Housing Starts in U.S. Drop to Lowest Level in Three Months
February 23, 2016 —
Michelle Jamrisko – BloombergNew-home construction in the U.S. unexpectedly cooled in January, indicating there is a limit to how much gains in residential real estate will boost growth at the start of 2016.
Housing starts dropped 3.8 percent to a 1.1 million annualized rate, the weakest in three months, from a 1.14 million pace the prior month, a Commerce Department report showed Wednesday in Washington. The median forecast of 76 economists surveyed by Bloomberg was 1.17 million. Permits, a proxy for future construction, were little changed.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Jamrisko, Bloomberg
Fourth Circuit Finds Insurer Reservation of Rights Letters Inadequate to Preserve Coverage Defenses Under South Carolina Law
January 17, 2023 —
Jason Taylor - Traub Lieberman Insurance Law BlogIn Stoneledge at Lake Keowee Owners Ass'n v. Cincinnati Ins. Co., 2022 U.S. App. LEXIS 34292 (D.S.C. Dec. 13, 2022), the Fourth Circuit Court of Appeals addressed the adequacy of reservation of rights letters issued by Builders Mutual Insurance Company (“Builders Mutual”) and Cincinnati Insurance Company (“Cincinnati”) to their insureds, Marick Home Builders, LLC (“Marick”) and Rick Thoennes (“Thoennes”), Marick’s managing member, for an underlying construction defect lawsuit. In short, the Fourth Circuit found that the reservation letters were inadequate to preserve the insurers’ coverage defenses because they did not sufficiently explain the basis of the carriers’ position.
Stoneledge, a homeowners association, managed a community of 80 townhomes on South Carolina’s Lake Keowee. In 2009, Stoneledge brought suit against Marick and Thoennes, among other defendants, alleging construction defects in the townhomes that resulted in water intrusion and other physical damage. Marick and Thoennes held commercial general-liability policies through Cincinnati and Builders Mutual covering, in relevant part, “property damage” as defined by the policies. Builders Mutual issued policies covering the period from January 2004 to October 2007, and Cincinnati issued policies covering the period from April 2008 to April 2012. After Marick notified the insurers of the underlying action, Builders Mutual sent Marick two reservation of rights letters, one in May 2009 and one in July 2009. Cincinnati sent Marick one reservation of rights letter in March 2010.
In March 2014, Stoneledge brought a declaratory-judgment action against Cincinnati seeking coverage for a judgment entered in the underlying action. The insurers removed the case to federal court, and in September 2016, Stoneledge amended its complaint, adding Builders Mutual as a defendant and seeking coverage for additional damages pursuant to a settlement agreement entered into by Stoneledge, Marick, Thoennes. The district court granted Stoneledge's motion for summary judgment, primarily on the ground that the insurers failed to reserve the right to contest coverage. The insurers appealed to the Fourth Circuit, which affirmed.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Traub Lieberman Attorneys Win Motion for Judgment on the Pleadings In Favor of Insurer
June 26, 2023 —
Jeremy S. Macklin & Danielle K. Kegley - Traub LiebermanTraub Lieberman Partner Jeremy Macklin and Associate Danielle Kegley obtained judgment on the pleadings in favor of Admiral Insurance Company (“Admiral”), in a matter brought before the Chancery Division of the Circuit Court of Cook County, Illinois. In the underlying case, an injured employee sued various companies, and their agents, for injuries he sustained on a construction project. The insureds, one of the defendant companies and its employee, sought coverage for the underlying lawsuit under a professional liability policy issued to that company by Admiral. The policy at issue provided coverage for the company and its employees, for negligent acts or omissions committed in the rendering of “professional services,” defined as services “involving specialized training and skill while in the pursuit of” mechanical and process engineering.
After initially defending the insureds, Admiral filed a declaratory judgment action asking the Court to declare that the company has no duty to defend or indemnify the insureds in the underlying lawsuit and to allow Admiral to immediately withdraw its defense of the insureds. Admiral argued there is no coverage under the professional liability policy, as the underlying lawsuit does not contain allegations that the underlying plaintiff’s injuries arose from the rendering of or failure to render “professional services.” The insureds argued that since they were hired as mechanical and process engineers for the project, that any lawsuits against them must necessarily arise from their “professional services.” Further, the insureds asked the Court to disregard the express allegations in the underlying lawsuit concerning their role on the project as a general contractor.
Reprinted courtesy of
Jeremy S. Macklin, Traub Lieberman and
Danielle K. Kegley, Traub Lieberman
Mr. Macklin may be contacted at jmacklin@tlsslaw.com
Ms. Kegley may be contacted at dkegley@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Catch 22: “If You’re Moving Dirt, You Need to Control Your Dust” (But Don’t Use Potable Water!)
February 18, 2015 —
Stephen McKae – California Construction Law BlogReturning from an Oregon vacation this past Summer along I-5, I found frequent reminders of the extraordinary drought conditions prevailing across California. A grey smoky gloom blanketed the California-Oregon border from Ashland to Weed from at least five wildfires. The prediction of rains in the north state was more curse than blessing as lightning threatened to touch off tender-dry fuel in the forests and start more fires. Farmers tilling fields produced massive dust clouds. And under the I-5 bridge along the Sacramento River arm of Lake Shasta, the lake had receded to the original streambed.
