Subcontractors on Washington Public Projects can now get their Retainage Money Sooner
July 26, 2017 —
Brett M. Hill - Ahlers & Cressman PLLCSubcontractors on public projects in Washington State will no longer be required to wait until final acceptance of the project to get their retainage money. A new statute, which goes into effect on July 23, 2017 and applies only to Washington public projects, will allow subcontractors to get their retainage sooner.
Under prior law, a subcontractor could only get its retainage prior to final acceptance if the general contractor provided a retainage bond to the public owner to secure a release of the general contractor’s retainage and the subcontractor then provided a similar retainage bond to the general contractor in the amount of its own retainage. If the general contractor decided to not provide a retainage bond to the owner, the subcontractor would be forced to wait until final acceptance of the project before it could get paid its retainage.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers & Cressman PLLCMr. Hill may be contacted at
bhill@ac-lawyers.com
Business Interruption, Food Spoilage Claims Resulting from Off Premise Power Failure Denied
June 02, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe insurer denied the insured restaurant's claim for food spoilage and loss of business income when a flood elsewhere caused a power outage. N. Spy Food Co., LLC v. Tower Nat'l. Ins., 2016 N.Y. Misc. LEXIS 1033 (N.Y. Sup. Ct. March 22, 2016).
Tower denied the claim based on an investigation which revealed that the claims resulted from an off premises power failure. The utility company verified that the cause of the power failure was due to flood, a cause excluded under the policy. The food loss and business interruption, therefore, did not result from direct physical loss or damage by a covered cause, justifying the denial of the claim.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
A Homeowner’s Subsequent Action is Barred as a Matter of Law by way of a Prior “Right to Repair Act” Claim Resolved by Cash Settlement for Waiver of all Known or Unknown Claims
February 26, 2015 —
Richard H. Glucksman, Esq., Jon A. Turigliatto, Esq., and David A. Napper, Esq. – Chapman Glucksman Dean Roeb & Barger BulletinDavid Belasco v. Gary Loren Wells et al. (2015) B254525
OVERVIEW
In a decision published on February 17, 2015, the Second District Court of Appeal made clear that settlement agreements containing waivers of unknown claims in connection with a construction of a property, absent fraud or misrepresentation, will be upheld. In brief, the homeowner plaintiff had made a claim against the builder pursuant to California Code of Civil Procedure Section 896 (“Right to Repair”) and settled for a cash payment and obtained a Release of all Claims including for all known and unknown claims. The court held that homeowner’s subsequent construction defect claim was barred pursuant to the terms and conditions of the earlier release.
DISCUSSION
Plaintiff and Appellant, David Belasco ("Belasco"), purchased a newly construction home in Manhattan Beach from builder Gary Loren Wells ("Wells"). Two years after purchasing the property, Belasco filed a Complaint for construction defects, which eventually resulted in settlement between the parties. The settlement agreement included a California Civil Code Section 1524 waiver of all known or unknown claims with the word "claims" defined in part as “any and all known and unknown construction defects." Six years later in 2012, Belasco filed a Complaint alleging a claim, amongst others, that the defective and leaky roof breached the statutory warranty on new construction under California Civil Code section 896 ("Right to Repair Act").
Relying on San Diego Hospice v. County of San Diego (1995) 31 Cal.App.4th 1048, Wells and Wells' surety, American Contractors Indemnity Company (collectively "Wells"), filed a motion for summary judgment contending that the 2012 action was barred by the settlement of Belasco’s prior Complaint against Wells for construction defects to his home. When the trial court ruled in favor of Wells, Belasco appealed. Belasco, a patent attorney, made the following contentions:(1) the general release and section 1542 wavier in the settlement agreement for patent construction defects is not a "reasonable release" of a subsequent claim for latent construction defects within the meaning of section 929 and the “Right to Repair” Act; (2) a reasonable release can only apply to a "particular violation" and not to a latest defect under the language of section945.5, subdivision (f), and the settlement was too vague to be valid because it does not reference a "particular violation;" (3) section 932 of the California Civil Code specifically authorizes an action on "[s]subsequently discovered claims of unmet standards;" (4) public policy prohibits use of a general release and section 1542 waiver to bar a subsequent claim for latent residential construction defects; and (5) a genuine issue of material fact exists concerning Belasco's fraud and negligence claims that would have voided the settlement pursuant to section 1668.
