Research Institute: A Shared Information Platform Reduces Construction Costs Considerably
October 26, 2017 —
Aarni Heiskanen - AEC BusinessA new Danish study shows how the use of a shared digital management and communication platform on large-scale construction projects leads to considerable cost reductions.
The Danish Building Research Institute conducted a six-month research project that studied the effects of using a specific IT concept during construction. The three case studies were:
1. The Maersk Tower, a 15-story, 42,700-square-meter extension to the Panum complex.
2. The Niels Bohr Building, a 52,000-square-meter new laboratory and academic building.
3. The Danish Defence’s Property Agency’s construction project portfolio (FES).
Each of them used GenieBelt as the shared IT platform. It was used for the progress management of a construction project portfolio, management of construction activities, and communication between the construction management team and contractors.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi
Oregon agreement to procure insurance, anti-indemnity statute, and self-insured retention
March 05, 2011 —
CDCoverage.comIn Continental Casualty Ins. Co. v. Zurich American Ins. Co., No. 09-35484 (9th Cir. Oct. 28, 2010), general contractor TCR was sued by an employee of subcontractor Safeway for bodily injuries suffered while working on the project. In the subcontract, Safeway agreed to procure primary insurance providing coverage for TCR for liability arising out of Safeway’s negligence. Safeway’s CGL policy included a self-insured retention that had to be satisfied before the insurer had a duty to defend. TCR filed suit against Safeway alleging that
Read the full story...Reprinted courtesy of CDCoverage.com
Read the court decisionRead the full story...Reprinted courtesy of
No Duty to Indemnify When Discovery Shows Faulty Workmanship Damages Insured’s Own Work
November 07, 2012 —
CDJ STAFFOur post last week addressed the duty to defend when alleged faulty workmanship caused loss to property adjacent to where the insured was working. See Pamerin Rentals II, LLC v. R.G. Hendricks & Sons Constr., Inc., 2012 Wis. App. LEXIS 698 (Wis. Ct. App. Sept. 5, 2012) [post here]. Today, we report on recent developments in the same case where the court determined, despite earlier finding the insurer owed a defense, it had no duty to indemnify. Pamperin Rentals II, LLC v. R.G. Hendricks & Sons Constr., Inc., 2012 Wisc. App. LEXIS 793 (Wis. Ct. App. Oct. 10, 2012).
Hendricks contracted to “prepare the site and supply and install concrete, tamped concrete, and colored concrete” at several service stations. The owner sued Hendricks, alleging the concrete “was defective and/or the work performed was not done in a workman-like manner and resulted in damages, and will require replacement.”
Pekin Insurance Company agreed to defend Hendricks subject to a reservation of rights.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law Hawaii.Mr. Eyerly can be contacted at
te@hawaiilawyer.com
New York Office Secures Appellate Win in Labor Law 240(1) Fall in Basement Accident Case
March 20, 2023 —
Nicholas P. Hurzeler & Gregory S. Katz - Lewis BrisboisNew York, N.Y. (March 14, 2023) – New York Appellate Partner Nicholas P. Hurzeler and Managing Partner Gregory S. Katz recently prevailed when the New York Appellate Division, Second Department affirmed the dismissal of a Labor Law 240(1) claim involving an accident that occurred in the basement of a house under construction. Balfe v. Graham, ___ AD3d ___ (2d Dept. 2023), decided March 8, 2023.
In this matter, the plaintiff was installing ductwork in the basement of a house that had been stripped down to its foundation when he stepped backwards into an open hole that had been dug out of a concrete floor to accommodate the installation of an ejector pump. The lower court dismissed the plaintiff’s claim based on Labor Law 240(1), and he appealed. The plaintiff argued that he fell into an unprotected opening that should have been covered or barricaded. He further claimed the accident qualifies as a typical “falling worker” case within the scope of Labor Law 240(1), citing the depth of the hole needed to accommodate the ejector pump, and the size of the pump. Under the case law, a worker who falls into an uncovered opening on a construction site will typically be covered by Labor Law 240(1).
Reprinted courtesy of
Nicholas P. Hurzeler, Lewis Brisbois and
Gregory S. Katz, Lewis Brisbois
Mr. Katz may be contacted at Greg.Katz@lewisbrisbois.com
Mr. Hurzeler may be contacted at Nicholas.Hurzeler@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Judgment Stemming from a Section 998 Offer Without a Written Acceptance Provision Is Void
March 22, 2021 —
Arezoo Jamshidi, Stevie B. Newton & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPIn Mostafavi Law Group, APC v. Larry Rabineau, APC (B302344, Mar. 3, 2021), the California Court of Appeal, Second Appellate District (Los Angeles), addressed an issue of first impression: whether the purported acceptance of a Code of Civil Procedure section 998 (“section 998”) offer lacking an acceptance provision gives rise to a valid judgment. The appellate court held that a section 998 offer to compromise (“998 Offer”) without an acceptance provision is invalid and any judgment stemming from it is void.