On NOAA’s Palmer Drought Severity Index, nearly all of California is listed as in a condition of extreme or severe drought, and the Governor has issued a Proclamation of Continued State of Emergency requiring water conservation measures affecting all California residents. Indeed, early August news reports indicate that hopes of relief from an El Nĩno year are waning. The State Water Resources Control Board’s Emergency Regulation No. 2014 issued July 15 mandates action to reduce water use and require larger water suppliers to activate their Water Shortage Contingency Plan. The emergency regulation will remain in effect until April 25, 2015 unless extended due to ongoing drought conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen McKae, Wendel Rosen Black & Dean LLPMr. McKae may be contacted at
smckae@wendel.com
Structural Failure of Precast-Concrete Span Sets Back Sydney Metro Job
January 04, 2018 —
Chris Webb - Engineering News-RecordOriginally Published by CDJ on February 23, 2017
A key component of Australia’s biggest public transport infrastructure project—Sydney’s $6.3-billion Metro North West—is the subject of a critical and detailed technical report describing how an elevated viaduct span failed at a stitch joint between two precast segments during construction last September. Project officials say the affected span, which did not suffer a progressive collapse, has since been removed and its replacement fast-tracked to avoid further delays. Little additional detail was provided.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Webb, ENR
When to Withhold Retention Payments on Private or Public Projects
August 29, 2018 —
Nicholas Karkazis - Gordon & Rees Construction Law BlogTo ensure that construction contractors and subcontractors receive timely progress and retention payments, the California Legislature enacted statutes that impose deadlines and penalties on owners and direct (general) contractors who delay payments. (Cal. Civ. Code, §§ 8800, 8802, 8812, 8814; Pub. Contract Code, §§ 7107, 10262.5; Bus. & Prof. Code, § 7108.5.) However, there is an exception to these deadlines and penalties on both private and public projects. The exception allows an owner or direct contractor to withhold payment1 when there is a good faith dispute between an owner and a direct contractor or between a direct contractor and a subcontractor. (Civ. Code, §§ 8800, subd. (b), 8802, subd. (b), 8812, subd. (c), 8814, subd. (c); Pub. Contract Code, §§ 7107, subds. (c), (e), 10262.5, subd. (a); Bus. & Prof. Code, § 7108.5, subd. (a).)
But the term “good faith dispute” has been a source of confusion where direct contractors owe subcontractors retention payments, but want to withhold the payment because of a dispute.2 California appellate courts were split, with one court finding that any type of bona fide dispute justified withholding, and another finding that only disputes related to the payment itself justified withholding. (Compare Martin Brothers Construction, Inc. v. Thompson Pacific Construction, Inc. (2009) 179 Cal.App.4th 1401 [any bona fide dispute could justify withholding] with East West Bank v. Rio School Dist. (2015) 235 Cal.App.4th 742 [disputes related to the payment itself may justify withholding].) In May 2018, the California Supreme Court clarified that for a direct contractor to withhold a retention payment on a private project, the good faith dispute must somehow relate to the payment itself. (United Riggers & Erectors, Inc. v. Coast Iron & Steel Co. (2018) 4 Cal.5th 1082, 1097-1098.)
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas Karkazis, Gordon & Rees Scully MansukhaniMr. Karkazis may be contacted at
nkarkazis@grsm.com
Nancy Conrad to Serve as President of the Pennsylvania Bar Association
May 28, 2024 —
White and Williams LLPWhite and Williams is honored to announce that Nancy Conrad, Managing Partner of the Lehigh Valley office and Chair of the Higher Education Practice Group, will serve as President of the Pennsylvania Bar Association (PBA) for the 2024-2025 term. She will be the seventh woman to serve as President, the second president to hail from Lehigh Valley, the third partner from White and Williams and our firm’s first woman Partner to serve in this role. Conrad recently completed her term as President of the Lehigh County Bar Association (2023-2024).
Tim Davis, Managing Partner stated, “We are proud of Nancy as she begins her term as President of the Pennsylvania Bar Association. Her commitment to ensuring excellence in the profession, her focus on the community and on being an inclusive thought-leader have all laid the foundation for her to take on this important position."
During her career and involvement with the PBA, Conrad served on a number of committees and sections. She started with the Women in the Profession Committee (WIP), then expanded to the Federal Practice Committee, the Labor & Employment Section, the Civil Litigation Section and others. In each of these committees and sections, she served in leadership roles leading to her appointment as Woman Governor and Chair of the DEI Team.
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Ahead of the Storm: Preparing for Irma
September 07, 2017 —
Stephen H. Reisman – Peckar & Abramson, P.C.While Hurricane Irma boils in the Atlantic and seems to be aiming towards Florida, storm preparations are well underway. As contractors are busy organizing efforts to secure their job sites, we at Peckar & Abramson offer some quick reminders that may prove helpful when the dust finally settles:
- Review your contracts, particularly the force majeure provisions, and be sure to comply with applicable notice requirements.
- Even if not expressly required at this point in time, consider providing written notice to project owners that their projects are being prepared for a potential hurricane or tropical storm and that productivity and the progress of the work will be affected, with the actual time and cost impact to be determined after the event.
- Consult your hurricane plan (which is often a contract exhibit) and confirm compliance with all specified safety, security and protection measures.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen H. Reisman, Peckar & Abramson, P.C.Mr. Reisman may be contacted at