Summary Judgment for Insurer Reversed Based on Expert Opinion
May 30, 2022 —
Tred R. Eyerly - Insurance Law HawaiiAfter the trial court discounted the insured's expert witness and granted summary judgment to the insurer, the Florida District Court of Appeal reversed. Morales v. Citizens Prop. Ins. Corp., 2022 Fla. App. LEXIS 1831 (Fla. Ct. App. March 15, 2022).
The insureds' property was allegedly damaged by Hurricane Irma in 2017. They filed a claim with Citizens. Citizens sent its adjuster and eventually denied the claim because the policy did not cover damages caused by wear and tear. Further, there was no coverage for loss caused by "rain . . . unless a covered peril first damages the building causing an opening in a roof or wall and the rain . . . enters through this opening."
The insureds sued and Citizens moved for summary judgment. At the hearing, Citizens' expert, a civil engineer, concluded that there were no storm-created openings in the roof. The insureds engaged a licensed contractor, Steven Delgado, who stated that he found significant damage to the roofing system and water intrusion through the roof. He observed loose shingles which were most likely damaged during Hurricane Irma, allowing for high winds and airborne debris to create small openings permitting water intrusion.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
When Is a Project Delay Material and Actionable?
January 11, 2022 —
Rick Erickson - Snell & Wilmer Real Estate Litigation BlogWelcome to 2022! This year, the construction industry will undoubtedly reflect on the last two years as unprecedented times plagued by construction project delays. The COVID-19 pandemic contributed to suspension of work and closure of construction projects worldwide in 2020. The end of 2021 brought additional delays caused by an inexplicable clog in the supply chain of construction materials. The combined impact of these events on project milestones and completion deadlines led our clients to ask, with unusual and particular urgency, who is liable for such delays and how do contracting parties lessen the consequences from such unexpected and uncontrollable delays.
Granted that project delays are nothing new or unusual. They were common enough before inflation caused shipping complications and pandemic decimated the construction labor force. All delays, whatever the source, variably cause loss to all players on a construction project. But not all delays matter when it comes to claims and remedies available to the contracting parties in dispute resolution, where the determinative focus is on material delays impacting the entire project and on delays the claimant can credibly prove.
Most, if not all, jurisdictions interpret actionable delays from the contract documents for the project. The contract is definitely where you should start before pursuing any delay remedies. Delay remedies may be a time extension only, or a time extension plus your additional general conditions. Some delay remedies may be barred by the contract’s express terms and may be enforced adversely by the courts when such contract terms are indisputable. See Quinn Constr. v. Skanska USA Bldg., Inc., 730 F. Supp. 2d 401, 411 (D.C. Pa. 2010) (enforcing the subcontractor’s contractual waiver of claims for delay and disruption damages). On the other hand, delay damages that are expressly allowed by the contract—like overtime necessitated by the delays—are usually actionable and recoverable. Id. However, not only the contract terms, but applicable law, may affect the outcome.
Read the court decisionRead the full story...Reprinted courtesy of
Rick Erickson, Snell & WilmerMr. Erickson may be contacted at
rerickson@swlaw.com
Prison Time and Restitution for Construction Fraud
February 14, 2013 —
CDJ STAFFFederal prosecutors have obtained prison sentences and fines for the two leaders of a construction kickback scheme. Others are awaiting sentencing. The Chicago Sun-Times reports that John Paderta the former president of Krahl Construction has been sentenced to five years in prison and must pay $10 million in restitution. His executive vice president, Doug Harner will be spending five years in prison and has been ordered to pay $9.6 million in restitution.
Paderta and Harner overbilled two clients on renovation projects, giving kickbacks to employees at the client companies. Two employees of these client companies have pled guilty. A further five employees of the three companies have admitted that they were involved in the fraud. They are yet to be sentenced.
Read the court decisionRead the full story...Reprinted courtesy of
Connecticut Federal District Court Again Finds "Collapse" Provisions Ambiguous
March 22, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe Federal District Court for the District of Connecticut has issued several decisions of late finding coverage for collapse despite the building not being reduced to rubble. The latest decision in this series is Metsack v. Liberty Mutual Fire Ins. Co., 2017 U.S. App. LEXIS 24062 (D. Conn. Feb. 21, 2017).
