Update Regarding New York’s New Registration Requirement for Contractors and Subcontractors Performing Public Works and Covered Private Projects
February 06, 2023 —
Christopher B. Kinzel, K. Greer Kuras, Aaron C. Schlesinger - Peckar & Abramson, P.C.Some significant changes are being made by chapter amendments (S.838 and A.984) to Section 220-i of New York’s Labor Law. Contractors and subcontractors bidding on public contracts and performing work on covered private projects will have two years (by December 30, 2024) to register with the Department of Labor, Bureau of Public Works, rather than one year. The amendments also remove the requirement that a contractor submit registration certificates for all its subcontractors at the time its bid is submitted; amend language with respect to notice and hearing requirements; require re-registration to occur not less than 90 days before expiration; and add language to require a monitor to oversee ongoing work if a contractor or subcontractor is found unfit.
The stated purpose of the law is to help enforce New York’s prevailing wage and other worker protection laws. The DOL will create an online system through which contractors and subcontractors will have to answer questions and submit documents about:
- the business entity and its owners and officers
- unemployment and workers’ compensation insurance
- any outstanding wage assessments
- debarment under New York or federal law, or any other state’s laws
- final determinations of a violation of any labor laws, employment tax laws, or workplace safety standards (including OSHA)
- association or signatory to an apprenticeship program
Reprinted courtesy of
Christopher B. Kinzel, Peckar & Abramson, P.C.,
K. Greer Kuras, Peckar & Abramson, P.C. and
Aaron C. Schlesinger, Peckar & Abramson, P.C.
Mr. Kinzel may be contacted at ckinzel@pecklaw.com
Ms. Kuras may be contacted at gkuras@pecklaw.com
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
NLRB Finalizes Rule for Construction Industry Unions to Obtain Majority Support Representational Status
September 23, 2024 —
Aaron C. Schlesinger - Peckar & Abramson, P.C.On July 26, 2024, the National Labor Relations Board (“NLRB”) issued its Fair Choice – Employee Voice Final Rule (“Final Rule”), which takes effect September 30, 2024. The Final Rule eases the process for unions in the construction industry to convert their status as collective bargaining representative of bargaining unit employees from Section 8(f) to 9(a) of the National Labor Relations Act (“Act”) simply by placing certain recognitional acceptance language in their collective bargaining agreements. As a result, construction industry employers should review their collective bargaining agreements prior to signing to determine if such language exists.
Section 9(a) Non-Construction Industry Employers
In most industries, not including construction, union recognitional status as collective bargaining representative of the employer’s employees is governed by Section 9(a) of the Act. In order for a Union to obtain recognitional status under Section 9(a), the union must either: (1) file a petition with the NLRB showing support of 30% of the proposed bargaining unit via employee executed authorization cards and win an election of 51% of the employees in the proposed bargaining unit who actually vote; or (2) by reaching an agreement with the employer that the union possesses employee executed authorization cards from 51% of the proposed bargaining unit, which has been confirmed by a neutral arbitrator pursuant to a card count. Once such status is achieved, the union and employer are required to meet and bargain towards reaching a collective bargaining agreement covering the terms and conditions of employment of the union represented employees. A Section 9(a) union cannot have its recognitional status revoked absent the loss of majority support of the employees it represents.
Read the court decisionRead the full story...Reprinted courtesy of
Aaron C. Schlesinger, Peckar & Abramson, P.C.Mr. Schlesinger may be contacted at
aschlesinger@pecklaw.com
"Ongoing Storm" Rules for the Northeast (Connecticut, Massachusetts, New Jersey, New York & Rhode Island)
February 22, 2021 —
Angeline Ioannou, Kenneth Walton, Colin Hackett, Gregory Katz & Lauren Motola-Davis - Lewis BrisboisThe winter storm that recently brought several feet of snow to the Northeast signaled that we are, indeed, in the middle of winter. Moreover, our nation’s favorite groundhog, Punxsutawney Phil, saw his shadow on Groundhog Day this year, indicating that winter will be with us for six more weeks. As we move through the remainder of this snowy season, it is important for businesses to understand their legal obligations concerning snow removal and the defenses that are available to them in the event that an injury occurs on their premises. This alert summarizes the ongoing storm rules in Connecticut, Massachusetts, New Jersey, New York, and Rhode Island, and analyzes property owners’ snow removal responsibilities as well as related premises liability issues under these states’ laws.