Pursuant to the "Right to Repair Act" Section 929 subsection (a), a builder can make a cash offer in lieu of a repair and the homeowner is free to accept or reject such offer. Section 929subsection (b) goes on to state that
"[t]he builder may obtain a reasonable release in exchange for the cash payment. The builder may negotiate the terms and conditions of any reasonable release in terms of scope and consideration in conjunction with a cash payment under this chapter."
The Second District Court of Appeal ruled that the prior cash settlement, with a release and section 1524 wavier, was a "reasonable release" under the language of California Civil Code Section 929.
On multiple occasions, the Court noted that Belasco is an attorney and was represented by an attorney during the negotiation of the settlement agreement. By executing the agreement with express language regarding what claims were to be release, Belasco released Wells of "any and all claims" due to "any and all known and unknown construction defects." The Court reasoned that because Belasco is an attorney in his own right, he should have understood the import of the Section 1542 waiver and had the opportunity to reject or revise the settlement agreement prior to binding himself to it. The Court further found that the agreement "could not have been more clear" regarding the waiver of all unknown and known construction defect claims and therefore was not vague. Belasco's additional contentions were found to be without merit because Belasco availed himself of the statutory remedy of a cash settlement in lieu of repairs and voluntarily entered into a negotiated settlement agreement. Lastly, Belasco failed to present any evidence regarding his misrepresentation claim.
When a homeowner files a "Right to Repair Act" claim, often it seems that only two options exist: either repair the alleged defects or go to court. However, Belasco is a reminder to builders that the "Right to Repair Act" does offer an avenue for settlement. The Second District Court of Appeal presented a clear, unqualified opinion regarding the validity and enforceability of settlement agreements releasing all known or unknown construction defects in a single family home case. The Court will hold parties to the settlements they agree to. This is especially so when one of the parties is an attorney and provides deposition testimony expressly acknowledging that he understood the scope of the agreement. Attorneys for builders should always include a waiver of all known and unknown claims, which pursuant to Belasco and San Diego Hospice, will ensure that any future claims at the property will be effectively barred by the terms of the settlement agreement.
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard H. Glucksman,
Jon A. Turigliatto and
David A. Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Turigliatto may be contacted at jturigliatto@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Senate’s Fannie Mae Wind-Down Plan Faces High Hurdles
March 19, 2014 —
Clea Benson, Cheyenne Hopkins and Kathleen Hunter – BloombergA bipartisan U.S. Senate plan to dismantle Fannie Mae (FNMA) and Freddie Mac must clear many political hurdles in a short time if it is to become law, leaving narrow chances of a housing-finance overhaul being enacted this year.
Senate Banking Committee leaders said the proposal, which they plan to release later this week, would replace the two U.S.-owned mortgage financiers with government bond insurance that would kick in only after private capital suffered severe losses.
It will be left to the courts to decide how investors in Fannie Mae and Freddie Mac are treated as the two companies are wound down, Mike Crapo, an Idaho Republican who co-wrote the bill, said today in an interview on Bloomberg Television. Investors including Perry Capital and Fairholme Capital Management are suing the U.S. to challenge an arrangement in which all the companies’ profits go to the Treasury.
Ms. Benson may be contacted at cbenson20@bloomberg.net; Ms. Hunter may be contacted at khunter9@bloomberg.net; Ms. Hopkins may be contacted at chopkins19@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Clea Benson, Cheyenne Hopkins and Kathleen Hunter, Bloomberg
Subcontractor Exception to Your Work Exclusion Paves the Way for Coverage
April 03, 2013 —
CDJ STAFFIn a brief opinion, the Second Circuit vacated the district court's denial of coverage for construction defects. Scottsdale Ins. Co. v. R.I. Pools Inc., 2013 U.S. App. LEXIS 5680 (2nd Cir. March 21, 2013).
The insured, R.I. Pools, employed outside companies to supply concrete and to shoot the concrete into the ground. During the summer of 2006, it obtained its concrete from one subcontractor and used another to shoot the concrete. In 2009, nineteen customers of R.I. Pools from 2006 complained damage to their pools, including cracking, flaking, and deteriorating concrete.
