School System Settles Design Defect Suit for $5.2Million
October 01, 2013 —
CDJ STAFFA school district in New York State has settled a dispute with its architectural and engineering firm for $5.2 million. Greece School District alleged that the multi-million dollar remodel lead to a variety of problems due to design defects. The problems included leaking roofs, malfunctioning drainage systems, and problems with heating systems. Tetra Tech had one work at 20 schools in the district.
The state Comptroller audited the $119.5 million renovation project and concluded that haste in the planning resulted in costly changes. Prior to the lawsuit, the architectural and engineering firm managed to recoup about $200,000 on behalf of the school district for work that was defective.
Read the court decisionRead the full story...Reprinted courtesy of
A Tort, By Any Other Name, is Just a Tort: Massachusetts Court Bars Contract Claims That Sound in Negligence
March 20, 2023 —
Gus Sara - The Subrogation StrategistIn University of Massachusetts Building Authority v. Adams Plumbing & Heating, Inc., 2023 Mass. App. Unpub. LEXIS 28, 102 Mass. App. Ct. 1107, the Appeals Court of Massachusetts (Appeals Court) considered whether the lower court properly held that the plaintiff’s breach of contract and indemnification claims were time-barred by the statute of repose because they sounded in tort. The Appeals Court held that while the six-year statute of repose only applies to tort claims, they can also bar claims for breach of contract and indemnification if they sound in tort. The Appeals Court affirmed the lower court’s ruling, finding that the plaintiff’s breach of contract and indemnification claims were just negligence claims disguised as non-tort claims.
In 2013 and 2014, the University of Massachusetts (UMass) retained various contractors to renovate the dining hall for one of its campus buildings, which included the installation of new ductwork for the kitchen’s exhaust system. The dining hall opened for service in September 2014. In the Spring of 2018, it was discovered that the ductwork for the kitchen had collapsed. Further investigation revealed other deficiencies with the exhaust system. On December 1, 2020, UMass filed a lawsuit against various contractors, asserting negligence, breach of contract, and indemnification. The breach of contract claims alleged breach of express warranties.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Proving & Defending Lost Profit Damages
June 09, 2016 —
David Adelstein – Florida Construction Legal UpdatesI have written numerous articles regarding the challenge in proving
lost profit damages. Yes,
lost profits are a form of damages in business disputes, but they are a form of damages that are subject to a certain degree of
conjecture and speculation. For this reason,
lost profit evidence is oftentimes precluded from being presented at trial or lost profit damages are reversed on appeal. This is why it is imperative to ensure i’s are dotted and t’s are crossed when it comes to proving lost profit damages. It is also imperative, when defending a lost profit claim, to put on evidence and establish the speculative nature of the lost profit damages.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Virtual Reality for Construction
July 14, 2016 —
Aarni Heiskanen – AEC BusinessParadoxically, Virtual Reality (VR) technologies are still lagging behind the visions that people have for their use. However, VR has already demonstrated its capacity to change the ways we design, make decisions about, and produce built environments.
Is VR finally feasible?
Two AEC Hackathons and meetings with certain startups have made me think that Virtual Reality (VR) might finally break through in construction. There are two reasons for my belief. Firstly, 3D and building information modeling (BIM) are widely adopted in the industry. The idea of virtual buildings and environments is nothing new and has become very natural. Secondly, there’s a growing interest in Gaming and Entertainment VR investments. This will push the technology forward and make it affordable to consumers.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aarni@aepartners.fi
In Louisiana, Native Americans Struggle to Recover From Ida
August 07, 2022 —
The Associated Press (Rebecca Santana) - BloombergAlong Bayou Pointe-Au-Chien, La. (AP) -- Driving through her village along a southeastern Louisiana bayou, tribal official Cherie Matherne points out the remnants of house after house — including her own — wrecked nine months ago when Hurricane Ida roared through the Pointe-au-Chien Indian Tribe community.
