Is A Miller Act Payment Bond Surety Bound by A Default or Default Judgment Against Its Principal?
February 08, 2021 —
David Adelstein - Florida Construction Legal UpdatesMaguire-O’Hara Construction, Inc. v. Cool Roofing Systems, Inc., 2020 WL 6532852 (W.D. Oklahoma 2020) is an interesting case dealing with suretyship law and the subject of whether a Miller Act payment bond surety is bound by a default or default judgment against its prime contractor (bond principal).
In this case, a subcontractor sued a prime contractor for breach of contract and the contractor’s Miller Act payment bond surety for a breach of the payment bond. The prime contractor did not respond to the lawsuit and the subcontractor obtained a default against the contractor. The Miller Act payment bond surety did engage counsel to defend itself in the dispute. Prior to trial, the subcontractor moved in limine to preclude the surety from raising defenses at trial under the subcontract because a default was entered against the prime contractor. The subcontractor argued that the surety should be bound by the default and, therefore, precluded from raising liability defenses under the subcontract. Such a ruling would leave the surety no defenses disputing liability at trial.
[A] suretys’ liability under the Miller Act coincides with that of the general contractor, its principal. Accordingly, a surety [can] plead any defenses available to its principal but [can]not make a defense that could not be made by its principal.
Maguire-O’Hara Construction, supra, at *2 (internal citations and quotations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Wildfire Risk Harms California Home Values, San Francisco Fed Study Finds
August 26, 2024 —
Laura Curtis - BloombergCalifornia’s wildfires are weighing on home prices more than in the past, and insurance availability does little to help in areas considered to be at higher risk, according to a Federal Reserve Bank of San Francisco study.
“Our results suggest that property values have been more adversely impacted in recent years by being close to past wildfires than was the case previously,” economists Leila Bengali, Fernanda Nechio and Stephanie Stewart wrote in a paper published Monday on the Fed bank’s website.
While the effect of the proximity may be relatively small now, the economists warned “this pattern may become stronger in years to come if residential construction continues to expand into areas with higher fire risk and if trends in wildfire severity continue,” the study cautioned.
Read the court decisionRead the full story...Reprinted courtesy of
Laura Curtis, Bloomberg
Quick Note: Independent Third-Party Spoliation Of Evidence Claim
June 18, 2019 —
David Adelstein - Florida Construction Legal UpdatesIn an earlier posting I discussed the difference between first-party spoliation of evidence and third-party spoliation of evidence.
There is NO independent cause of action for first-party spoliation of evidence because that can be dealt with directly in the underlying lawsuit. This deals with the assertion that an actual party to a lawsuit spoiled evidence.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
A Relatively Small Exception to Fraud and Contract Don’t Mix
April 06, 2016 —
Christopher G. Hill – Construction Law MusingsRemember all of my posts about how fraud and contract claims don’t usually play well in litigation? Well, as always with the law, there are exceptions. For instance, a well plead Virginia Consumer Protection Act claim will survive a dismissal challenge.
A recent opinion out of the Alexandria division of the U. S. District Court for the Eastern District of Virginia sets out another exception, namely so called fraudulent inducement. In XL Specialty Ins. Co. v. Truland et al, the Court considered the question of whether both a tort and contract claim can coexist in the same lawsuit when the tort claim is based upon the information provided to the plaintiff when that information proves false.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Construction Law MusingsMr. Hill may be contacted at
chrisghill@constructionlawva.com
Doing Construction Lead Programs the Right Way
October 16, 2018 —
Natalie Craigmile - Construction InformerRunning a construction business takes hard work. When you are working on a job, it can be difficult to find time to spend on marketing and advertising. If you are short on time, buying leads through construction lead programs could be a good way to meet new customers, grow your business, and find your next job. Keep reading to learn more about some of the pros and cons of buying leads.
A construction lead generation service exists solely to connect home owners with local home improvement contractors. They market across different construction specialties and reach customers who are looking for construction companies. Once they capture the ‘lead’, which is essentially the contact information and a few project details of that potential customer, they sell the lead to one or more local contractors in their network.
Read the court decisionRead the full story...Reprinted courtesy of
Natalie Craigmile, Construction Informer
Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Appeal of Jury Verdict Rejected by Tenth Circuit
March 06, 2023 —
Tred R. Eyerly - Insurance Law HawaiiAfter a jury awarded damages related to the insurer's delayed payment under the claim and the insurer's post trial motions to set aside the verdict were denied, the Tenth Circuit affirmed. US General, LLC v. GuideOne Mut. Ins. Co., 2022 U.S. App. LEXIS 34066 (10th Cir. Dec. 12, 2022).
Crossroads American Baptist Church submitted a claim to GuideOne for hailstorm damage. Crossroads hired US General as the general contractor to perform the repairs and later assigned its interest in the insurance policy to US General.
Numerous disputes arose between Crossroads and GuideOne regarding the cost of the repairs. There were delayed payments and portions of the repairs were never paid for. The delayed payments meant GuideOne's ability to begin making the repairs was hindered because it was more expensive to start and stop a project.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Congratulations to Arezoo Jamshidi & Michael Parme Selected to the 2022 San Diego Super Lawyers Rising Stars List
April 04, 2022 —
Arezoo Jamshidi & Michael C. Parme - Haight Brown & Bonesteel LLPCongratulations to Arezoo Jamshidi and Michael Parme who were selected for the 2022 San Diego Super Lawyers Rising Stars list. The 2022 San Diego Rising Stars list is an honor reserved for lawyers who exhibit excellence in practice. Only 2.5% of attorneys in San Diego receive this distinction.
Reprinted courtesy of
Arezoo Jamshidi, Haight Brown & Bonesteel, LLP and
Michael C. Parme, Haight Brown & Bonesteel, LLP
Ms. Jamshidi may be contacted at ajamshidi@hbblaw.com
Mr. Parme may be contacted at mparme@hbblaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of