Gru Was Wrong About the Money: Court Concludes that Lender Owes Contractor “Contractually, Factually and Practically”
November 07, 2022 —
Matthew DeVries - Best Practices Construction LawThis weekend was all about
The Rise of Gru. I love Gru so much that when my children ask for money, my best Gru-like voice belts back: “Now, I know there have been some rumors going around that the bank is no longer funding us….In terms of money, we have no money.” And that’s precisely what many lenders say on distressed projects when the owner fails to make final payment and the contractor looks to the bank for funding: “We have no money for you contractor!”
In
BCD Associates., LLC v. Crown Bank, CA No. N15c-11-062 (Super. Ct. Del, May 2, 2022), the trial court found that when a bank pays a contractor directly, it can create a legally binding relationship subject to the terms of the construction loan agreements with the owner.
The project involved a $13m construction loan between the lender and the owner to renovate a hotel. The owner and contractor entered into an AIA Contract for the construction management services. During construction the contractor would submit payment applications to the lender, who would review and approve the invoices for payment. The lender then would pay 90% of the approved payment application and hold back the remaining 10% as retainage. The contractor was supposed to be paid the final retainage upon completion, which it did not receive in accordance with the terms of the AIA Contract.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew DeVries, Burr & Forman LLPMr. DeVries may be contacted at
mdevries@burr.com
Construction Litigation Roundup: “Sudden Death”
October 17, 2023 —
Daniel Lund III - LexologyIt’s not football, though. Rather, just when you thought it was safe in Louisiana to wait to file a garden-variety construction contract payment claim, an appellate court slams the door on it – applying a statute of “repose” to your claim.
“Personal actions” – such as an action on contract – are generally subject in Louisiana to a 10-year “liberative prescription,” the applicable statute of limitations pursuant to Louisiana Civil Code article 3499.
Like some other states, Louisiana has a statute of “repose” – imposing “peremption” rather than prescription for claims having to do with construction projects – limiting those claims (generally speaking) to five years post-completion. Like other statutes of “repose,” Louisiana Revised Statute 9:2772 provides that claims on construction projects may not be filed after five years, a duration which is not subject to interruption or extension.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
COVID-19 Is Not Direct Physical Loss Or Damage
April 13, 2020 —
Joseph Blyskal, Dennis Brown & Michelle Bernard - Gordon & Rees Insurance Coverage Law BlogIs a cash register that is not being used damaged property? When you need to wash a table, a chair, or a section of flooring with readily available cleaning products to make them safe and useable, are you repairing damaged property? Is a spilled cup of coffee waiting to be wiped up actual damage to the premises? If your customers stay home to help stop the spread of a virus, has there been a physical loss inside your shuttered store or restaurant?
The insuring agreements typically found in commercial property insurance policies require “direct physical loss of or damage to” covered property as the triggering event. Without establishing direct physical loss or damage a policyholder cannot meet its burden to trigger coverage for a purely economic loss of business income resulting from shuttering its business due to concerns over exposure to—or even the actual presence of—COVID-19. Despite this well-understood policy language, it is already beyond question that insurers will confront creative—albeit strained—arguments from policyholder firms attempting to trigger coverage for pure economic loss. The scope of the human and economic tragedy we all face will be matched by the scope of the effort to force the financial harm onto insurance companies.
The plaintiffs in what appears to be the first-filed case seeking a declaratory judgment in the context of first-party insurance coverage rely on the assertion that “contamination of the insured premises by the Coronavirus would be a direct physical loss needing remediation to clean the surfaces” of its establishment, a New Orleans restaurant, to trigger coverage for business interruption.[1] See Cajun Conti, LLC, et. al. v. Certain Underwriters at Lloyd’s, London, et. al. Civil District Court for the Parish of Orleans, State of Louisiana. The complaint alleges that the property is insured under an “all risk policy” defining “covered causes of loss” as “direct physical loss.” The plaintiffs rely on the alleged presence of the virus on “the surface of objects” in certain conditions and the need to clean those surfaces. They go so far as to claim that “[a]ny effort by [the insurer] to deny the reality that the virus causes physical damage and loss would constitute a false and potentially fraudulent misrepresentation. . . .”
Reprinted courtesy of Gordon & Rees attorneys
Joseph Blyskal,
Dennis Brown and
Michelle Bernard
Mr. Blyskal may be contacted at tblatchley@grsm.com
Mr. Brown may be contacted at dbrown@grsm.com
Ms. Bernard may be contacted at mbernard@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of
Louisiana Court Applies Manifestation Trigger to Affirm Denial of Coverage
June 10, 2015 —
Tred R. Eyerly – Insurance Law HawaiiApplying the manifestation trigger, the Louisiana Court of Appeal affirmed denial of coverage where the property damage manifested after the policy period expired. Landry v. Williamson, 2015 La. App. Unpub. LEXIS 213 (La. Ct. App. May 1, 2015).