Connecticut
It is well settled in Connecticut that, in the absence of unusual circumstances, in fulfilling their duty to invitees on their property, property owners may wait a reasonable time after the conclusion of a storm to perform ice and snow removal from outside walkways and steps. Kraus v. Newton, 211 Conn. 191, 197-198 (1989). A property owner’s duty to perform reasonable snow and ice removal of outside walkways does not arise until after a reasonable period of time has passed after a storm ends. Umsteadt v. G.R. Realty, 123 Conn. App. 73, 83 (2010). The ongoing storm doctrine does not apply, however, if the defective condition arises from preexisting ice or snow, and not from the ongoing storm. Whether the alleged defective condition was caused by preexisting ice or snow and whether a storm has concluded are both questions of fact that may be decided by a jury. Kraus at 197-198.
Reprinted courtesy of
Angeline Ioannou, Lewis Brisbois,
Kenneth Walton, Lewis Brisbois,
Colin Hackett, Lewis Brisbois,
Gregory Katz, Lewis Brisbois and
Lauren Motola-Davis, Lewis Brisbois
Ms. Ioannou may be contacted at Angeline.Ioannou@lewisbrisbois.com
Mr. Walton may be contacted at Ken.Walton@lewisbrisbois.com
Mr. Hackett may be contacted at Colin.Hackett@lewisbrisbois.com
Mr. Katz may be contacted at Greg.Katz@lewisbrisbois.com
Ms. Motola-Davis may be contacted at Lauren.MotolaDavis@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Ohio “property damage” caused by an “occurrence.”
May 18, 2011 —
CDCoverage.comIn JTO, Inc. v. State Automobile Mut. Ins. Co., No. 2010-L-062 (Ohio Ct. App. March 25, 2011), general contractor JTO was sued by hotel project owner Marriott for breach of contract and warranties seeking damages for the repair of construction defects resulting in moisture penetration property damage to interior components. JTO filed a third party complaint against subcontractor Farizel and also tendered its defense as an additional insured under Farizel’s State Auto CGL policy.
Read the full story…
Reprinted courtesy of CDCoverage.com
Census Bureau, HUD Show Declines in Residential Construction
May 17, 2011 – CDJ Staff
The U.S. Census Bureau and the Department of Housing and Urban Development released their summary of residential construction for April 2011 on May 17.
Building permits for privately owned housing units were down 4% from last month and 12% from last year. Similarly, privately-owned housing starts were down 10% from March and 23% below the previous year.
For further details, read the Census Bureau/HUD report
Read the court decisionRead the full story...Reprinted courtesy of
Condominium Association Responsibility to Resolve Construction Defect Claims
July 23, 2014 —
Nicholas D. Cowie – Maryland Condo Construction Defect Law BlogThe Maryland Court of Special Appeals recently issued an opinion in Greenstein v. Council of Unit Owners of Avalon Court Six Condominium Inc. finding that an association can be sued by its unit owner members if it fails to take timely legal action against a developer. In that case, the association was aware of construction defects, but failed to take action to preserve its claim and then filed a lawsuit against the developer too late, after the statute of limitations expired. As a result, the suit against the developer was dismissed and the association was forced to assess its unit owner members for the $1 million in repair costs. Some of the unit owners then sued their association, seeking to recover the cost of their assessments on the ground that the association was negligent in failing to pursue a timely legal action against the developer.
On appeal, the court was asked to decide whether state law permits owners to sue their condominium association for negligently failing to sue a developer for common element construction defects. The court, in an unpublished opinion, found that an association could be held liable to its members. The court said: “The duty to maintain, repair and replace the common elements together with the exclusive right to initiate litigation regarding the common elements [which was stated in a provision of the association’s bylaws] creates a concomitant obligation on the part of the [association] to pursue recovery from [the developer] on behalf of [the unit owners] for damage to the common elements caused by [the developer’s] negligence, breach of contract or violation of any applicable law.”
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas D. Cowie, Maryland Condo Construction Defect Law BlogMr. Cowie may be contacted at
ndc@cowiemott.com
TOLLING AGREEMENTS: Construction Defect Lawyers use them to preserve Association Warranty Claims during Construction Defect Negotiations with Developers
March 07, 2014 —
Nicholas D. Cowie – Maryland Condo Construction Defect Law BlogIf properly drafted, a tolling agreement stops, or “tolls,” the running of the statue of limitations and other time periods aplicable to an association’s legal claims while it attempts to negotiate the repair of and/or monetary compensation for construction deficiencies with the developer and other responsible parties. In short, it is a “time -out” that allows and association to preserve its legal claim so it can focus on settling its claims rather than pursing them in court.