In Mostafavi Law Group, plaintiffs sued defendants for defamation per se, among other claims, which was litigated at-length over several years. Defendants served plaintiffs with a written 998 Offer, offering to settle the action for the sum of $25,000.01. The 998 Offer did not specify the manner in which plaintiffs were to accept the offer.
Within the statutory time period for acceptance, plaintiffs’ counsel hand-wrote the following onto the 998 Offer: “Plaintiff Mostafavi Law Group, APC accepts the offer.” That day, plaintiffs also filed a notice of acceptance of the 998 Offer, along with proof thereof, and sent a copy to defendants. The next day, having received the notice of acceptance, defendants advised plaintiffs that they would “draft and send . . . a settlement agreement for . . . signature” before paying the settlement funds.
Reprinted courtesy of
Arezoo Jamshidi, Haight Brown & Bonesteel LLP,
Stevie B. Newton, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Ms. Jamshidi may be contacted at ajamshidi@hbblaw.com
Mr. Newton may be contacted at snewton@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
New OSHA Rule Creates Electronic Reporting Requirement
June 22, 2016 —
John K. Baker & Kevin Conrad – White and Williams LLPThe United States Occupational Safety and Health Administration (OSHA) issued a
Final Rule revising portions of its Recording and Reporting Occupational Injuries and Illnesses regulations (Recording and Reporting Regulations). The revisions take effect August 10, 2016.
Employers subject to the new requirements have until July 1, 2017 to submit electronically the required information for calendar year 2016. OSHA will make electronically-submitted workplace-safety data for each reporting employer available publicly in an online database.
Reprinted courtesy of
John K. Baker, White and Williams LLP and
Kevin Conrad, White and Williams LLP
Mr. Baker may be contacted at bakerj@whiteandwilliams.com
Mr. Conrad may be contacted at conradk@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Settlement Reached in Bridge Failure Lawsuit
December 11, 2013 —
CDJ STAFFOfficials claimed the failure of a bridge in Afton Township, Illinois was because trucks owned by Welded Construction used the bridge despite exceeding the bridge’s weight limit of 36.5 tons. The firm argued that they should be responsible for the depreciated cost of the bridge, not its replacement cost. Welded Construction had been using the bridge to get to the site of an oil pipeline construction project for Enbridge Energy.
Replacement of the bridge was initially estimated at $933,000, but that was in advance of any design work. Enbridge Energy settled the case at $900,000, which should cover most or all of the cost of repair or replacement. Some federal funds may also be available for repairing or constructing a new bridge.
Read the court decisionRead the full story...Reprinted courtesy of
TOP TAKE-AWAY SERIES: The 2023 Fall Meeting in Washington, D.C.
November 13, 2023 —
Marissa L. Downs & Jennifer M. Kanady - The Dispute ResolverOver 500 construction lawyers, experts, and consultants descended on Washington last week for the Forum’s 2023 Fall Meeting. Newly minted Forum Chair John Cook and Program Coordinators Catherine Delorey and Brian Zimmerman put together a stellar program focused on navigating government construction. For this installation of the post-meeting post, I'm teaming up with guest contributor, Jennifer Kanady, to bring you 10 of our top take-aways from this unique program.
10. Contracting with the government is replete with risk that could easily trap the unwary. Nobody likes to be taken advantage of. But hell hath no fury like the U.S. Government scorned. Erin Cannon-Wells and Aaron Silberman, gave a (truly) delightful, Indiana-Jones-inspired presentation on the regulations that can doom the unwitting contractor who is less than perfectly forthright in its dealings. The government has created financial incentives for members of the public to report your company’s violations as part of a qui tam action. When you consider the number of potential whistleblowers in the bidding process and the contracting chain, a qui tam action would seem more likely than not. Add to that the sanctions contractors might face for even innocent errors either by their own companies or their downstream subs, and government contracting begins to sound increasingly like the Temple of Doom. Oh, and in case you were only focused on affirmative claims, beware the “reverse false claim” which is concealing information that would rightfully entitle the government to a credit…
Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLP and
Jennifer M. Kanady, FAC Services, LLC
Ms. Downs may be contacted at mdowns@lauriebrennan.com
Ms. Kanady may be contacted at JKanady@facfin.com
Read the court decisionRead the full story...Reprinted courtesy of