On August 28, 2002, the Burkarts purchased a home from the Williamsons. One month later, water started leaking into the home during periods of rainfall. Suit was filed against the contractor, who was insured by Scottsdale. Scottsdale, who was added as a defendant, filed a motion for summary judgment, asserting that it did not insure the developer at the time the alleged property damage occurred. Scottsdale's policy expired on August 1, 2002. The trial court granted Scottsdale's motion, finding coverage under its policy was not triggered because no property damage occurred during the policy period.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Great Skyscraper Comeback Skips North America
February 05, 2015 —
Patrick Clark – BloombergTall buildings are back. Developers around the globe completed a record 97 buildings of at least 200 meters (656 feet) in height in 2014, according to a new report from the Council on Tall Buildings and Urban Habitat, as size-obsessed builders got back on a growth track after a two-year skyscraper dip.
It’s not hard to explain the pattern. A typical skyscraper takes two to four years to finish, says report co-author Daniel Safarik. Work back from the year of completion, and the global financial crisis looks like an easy explanation for the drop-off in tall buildings. If you thought it was hard to get a home loan in 2009, imagine asking bankers to finance a gravity-and-wind-defying symbol of luxury, industry, and capitalist will. Especially, as Bloomberg Businessweek’s Bryant Urstadt pointed out, since supertall buildings are notorious for being hard to fill with tenants. (It’s worth noting that “tall” isn’t a technical term, though “supertall,” which is used to describe buildings more than 300 meters tall, is. And construction schedules vary. The Ryugyong Hotel in Pyongyang, North Korea, planned for 330 meters, has been under construction for 28 years, according to a CTBUH report last year.)
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Clark, Bloomberg
Design & Construction Case Expands Florida’s Slavin Doctrine
January 21, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to Amanda Baggett of Rogers Towers, Florida’s “Fourth District Court of Appeal appears to have expanded the Slavin doctrine in the context of design professional liability” in the case McIntosh v. Progressive Design and Engineering, Inc. (Jan. 7, 2015). McIntosh, a personal injury case, involved whether the design and construction of an intersection with multiple traffic signals in close proximity created confusion for drivers.
Baggett stated that McIntosh expanded the Slavin doctrine in two ways: “first, the ruling eliminates the requirement that the ultimate owner of a project accept the project before the Slavin doctrine may be invoked. Second, the decision applies the Slavin doctrine to completed and accepted design plans without regard to the completion of the project for which they were prepared.”
Read the court decisionRead the full story...Reprinted courtesy of
A Compilation of Quirky Insurance Claims
August 13, 2014 —
Beverley BevenFlorez-CDJ STAFFProperty Casualty 360 showcased five “nutty claims stories” based upon recollections by several insurance professionals.
Number four, subtitled, “The Case of the Soaked Survivalists,” described a claim by an elderly couple who “made a $350,000 water-damage claim after heavy rains and an inadequate sump pump ruined what they described as thousands of ‘valuable items’ in their storage area.” However, a claims adjuster discovered during the investigation that the area in question was actually a bomb shelter built during the Cold War era, and the so-called valuable items were actually “soap, toothpaste, canned goods, and more.” The insurer ended up settling for about $200,000.
Read the court decisionRead the full story...Reprinted courtesy of
Issuing Judgment After Confirmation of Appraisal Award Overturned
May 01, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe Florida Court of Appeal reversed and remanded the trial court's judgment in favor of the insured because after confirming the appraisal award, judgment was issued before the insurer could offer policy defenses. State Farm Florida Ins. Co. v. Hochreiter, 2023 Fla. App. LEXIS 743 (Fla. Ct. App. Feb. 3, 2023.
After a dispute arose over the scope and amount of damage suffered by the insureds' roof, they sued State Farm. State Farm responded to the complaint by demanding an appraisal, a stay of litigation, and an extension of time to respond to the complaint.
The trial court granted the demand and retained jurisdiction regarding post-appraisal matters once the appraisal was complete. The court further ordered State Farm to respond to the complaint within twenty days of the conclusion of the appraisal "if any issues remain." The order did not specify whether the issues that remained had to relate to the initial appraisal stage of the litigation or the subsequent stage during which the trial court had jurisdiction to adjudicate disputed issues related to coverage.
Read the court decisionRead the full story...Reprinted courtesy of