Wyncrest Commons: Commonly Used Progress Payments in Construction Contracts Do Not Render Them Installment Contracts
December 11, 2023 —
Benjamin J. Hochberg - Peckar & Abramson, P.C.In BIL-JIM Construction Company, Inc. v. Wyncrest Commons, LP, 2023 WL 7276637 (Unpublished, decided November 3, 2023), the New Jersey Appellate Division was asked to consider two issues regarding the interpretation and application of a construction contract that utilized the standard form American Institute of Architects owner/contractor agreement (AIA Document A101-2007) (the “AIA Contract”). Specifically, it was asked to consider: 1) whether a modified AIA Contract was an “installment contract,” whereby each progress payment was subject to its own statute of limitations; and 2) whether and when work had been approved in the context of New Jersey’s Municipal Land Use Law. While the decision is presently unpublished, it provides guidance as to how form contracts utilizing the same or similar terms will be treated by New Jersey’s courts and is a reminder that the potential for future claims must be considered during contract negotiations.
Discussion
The primary issue in Wyncrest was whether an AIA Contract was an “installment contract,” and the remaining issues turned on the resolution of this question. Wyncrest, the owner for the project at issue, did not dispute that its contractor, BIL-JIM Construction Company, Inc., had not been fully paid for work that it had performed in connection with a construction project located in Ocean County, New Jersey. Instead, Wyncrest argued that because its AIA Contract with BIL-JIM required that invoices be presented and paid monthly, it constituted an “installment contract.” As such, older payments would be treated as individual transactions and were time barred by the applicable statute of limitations. The trial court agreed with Wyncrest’s characterization of the AIA Contract as an “installment contract,” and found that BIL-JIM’s invoices were each subject to their own statute of limitations. However, the trial court disagreed with Wyncrest’s argument that BIL-JIM’s claim for retainage—which was submitted at the end of its work at the project—was time barred.
Read the court decisionRead the full story...Reprinted courtesy of
Benjamin J. Hochberg, Peckar & Abramson, P.C.Mr. Hochberg may be contacted at
bhochberg@pecklaw.com
Construction Professionals Could Face More Liability Exposure Following California Appellate Ruling
December 17, 2024 —
Jamison Rayfield & Brian Slome - Lewis BrisboisSan Diego/San Francisco, Calif. - The California Court of Appeal
recently reversed a summary judgment ruling in favor of a geotechnical engineering firm that had conducted a brief inspection of a residential construction project's footing trench for $360. The case arose when homeowner Cheryl Lynch experienced significant property damage after her home's foundation failed and the structure began subsiding into a slope. Lynch sued Peter & Associates for professional negligence and nuisance, despite having no direct contractual relationship with the firm, which had been hired by her contractor to perform the geotechnical inspection.
The court distinguished this case from Bily v. Arthur Young & Co. (1992) 3 Cal.4th 370, which had limited auditors' professional duty to third parties, noting that Bily dealt with purely economic damages, whereas Lynch involved physical property damage, making Bily's policy concerns about unlimited liability inapplicable. The court emphasized that construction professional negligence cases, particularly those involving residential property damage, warrant a different analysis than cases involving economic loss.
Reprinted courtesy of
Jamison Rayfield, Lewis Brisbois and
Brian Slome, Lewis Brisbois
Mr. Rayfield may be contacted at Jamison.Rayfield@lewisbrisbois.com
Mr. Slome may be contacted at Brian.Slome@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Billionaire Behind Victoria’s Secret Built His Version of the American Heartland
June 25, 2019 —
Sophie Alexander - BloombergBeyond emerald-green golf links, over snow-white fences, and past tree-lined cul-de-sacs rises the American fantasyland of billionaire Les Wexner.
Here in the middle of Ohio, of all places, Wexner—the man behind Victoria’s Secret and its push-up-bra notions of female beauty—has brought to life his singular vision of the heartland.
Read the court decisionRead the full story...Reprinted courtesy of
Sophie Alexander, Bloomberg
What You Need to Know About Home Improvement Contracts
July 30, 2019 —
Garret Murai - California Construction Law BlogGiven the variety of problems that can arise on a construction project, from defects to delays, it’s difficult to draft a construction contract that addresses every possible problem exactly right. However, so long as you adequately address the “big three” of scope, price and time, it’s also difficult to draft a construction contract wrong.
That is, with one exception.
And that one exception, in California, is home improvement contracts. In 2004, the California State Legislature enacted the state’s Home Improvement Business statute (Bus. & Prof. Code §§7150 et seq.). Section 7159 of the statute sets forth what must be included in home improvement contracts.