Scottsdale sought a declaratory judgment against R.I. Pools that it had no obligations under the policy to defend or indemnify for claims related to cracks in the pools.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Do You Have the Receipt? Pennsylvania Court Finds Insufficient Evidence That Defendant Sold the Product
December 23, 2024 —
Gus Sara - The Subrogation StrategistIn State Farm Fire & Cas. Co. v. Coway USA, Inc., No. 22-cv-3516, 2024 U.S. Dist. LEXIS 192849, the United States District Court for the Eastern District of Pennsylvania (District Court) considered whether the plaintiff produced sufficient evidence to establish that the defendant sold and/or marketed a product and, thus, could be held liable for an alleged defect in the product. The plaintiff, a subrogating insurance carrier, brought strict product liability and breach of warranty claims against the defendant—the installer of a bidet in its insured’s home—claiming that the defendant also marketed and sold the bidet. The sole evidence to support a finding that the defendant sold the bidet was the homeowner’s testimony that she bought the product from the installer. The court found that the insured’s testimony, without any documentation or other corroborating evidence, was insufficient to establish that the defendant sold the product. Since proof of a sale is a required element for strict product liability and breach of warranty claims, the District Court granted the defendant’s motion for summary judgment, dismissing the case.
This case involved a water loss to the Pennsylvania residence of Mikyung Kim and her husband Adrian Kim (collectively, the Kims) that was discovered in April 2021. An investigation revealed that the water loss originated from the failure of a bidet for a toilet in the second-floor bathroom. The Kims alleged that defendant, Coway USA, Inc. (Coway), sold the bidet and installed it around 2010. An employee of the plaintiff’s liability expert, a materials engineer, opined that a T-connector—a plastic valve that regulates the flow of water to and through the bidet—failed due to overtightening of the connector during the manufacturing process.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Unesco Denies Claim It Cleared Construction of Zambezi Dam
November 06, 2023 —
Antony Sguazzin - BloombergUnesco denied that it cleared Zimbabwe and Zambia to proceed with the construction of a $5 billion hydropower dam downstream from the Victoria Falls, which it has designated as a World Heritage Site.
Munyaradzi Munodawafa, chief executive officer of the Zambezi River Authority, said in an
earlier interview that Unesco’s World Heritage Committee “agreed that Batoka could go ahead,” referring to the planned dam and 2,400-megawatt power plant on the Zambezi River. Munodawafa didn’t answer calls or text messages to his mobile phone.
“The decision taken by the committee raises several concerns regarding the site, including the inevitable negative impacts of the Batoka Gorge” project, Unesco said in a response to queries.
Read the court decisionRead the full story...Reprinted courtesy of
Antony Sguazzin, Bloomberg
How the Cumulative Impact Theory has been Defined
November 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesLargely in the federal contract arena, there is a theory referred to as “cumulative impacts” used by a contractor to recover unforeseeable costs associated with a multitude of changes that have an overwhelming ripple effect on its efficiency, particularly efficiency dealing with its original, base contract work. In other words, by dealing with extensive changes, there is an unforeseeable impact imposed on the contractor relative to its unchanged or base contract work. Under this theory, the contractor oftentimes prices its cumulative impact under a total cost approach with an examination on its cost overrun. However, this is not an easy theory to prevail on because there needs to be a focus on the sheer number of changes, causation supporting the impact, and whether there were concurrent impacts or delays that played a role in the ripple effect. See, e.g., Appeals of J.A. Jones Const. Co., ENGBCA No. 6348, 00-2 BCA P 31000 (July 7, 2000) (“However, in the vast majority of cases such claims are routinely denied because there were an insufficient number of changes, contractor-caused concurrent delays, disruptions and inefficiencies and/or a general absence of evidence of causation and impact.”).
To best articulate how the cumulative impact theory has been defined, I want to include language directly from courts and board of contract appeals that have dealt with this theory. This way the contractor knows how to best work with their experts with this definition in mind–and, yes, experts will be needed–to persuasively package and establish causation and damages stemming from the multitude of changes. While many of these definitions are worded differently, you will see they have the same focus dealing with the unforeseeable ripple effect of the extensive changes.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com