Ready, Fire, Aim: The Importance of Targeting Your Delay Notices
November 08, 2021 —
Bradley Sands, Jones Walker LLP - ConsensusDocsProviding written notice of delay to subcontractors when a project is behind schedule is a regular part of good project documentation practices. A properly targeted delay notice is an important, project correspondence that is an appropriate response to a subcontractor’s specific delay or ongoing delays. However, when a project falls behind schedule and the project management team is in the fog of war, it could seem like a good idea to start firing off project delay notices to any and every subcontractor. While these delay notices may provide a short term burst of productivity, you could find that those same notices are aimed back at you in a future litigation.
This article identifies two potential unintended consequences of sending delay notices that a contractor should keep in its sights and then provides recommendations for properly calibrating future delay notices in light of these potential consequences.
Acceleration: You Might Get What You Ask For
A delay notice to a subcontractor could be interpreted as—or expressly state—direction to the subcontractor to accelerate its work. When a subcontractor is directed to accelerate its work, it may incur additional costs for premium, extended, or overtime labor, additional crews, increased supervision costs, increased overhead costs, and losses due to productivity impacts from the acceleration (e.g., stacking of trades and fatigue). A subcontractor may be entitled to recover these increased costs that are caused by a direction to accelerate.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley Sands, Jones Walker LLPMr. Sands may be contacted at
bsands@joneswalker.com
Biden’s Buy American Policy & What it Means for Contractors
February 22, 2021 —
Meredith Thielbahr & Nicole Lentini - Gordon & Rees Construction Law BlogJanuary 25, 2021, President Biden signed an Executive Order (EO) “Ensuring the Future is Made in All America by All of America’s Workers”, which seeks to bolster U.S. manufacturing through the federal procurement process. Note that, just six day earlier, on January 18, the Federal Acquisition Regulation (FAR) Counsel issued a final rule implementing former President Trump’s July 2019 EO, titled “Maximizing Use of American-Made Goods, Products, and Materials” (EO No. 13881) on the then-current Buy American standards. For context, Trump’s proposed revisions – adopted and implemented by the FAR Council earlier this year – imposed three (3) significant changes worth noting: (1) increasing the percentage of domestic content (other than iron or steel) from 50% to 55% that an end product must contain in order to qualify as a “domestic end product”; (2) implementing an even higher increase in the domestic content requirement for iron and steel products to at least 95% U.S. “predominately” iron or steel product; and (3) increasing the price evaluation preference for domestic offerors from 6% to 20% (for other than small business) and 30% (for small businesses). The FAR’s rule became effective January 21, 2021, and applies to solicitations issued on or after February 22, 2021, and resulting contracts let. Biden’s EO rescinds Trump’s EO No. 13881 “to the extent inconsistent with [Biden’s] EO.” However, when dissected, it is clear Biden’s Buy American plan does little to modify thresholds inconsistent with the Trump Administration; rather, the White House’s latest EO implements changes in the form of BA administration. Nonetheless, Biden’s EO does expressly note that it supersedes and replaces Trump’s EO on the same issues.
Reprinted courtesy of
Meredith Thielbahr, Gordon & Rees and
Nicole Lentini, Gordon & Rees
Ms. Thielbahr may be contacted at mthielbahr@grsm.com
Ms. Lentini may be contacted at nlentini@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of
Deadlines Count for Construction Defects in Florida
November 06, 2013 —
CDJ STAFFScott Kiernan, an attorney in the Orlando offices of Becker & Poliakoff, writing on their Florida Construction Law Authority site notes that “nothing lasts forever, especially the right to sue for building defects.” Under Florida law, according to Mr. Kiernan, the time in which a condominium association can file a construction defect is “only 4 years from the time that the Condominium Association knew or should have known of the defect(s).” However, for defects that aren’t even discovered during those first four years, there is a ten-year period where claims for latent defects can become the subject of a construction defect claim.
Read the court decisionRead the full story...Reprinted courtesy of
Top 10 Take-Aways from the 2024 Fall Forum Meeting in Pittsburgh
December 03, 2024 —
Marissa L. Downs - The Dispute ResolverOver 500 construction law attorneys and consultants convened last week at the confluence of three rivers in what became the first-ever meeting in Pittsburgh, Pennsylvania of the ABA Forum on Construction Law. The Steel City was a fitting backdrop for a meeting focused on issues of design in construction. Thanks to the hard work of many, most notably the newly minted Forum Chair Keith Bergeron and Meeting Coordinators Kendall Woods and Michael Clark, the meeting's attendees brought home new connections and a host of new lessons learned. Read on for my top 10 take-aways from the 2024 Fall Meeting in Pittsburgh and feel free to share yours in the comments below.