It’s a section that could have been written by Felix Unger of the Odd Couple. In addition to setting forth required language that must be included in a home improvement contract, it directs where that language is to be set forth in a home improvement contract, and even how it is to be presented, down to type sizes.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Coronavirus and Contract Obligations
March 30, 2020 —
David R. Cook - AHC Construction and Procurement BlogThe Coronavirus (COVID-19) pandemic has caused a global disruption to businesses, causing many to temporarily close and lay off employees. As businesses assess the short– and long–term economic impact of COVID-19, they should also evaluate what contractual obligations and remedies are available under various agreements (e.g., leases, vendor agreements, and supply agreements). When performance may be delayed or may not occur altogether, businesses should consider their force majeure clauses, if any, and the doctrines of impossibility, impracticability, and frustration of purpose.
Force Majeure
Generally, unless a contract provides that performance will be suspended or relieved when certain events occur (e.g., “acts of God,” government regulation, acts of war or terror, strikes), each party is obligated to perform. However, when there is an express force majeure provision, certain events or acts may excuse non-performance or delayed performance. But depending on the jurisdiction, courts may construe force majeure provisions narrowly and excuse performance only for those events expressly listed in the clause. Nonetheless, if the force majeure provision includes pandemic, epidemic, quarantine, government act, disease, or similar terms, then the COVID-19 pandemic may excuse performance or allow delayed performance.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Saudi Prince’s Megacity Shows Signs of Life
September 03, 2019 —
Vivian Nereim & Donna Abu-Nasr - BloombergThe walls are covered with graffiti in the sleepy fishing village of Khurayba. There are supplications to God, advertisements for vacation rentals and house painters. Near the local school, there’s a scribbled plea: “Open the windows of hope and drive out the despair.”
It’s here in northwest Saudi Arabia that Crown Prince Mohammed bin Salman wants investors to put their money to realize his $500 billion vision for the region. Called “Neom,” it promises to be the most freewheeling part of the kingdom, with state-of-the-art resorts and smart technologies run by robots.
But it’s also here where the risks to the 33-year-old prince’s grand plan for his country are writ large. Neom is the boldest pillar of a social and economic transformation that so far has seen at least as many delays as successes. Indeed, the question since the prince announced the vast development at an extravaganza in 2017 has been whether it can become a reality.
Read the court decisionRead the full story...Reprinted courtesy of
Vivian Nereim & Donna Abu-Nasr, Bloomberg
Supreme Court Grants Petition for Review Regarding Necessary Parties in Lien Foreclosure Actions
August 17, 2017 —
Lindsay K. Taft - Ahlers & Cressman PLLCFor several years, the requirements for which parties must be named in a lien foreclosure action when a release of lien bond is in place have been cloudy. RCW 60.04 et seq., the “mechanics’ lien” or “construction lien” statute, provides protection for a party or person who provides labor, materials, or equipment to a construction project. That person or party, if not paid, can file a lien against the construction project property to secure recovery. As the lien impacts the property by “clouding title” and could potentially result in foreclosure of the property, the statute sets forth strict requirements with respect to timing, notice, and parties. For example, the lien must be recorded within 90 days of the person or party’s last day of work or materials or equipment supplied, and the lien claimant must then give a copy of the claim of lien to the owner or reputed owner within 14 days of the lien recording. RCW 60.04.081.
The statute also allows a property owner or other party to “free” the property from the lien prior to the claim being resolved by issuing a release of lien bond. While the claim is still in dispute, the lien then attaches to the bond and not the property. The same rules about foreclosure, however, still apply but not without some confusion.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay K. Taft, Ahlers & Cressman PLLCMs. Taft may be contacted at
ltaft@ac-lawyers.com
Construction Defect Bill a Long Shot in Nevada
June 28, 2013 —
CDJ STAFFConstruction defect reform may still be on the table in Nevada, according to the Reno Gazette Journal. Assembly member Pat Hickey got a committee hearing for Assembly Bill 504 on Sunday. The bill is backed by the construction industry and opposed by trial lawyers. Hickey told the Assembly Commerce and Labor committee that “this bill is not perfect, I would like for it to do more,” and said that without changes Nevada will “continue to reward litigation over resolution.”
AB504 would, among other provisions, provide some protection to subcontractors from the actions of general contractors, though Ira Hansen, an assembly member from Sparks and the owner of a plumbing business, called it a “backhanded slap.” The Gazette noted that similar language pertaining to subcontractors was in AB367, which is sponsored by Democrats. Hickey and Hansen are both Republicans.
Read the court decisionRead the full story...Reprinted courtesy of