Too often, condominium associations and homeowner associations (“HOA”) unknowingly allow their legal claims for construction defects to expire during lengthy negotiations with developers and builders. If negotiations fail, the association may turn to a construction defect attorney for legal representation only to find their construction defect legal claims are time barred because the statute of limitations or other legal time period has expired.
This article explains how condominium associations and HOAs can avoid this scenario by the use of tolling agreements to preserve their legal claims while engaged in potentially lengthy negotiations with developers to correct construction defects.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas D. Cowie, Maryland Condo Construction Defect Law BlogMr. Cowie may be contacted at
ndc@cowiemott.com
EPA Announces that January 2017 Revised RMP Rules are Now Effective
February 06, 2019 —
Anthony B. Cavender - Gravel2GavelOn December 3, the Environmental Protection Agency (EPA) published a Federal Register notice advising the regulated community that EPA’s controversial Clean Air Act (CAA) stationary source Risk Management Program (RMP) rules are effective as of December 3, 2018 – the Final Rule: Accidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act (83 FR 62268). The initial package of the RMP rules was promulgated in 1996, but a series of chemical explosions prompted the development of new rules, whose process safety, third party auditing, emergency response, preparedness and information sharing provisions were designed to confront these challenges.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Brown Paint Doesn’t Cover Up Construction Defects
April 25, 2012 —
CDJ STAFFIn a decision that describes the case as illustrating “the perils that real estate brokers and their agents assume when acting as a dual listing agent to both the buyers and sellers of the same house,” the California Court of Appeals has issued a decision in William L. Lyon & Associates v. The Superior Court of Placer County. Lyon & Associates sought summary judgment to dismiss the claims of the Henleys who bought a home in a transaction where a Lyon agent represented both sides.
The prior owners of the home, the Costas, had used a Lyon agent in purchasing their home. When they later sought to sell it, that agent “became aware of some of the house’s defects and problems.” In response, the Costas sought the help of another agent, Connie Gidal, also of Lyons & Associates. Photos taken in the presence of Ms. Gidal show defects of the paint and stucco. The Costas also took the step of painting the house dark brown. During the sale process, “rain caused many of the painted-over defects to reappear.” The Costas “purchased more dark brown paint and covered up the newly visible damage prior to inspection by the Henleys.”
With the damage concealed, the Henleys bought the home in May 2006. The agreement with Lyons & Associates noted that “a dual agent is obligated to disclose known facts materially affecting the value or desirability of the property to both parties.” Escrow closed on May 9, 2006. The contract with the broker included a two-year limit on the time to bring legal action.
The Henleys moved in during June 2006, and “began to discover construction defects that had been concealed by the Costas.” In addition to the painted-over stucco problems, the Henleys found that the Costas had “installed quartzite stone overlays on the backyard steps in a manner that caused water intrusion on the house’s stucco walls.”
In May 2009, the Henleys sued the Costas, Ron McKim Construction, Lyons & Associates, and Ms. Gidal. Their complaint alleged that Lyons & Associates had committed breach of contact, negligence, fraud, breach of fiduciary duty, and negligent nondisclosure in connection with the construction defects. The Costas named Lyons in a cross complaint. Lyons moved for summary judgments on the grounds that the two-year statute of limitations had expired before the complaint and cross-complaint were filed. Both the Henleys and the Costas opposed this claim. The court denied the motion and Lyons appealed.
The appeals court upheld the denial, noting that the both California Supreme Court decision and later action by the legislature compels real estate brokers and salespersons “to conduct a reasonably competent and diligent visual inspection of the property offered for sale.” The court noted that under California law, brokers have responsibilities to both sellers and buyers. The section of law cited by Lyons applies to seller’s agents. The court rejected the contention by Lyons that they were “cooperating brokers.” The Henleys were “not constrained by the two-year statute of limitations.”
Lyons contended that even if California’s statute did not apply, there was a contractual limit of two years. The court also rejected this, agreeing with the Henleys that “the two-year limitation period must be extended by the discovery rule.”
The court noted that “Lyon & Associates may not reap the benefit of a shortened contractual limitation period when its own alleged malfeasance contributed to the delay in the discovery of the buyer’s injury.” The court found that the Henleys could proceed with their breach of contract claim, because, “when a breach of contract is committed in secret, such as the intentional nondisclosure of a real estate broker regarding a previously visible construction defect, the contractual limitations period is properly held subject to the discovery rule.” The court felt that the interpretation favored by the California Association of Realtors would “halve the applicable statute of limitations period.”
In addition to rejecting Lyon request for summary judgment on the claims made by the Henleys, the court also rejected the request of summary judgment on the claims made by the Costas, concluding that neither claim is time-barred. Costs were awarded to both the Henleys and Costas.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of