10. An architect's standard of care does not require perfection. A common refrain across many of the meeting's plenary sessions was that any design that is produced by human hands will never be perfect. In recognition of our own fallibility, the legal standard to which design professionals will be held to account does not require that their designs be error-free. A design professional must generally exercise the degree of care and skill ordinarily exercised by professionals performing similar services under similar circumstances. Establishing what that means in each locality will vary and will most likely need to be supported by the expert opinion of another practicing design professional.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Federal Court Rejects Insurer's Argument that Wisconsin Has Adopted the Manifestation Trigger for Property Policy
April 03, 2013 —
Tred Eyerly - Insurance Law HawaiiThe federal district court disagreed with the insurer's strident claim that Wisconsin followed the manifestation trigger for deciding coverage under a homeowner's policy. Strauss v. Chubb Indem. Ins. Co., 2013 U.S. Dist. LEXIS 224 (E.D. Wis. Jan. 2, 2013).
Several years after their house was constructed, the insureds discovered water damage. Chubb denied the claim. The insureds sued. Chubb moved for summary judgment and argued that the loss first manifested many years after its policy expired. Further, Chubb argued that Wisconsin followed the manifestation trigger for first-party property insurance, meaning that only the insurance policy in effect when the loss manifested was required to respond.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
The Value of Photographic Evidence in Construction Litigation
April 26, 2021 —
Marie Mueller - Construction ExecutiveIf a picture is worth a thousand words, can it be worth a thousand dollars? Ten thousand? Maybe, if it provides key evidence in a construction dispute. Litigating a construction case involves each side telling their story. Details and visual context make a story compelling. Evidence and corroboration make a story persuasive. Photographs can help on both of these fronts.
The Value of Photographic Evidence in Construction Litigation
Consider the following examples:
- A dispute relates to the timeliness of particular work. An employee has a memory of a load of materials arriving to the site later than it should have, but the records are incomplete or ambiguous about when it actually occurred. If the employee also took a photo of the materials, on the day they arrived, they could match up the date of the photo to their memory and build a clear timeline.
- A dispute relates to the presence or absence of obstructions in drilled shafts. There are no available photographs or videos of the work due to site restrictions. Presentation of this type of case may be severely limited by not being able to show photos depicting the size, shape and type of material removed from the shafts, and by the lack of video depicting the work.
Reprinted courtesy of
Marie Mueller, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Mueller may be contacted at
mmueller@verrill-law.com
ACS Recognized by Construction Executive Magazine in the Top 50 Construction Law Firms of 2021
September 06, 2021 —
Ahlers Cressman & Sleight PLLCACS is pleased to announce that the firm has been recognized by Construction Executive magazine in The Top 50 Construction Law Firms™ for 2021. Construction Executive ranked ACS number 31 among the top 50 construction practices in the country.
ACS is known for our depth of knowledge of the construction industry and experience in construction law. Our lawyers hold leadership positions within state and national industry organizations. Two of our lawyers are past chairs of the Washington State Bar Association’s Construction Law Section and the current chair, five of our lawyers have served as the Chair of the Associated General Contractors of Washington’s Legal Affairs Committee, and the majority of our lawyers are recognized as Super Lawyers and Rising Stars in Super Lawyers Magazine/Thomson Reuters.
Since it was first published in 2003, Construction Executive has become the leading trade magazine for news, market developments, and business issues impacting the construction industry. The magazine reaches more than 55,000 commercial, industrial, and institutional contractors and construction-related business owners. Each issue of Construction Executive includes articles designed to help owners and top managers run a more profitable and productive construction business.
Read the court decisionRead the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC
Florida Enacts Property Insurance Overhaul for Benefit of Policyholders
July 05, 2023 —
Laura Farrant & Bradley S. Fischer - Lewis BrisboisFort Lauderdale, Fla. (June 13, 2023) – On June 1, 2023, Governor Ron DeSantis signed into law CS/SB 7052 (the Act), increasing consumer protection and insurer accountability in Florida. The newly enacted and amended statutes under CS/SB 7052 bolster policyholder protections and impose greater insurer oversight, including heightened penalties for insurer misdeeds in the state under a new law that will take effect on July 1, 2023 (this legal alert does not address all of the statutory revisions associated with the Act). As House Speaker Paul Renner noted, “The insurance legislation signed by Governor DeSantis today . . . not only empowers homeowners, but also cultivates market-driven competition, ultimately leading to lower costs.”
Statutory Revisions Regarding Insurance Coverage
The Act prohibits authorized insurers from cancelling or nonrenewing a property insurance policy for a residential property or dwelling that was damaged by any covered peril until the earlier of: (a) when the property has been repaired; or (b) one year after the insurer issues the final claim payment. The Act also expands current law prohibiting authorized insurers from cancelling or nonrenewing a residential property insurance policy until 90 days after repairs are completed for damages resulting from a hurricane or wind loss that is the subject of a state of emergency declared by the Governor and for which the Office of Insurance Regulation (OIR) has issued an emergency order. See Fla. Stat. §627.4133(2)(d)(1)(a) and (b) (Notice of cancellation, nonrenewal, or renewal premium).
Reprinted courtesy of
Laura Farrant, Lewis Brisbois and
Bradley S. Fischer, Lewis Brisbois
Ms. Farrant may be contacted at Laura.Farrant@lewisbrisbois.com
Mr. Fischer may be contacted at Bradley.Fischer@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of