 Ga. at 333 (2), 711 S.E.2d 641. In some cases, the harm to the plaintiff’s property is immediately observable “upon the creation of the nuisance.” Id. For example, where a landowner or governmental agency “erects a harmful structure such as a bridge or conducts a harmful activity such as opening a sewer that pollutes a stream,” and it is immediately obvious that the structure or activity interferes with the plaintiff’s interests, the plaintiff must file “one cause of action for the recovery of past and future damages caused by [the] permanent nuisance” within four years of the date the structure is completed or the harmful activity is commenced. Id. at 333-336 (2) and (3), 711 S.E.2d 641 (citing Restatement (Second) of Torts §§ 899 and 930). Phrased another way, where the “construction and continuance” of the permanent nuisance at issue is “necessarily an injury, the damage is original, and may be at once fully compensated. In such cases[,] the statute of limitations begins to run upon the construction of the nuisance.” City Council of Augusta v. Lombard, 101 Ga. 724, 727, 28 S.E. 994 (1897).
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
“If It Walks Like A Duck . . .” – Expert Testimony Not Always Required In Realtor Malpractice Cases Where Alleged Breach Of Duty Can Be Easily Understood By Lay Persons
April 17, 2019 —
David W. Evans & Renata L. Hoddinott - Haight Brown & Bonesteel LLPIn Ryan v. Real Estate of the Pacific, Inc., et al. (No. D072724, filed 2/26/19), the Fourth Appellate District reversed a trial court’s granting of summary judgment and finding that expert testimony is not required in a professional negligence action where the claimed acts or omissions are within the understanding of a lay person.
Daniel and Patricia Ryan hired Defendants David Schroedl, David Schroedl & Associates, and Real Estate of the Pacific, Inc., doing business as Pacific Sotheby’s International Realty to list, market, and sell their property. During an open house, the Ryans’ neighbor informed Defendant David Schroedl that he planned significant construction on his own property which would impact the Ryans’ property including, but not limited to, building a large addition that would obstruct the property’s westerly ocean view. Schroedl never disclosed this information to the Ryans or to the subsequent purchasers of the Ryans’ property. The day after escrow closed, the new owners’ interior decorator spoke with that neighbor who again explained his extensive remodeling plans.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Renata L. Hoddinott, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Ms. Hoddinott may be contacted at rhoddinott@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Do You Have the Receipt? Pennsylvania Court Finds Insufficient Evidence That Defendant Sold the Product
December 23, 2024 —
Gus Sara - The Subrogation StrategistIn State Farm Fire & Cas. Co. v. Coway USA, Inc., No. 22-cv-3516, 2024 U.S. Dist. LEXIS 192849, the United States District Court for the Eastern District of Pennsylvania (District Court) considered whether the plaintiff produced sufficient evidence to establish that the defendant sold and/or marketed a product and, thus, could be held liable for an alleged defect in the product. The plaintiff, a subrogating insurance carrier, brought strict product liability and breach of warranty claims against the defendant—the installer of a bidet in its insured’s home—claiming that the defendant also marketed and sold the bidet. The sole evidence to support a finding that the defendant sold the bidet was the homeowner’s testimony that she bought the product from the installer. The court found that the insured’s testimony, without any documentation or other corroborating evidence, was insufficient to establish that the defendant sold the product. Since proof of a sale is a required element for strict product liability and breach of warranty claims, the District Court granted the defendant’s motion for summary judgment, dismissing the case.
This case involved a water loss to the Pennsylvania residence of Mikyung Kim and her husband Adrian Kim (collectively, the Kims) that was discovered in April 2021. An investigation revealed that the water loss originated from the failure of a bidet for a toilet in the second-floor bathroom. The Kims alleged that defendant, Coway USA, Inc. (Coway), sold the bidet and installed it around 2010. An employee of the plaintiff’s liability expert, a materials engineer, opined that a T-connector—a plastic valve that regulates the flow of water to and through the bidet—failed due to overtightening of the connector during the manufacturing process.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Untangling Unique Legal Issues in Modern Modular Construction
September 09, 2024 —
Chad Theriot & Brad Sands - Construction ExecutiveModular construction has grown significantly over the last few years and shows no signs of slowing down. This construction method is a departure from traditional approaches where all construction activity occurs onsite. Modular construction involves building standardized project components—usually in an offsite, controlled environment—which are then transported and assembled at the project site. Offsite construction generally allows for better quality control and economic efficiency, as it can utilize an assembly-line process. Modular fabrication can also centralize skilled labor in regions with lower labor costs.