The Metsack's property was insured by Allstate under policies issued from June 27, 1991 to September 9, 2009. From September 2009 to present, Liberty Mutual issued property policies to the insureds. Mr. Metsack built the insureds' home in 1992. The concrete basement walls used concrete supplied by JJ Mottes Company.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Mitigate Construction Risk Through Use of Contingency
April 26, 2021 —
Laurie A. Stanziale - Construction ExecutiveMitigation of risk and costs in a construction project are always priorities for owners. In some contracts, in particular, Guaranteed Maximum Price contracts, some of those monetary risks are shifted to the contractor. Contingency is important because it allows for money to be in the budget for the unexpected and to keep the project moving, which benefits everyone.
WHAT IS CONTINGENCY?
Contingency is an amount of money built into the contractor’s price to complete the project to address unforeseen (although sometimes very common) costs that arise. This sum of money is generally referred to as the contractor’s contingency. The amount of the contingency is a balance struck between having money on hand to address the unexpected while also not unnecessarily tying up money that could otherwise be used for the project. Contingency is typically 5-10% of the hard costs. However, how the money is actually allocated during the project is not always well thought out, which can be the source of problems during the project.
The contractor’s contingency is not to be confused with an owner’s contingency (or reserve) which is outside of the contractor’s budget and generally used for owner driven changes to the project, such as changes to scope, design and schedule.
Reprinted courtesy of
Laurie A. Stanziale, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Celebrities Lose Case in Construction Defect Arbitration
May 26, 2011 —
CDJ STAFFAn arbitration panel has ruled that problems with the Idaho home of actors Tom Hanks and Rita Wilson were not due to construction defects but rather to “poor design and bad architectural advice.” The couple had settled with the architectural firm, Lake Flato of San Antonio, Texas for $900,000 and was subsequently seeking $3 million from Storey Construction of Ketchum, Idaho.
Problems with the couple’s home “included leaking roofs, inadequate drainage, fireplaces that did not vent properly and an inadequate air-conditioning system. In 2003, sliding snow from the roof damaged kitchen windows and roof components.”
The arbitration panel, according to the report in the Idaho Mountain Express and Guide, noted that “Hanks and Wilson were responsible for the full $167,623 cost of arbitration, but further denied a Storey Construction counterclaim that alleged Hanks and Wilson filed their claim out of malice.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Failing to Pay Prevailing Wages May Have Just Cost You More Than You Thought
April 01, 2015 —
Garret Murai – California Construction Law BlogMechanics lien claims, payment bond claims, stop payment notice claims, delay claims, defect claims, abandonment claims . . .
With the variety of claims unique to construction projects it’s easy to forget that construction disputes are simply a category of business disputes in which broader business-related torts apply.
In Roy Allan Slurry Seal, Inc. v. American Asphalt South, Inc., Case No. B255558 (February 20, 2015), the California Court of Appeal for the Second District held for the first time that a second-place bidder on a public works contract may sue a winning bidder – who failed to pay its workers prevailing wages – under the business tort of intentional interference with prospective economic advantage.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Include Materials Price Escalation Clauses in Construction Clauses
December 26, 2022 —
Robert Alfert Jr. - Construction ExecutiveThe construction sector has been in a bull market for an unprecedented period of time. With the novel impacts from the coronavirus—and all the associated side effects, such as government moratoria, shipping delays and materials availability—we are now in a market of extreme volatility in pricing, inflation and increasing capital finance rates. And yet the construction sector continues to plow forward despite uncertainty, producing critical infrastructure, and much necessary housing, among other projects. The signs are that this trend will continue at least through Q1 of 2023, and likely beyond that, especially when you factor into the equation the many billions of dollars being placed into the market through the Bipartisan Infrastructure Law.
It is not surprising, therefore, that the number one issue in construction contracts in 2022 is how parties handle inflation and materials cost escalations in existing contracts and in the negotiations for new contracts. There is no other issue more heavily negotiated, often disputed and hotly debated in the construction sector today.
Reprinted courtesy of
Robert Alfert Jr., Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.