Beige trailers from the Federal Emergency Management Agency and travel campers sit next to pilings that elevated homes 14 feet (4.3 meters) off the ground to protect them from flooding. But it was the wind that got them this time. For hours, the Category 4 hurricane tore off roofs and siding, ripped out insulation and scattered treasured belongings. It destroyed shrimp boats and tossed crab traps.
“It’s going to take years before people can get back to their lives. The majority of people are still at a standstill,” said Matherne, the tribe’s cultural heritage and resiliency coordinator.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
Excess Carrier Successfully Appeals Primary Insurer’s Summary Judgment Award
December 09, 2011 —
Tred R. Eyerly - Insurance Law HawaiiAlthough the excess carrier was given inadequate notice of the underlying arbitration, the trial court determined it shared responsibility with the primary carrier for the arbitration award. Finding disputed issues of fact, the Washington Court of Appeals reversed in Am. States Ins. Co. v. Century Surety Co., 2011 Wash. App. LEXIS 2488 (Wash. Ct. App. Oct. 31, 2011).
The primary insurer, American States, issued two liability policies to Professional Home Builders (PHB), a siding contractor. The policies were for successive years, 1998-1999 and 1999-2000. Each policy had annual limits of $1 million per occurrence. PHB also had a commercial excess liability policy for 1999-2000 with Century Surety Company.
PHB was sued by Residential Investment Partners (RIP) for construction defects after moisture entered the building envelope, causing decay and damage. Century’s expert determined the decay started before the 1999-2000 policy period.
RIP and PHB went to arbitration.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Counterpoint: Washington Supreme Court to Rule on Resulting Losses in Insurance Disputes
September 01, 2011 —
Douglas Reiser, Builders Council BlogThis is the fourth installment of posts on Vision One v. Philadelphia Indemnity, a Washington Supreme Court case touching on Washington construction and insurance law. After Williams v. Athletic Field got so much coverage, I wished that I had provided a forum for argument on Builders Counsel. While we await that opinion from the Supreme Court, I decided to let a few good writers have at Vision One here on the blog. Last week, attorney Chris Carr weighed in. Today, insurance expert David Thayer returns to give his final impression. David provided an initial peak at the case earlier this year. Thanks to both Chris and David for contributing to the debate.
In August 2011 the Washington Supreme Court will rule on a pair of joined cases that involve critical insurance coverage issues. The outcome of the ruling will impact a large swath of policyholders in Washington State including builders, developers, and homeowners to name a few.
The cases are Vision One vs. Philadelphia Indemnity Insurance and Sprague vs. Safeco. The Vision one case comes from Division Two of the Appellate Court which overturned a lower court decision in favor the plaintiff, Vision One. Division Two decided that the collapse of a concrete pour during the course of construction did not constitute a resulting loss due to faulty workmanship. They further went on to redefine efficient proximate cause in a way that is harmful to policyholders by broadening rather than narrowing the meaning of exclusionary language in Philadelphia’s Builders Risk Policy.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
A Word to the Wise: The AIA Revised Contract Documents Could Lead to New and Unanticipated Risks - Part II
October 16, 2018 —
George Talarico - Construction ExecutivePart I addressed general conditions, revised insurance terms, revisions that affect owner’s required insurance and revisions that affect contractor’s required insurance.
REVISIONS THAT AFFECT DISPUTE RESOLUTION
A seemingly minor but noteworthy change is to the definition of “Claim.” Under Section 15.1 a “Claim” is defined to:
- include a request for a modification of contract time; and
- exclude any requirement that an owner must file a claim to impose liquidated damages.
Notably, any request relating to contract time must be brought within the specified time period for Notice of Claim and in the prescribed manner. There are at least two traps for the unwary. First, even though email is regularly used for communications among the parties, the revised contract documents do not recognize email as an acceptable form of delivery of a Notice of Claim. Second, an unwary contractor may wrongly assume that an owner’s failure to assert a claim for LDs means that LDs will not be imposed. This may lull the contractor into failing to timely assert its own claim for a time extension and thereby waiving its ability to do so.
Reprinted courtesy of
George Talarico, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Talarico may be contacted at
gtalarico@sillscummis.com