Establishing each party's expectations upfront is always important, but even more so in modular construction since much of the construction activity is performed away from the ultimate project site. This requires extensive coordination among designers, fabricators, installers and owners to ensure construction, testing and quality progresses accordingly. Every field change and design clash could have an exponential impact on the modular fabrication efficiencies given the assembly-line approach and remote nature of modular work.
Reprinted courtesy of
Chad Theriot & Brad Sands, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Housing Inflation Begins to Rise
February 25, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Kathleen Madigan writing for The Wall Street Journal, “inflation remains muted at the start of 2014” except in one category: housing. Madigan stated that housing costs were “worth watching.”
The “owners’ equivalent rent index had been rising at a steady pace through most of 2012 and 2013, with 12-month percent changes hovering around 2%” however, “the pace picked up” at the end of last year.
Read the court decisionRead the full story...Reprinted courtesy of
Flexible Seattle Off-Ramp Would Retain Shape in Quake
November 23, 2016 —
Tim Newcomb – Engineering News-RecordMoving from the lab to the field, a highway off-ramp bridge under construction in Seattle features memory-retaining metal rods and bendable concrete designed to provide the structure with flexibility sufficient to withstand a major seismic event.
Read the court decisionRead the full story...Reprinted courtesy of
Tim Newcomb, Engineering News-RecordEngineering News-Record may be contacted at
ENR.com@bnpmedia.com
Appeals Court Reverses Summary Judgment over Defective Archway Construction
February 10, 2012 —
CDJ STAFFA judge has ruled that a plaintiff can go forward with her suit that she was injured by a defective archway during a birthday party. A three-judge panel of the California Court of Appeals issued this ruling on January 23, 2012, in the case of Trujillo v. Cosio.
Ms. Trujillo attended a birthday party at the home of Maria Cosio and Joel Verduzco. A piñata was hung between a tree and a brick archway. Ms. Trujillo went to get candy that had fallen from the piñata, during which the archway fell on her hand. Subsequent examination of the archway showed that it had not been “properly anchored to the supporting pillars to protect the arch from falling.”
Ms. Cosio and Mr. Verduzco argued that they could not have been aware of the defective nature of the archway’s construction, as it had been built at the request of the prior property owner. The structure was constructed without building permits. Mark Burns, a civil engineer testifying for the plaintiff, said that “a reasonable property owner would have thoroughly tested the archway to ensure it was capable of withstanding such horizontal forces before allowing children to enter into the area.” Mr. Burns noted that twenty rope pulls would have been sufficient to demonstrate the structure’s instability.
The trial court rejected Mr. Burn’s statements, finding that the respondents did not have any knowledge of the defect and that a visual inspection should have sufficed. The court noted that this a triable issue, whether visual inspection suffices, or whether the property owners should have done as Mr. Burns suggested and yank a rope twenty times. The court noted that “although a jury may ultimately disagree with Burn’s opinion, it was supported by sufficient foundation and was not speculative.”
The opinion was written by Judge Flier, with Judges Rubin and Grimes concurring.
Read the court’s decison…
Read the court decisionRead the full story...Reprinted courtesy of
Scope of Alaska’s Dump Lien Statute Substantially Reduced For Natural Gas Contractors
March 16, 2020 —
Trevor Lane - Ahlers Cressman & Sleight PLLCIn All American Oilfield, LLC v. Cook Inlet Energy, LLC,[1] the Supreme Court of Alaska clarified and substantially reduced a natural gas contractor’s ability to secure a preferred lien for its contribution to a natural gas well.
Alaska’s dump lien statute (AS § 34.35.140) authorizes a laborer to claim a lien for the amount owed for their labor in the production of a “dump or mass” of “extracted, hoisted and raised” matter from a mine. While Alaska’s dump lien statute is one of three Alaskan statutes allowing laborers to attach liens to mines, mining equipment or minerals,[2] the dump lien statute is unique because it is prior and preferred over other liens, increasing the laborer’s chance of being paid in a bankruptcy proceeding.
Attaching a lien to a “dump or mass” of hard-rock minerals piled outside a mine or oil stored in a tank is relatively straightforward. However, natural gas is typically left in its natural reservoir until removed by a pipeline that carries the gas to a location far from the mine. Natural gas is not extracted and stored in a “dump or mass” like other minerals, and until August 2019, controversy existed over how—or if—the dump lien statute could be used by natural gas contractors.
Read the court decisionRead the full story...Reprinted courtesy of
Trevor Lane, Ahlers Cressman & Sleight PLLCMr. Lane may be contacted at
trevor.lane@acslawyers.com