Is Your Contract “Mission Essential?” Recovering Costs for Performing During a Force Majeure Event Under Federal Regulations
May 10, 2022 —
Joneis M. Phan & Sarah K. Bloom - ConsensusDocsFederal contractors have faced unprecedented challenges performing during the COVID-19 pandemic. Additional costs have included delays and inefficiencies, site closures, quarantines, unavailability of supplies and materials, and full shutdowns of subcontractor operations. For contractors performing under fixed price contracts, the cost impact of COVID-19 was likely severe.
The Federal Acquisition Regulation (“FAR”) recognizes “epidemics” as a force majeure event that may excuse non-performance. Many federal contracts include some version of the Default clause, which prevents the government from terminating a contractor for default due to impacts of force majeure events that are beyond a contractor’s control, such as an epidemic. See, e.g., FAR 52.249-10. See also Pernix Serka Joint Venture v. Dep’t of State, CBCA No. 5683 (Apr. 20. 2020). The Default clause, however, operates as a shield from liability, not a sword authorizing recovery. Contractors are now left wondering whether any avenue exists to recover additional costs incurred after performing in the face of the COVID-19 pandemic.
In response to a likely influx of claims and requests for equitable adjustment due to COVID-19 impacts, the federal government largely took the position that contractors were entitled to extensions of time, but not to additional costs. This article explores the avenues that may be available for contractors to recover costs for performing during a force majeure event that would otherwise be non-compensable.
Reprinted courtesy of
Joneis M. Phan, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs and
Sarah K. Bloom, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs).
Mr. Phan may be contacted at jphan@watttieder.com
Ms. Bloom may be contacted at sbloom@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
It’s Time to Start Planning for Implementation of OSHA’s Silica Rule
May 03, 2017 —
Nathan Owens & Louis “Dutch” Schotemeyer – Newmeyer & Dillion LLPGetting a notification from OSHA that your company is being investigated for a health or safety violation is an unwanted disruption to your business that could lead to a hefty monetary fine. Worse yet, if your company is found to have committed multiple violations, OSHA may categorize your company as a severe violator, which makes you subject to follow-up inspections. In the last 6 years, OSHA has added 520 companies to the Severe Violator Enforcement Program - sixty percent of which are in the construction industry.
New OSHA regulations impacting the construction industry may result in more companies facing investigations and fines, or worse yet, laying off workers and unable to compete for new work. In 2013, OSHA proposed a new mandate to reduce silicosis in workers. The mandate, which was revised multiple times before being made final in March 2016, requires that employers ensure their workers are exposed to no more than 50 micrograms of crystalline silica in an eight hour period (down from the current standard of 250 micrograms). Under the new mandate, employers are also held to heightened reporting requirements, protective measures and medical testing for employees with extended exposure to silica.
In the construction industry alone, OSHA believes the new mandate will prevent 1,080 cases of silicosis and more than 560 deaths. Builder and trade groups believe the new mandate will result in the loss of tens of thousands of jobs and cost the building industry billions of dollars. The National Association of Home Builders estimates that the Silica Rule will cost homebuilders $1,500 per start. While the two sides mount their arguments and seek support, how to implement the rule and its long term feasibility are still contested questions.
Recognizing the challenges employers will have with the heightened requirements of the Silica Rule, OSHA just announced that enforcement is being delayed 90 days to develop additional guidance for implementation of the rule in the construction industry. The new start date for enforcement of the Silica Rule is September 23, 2017.*
Many in the industry are hoping the Trump administration repeals the Silica Rule like they have “blacklisting” and the Volks rule. However, until that happens, OSHA expects your company to implement processes to ensure compliance by the new start date.
*The Silica Rule was adopted by Cal/OSHA in August 2016 even though Cal/OSHA’s own silica standard had been in place since 2008. Cal/OSHA adopted the federal standard with the June 23, 2017 effective date; however; in an effort to synchronize with OSHA, Cal/OSHA recently announced that the effective date in California will also be September 23, 2017.
Nathan Owens is the Las Vegas Managing Partner of Newmeyer & Dillion, and represents businesses and individuals operating in a wide array of economic sectors including real estate, construction, insurance and health care in all stages of litigation in state and federal court. For questions related to the OSHA and the Silica Rule, you can reach him at Nathan.Owens@ndlf.com.
Louis “Dutch” Schotemeyer is an associate in Newmeyer & Dillion’s Newport Beach office. Dutch’s practice concentrates on the areas of business litigation, labor and employment law, and construction litigation. For questions related to OSHA or the Silica Rule, you can reach him at Dutch.Schotemeyer@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
When Is a Project Delay Material and Actionable?
January 11, 2022 —
Rick Erickson - Snell & Wilmer Real Estate Litigation BlogWelcome to 2022! This year, the construction industry will undoubtedly reflect on the last two years as unprecedented times plagued by construction project delays. The COVID-19 pandemic contributed to suspension of work and closure of construction projects worldwide in 2020. The end of 2021 brought additional delays caused by an inexplicable clog in the supply chain of construction materials. The combined impact of these events on project milestones and completion deadlines led our clients to ask, with unusual and particular urgency, who is liable for such delays and how do contracting parties lessen the consequences from such unexpected and uncontrollable delays.
Granted that project delays are nothing new or unusual. They were common enough before inflation caused shipping complications and pandemic decimated the construction labor force. All delays, whatever the source, variably cause loss to all players on a construction project. But not all delays matter when it comes to claims and remedies available to the contracting parties in dispute resolution, where the determinative focus is on material delays impacting the entire project and on delays the claimant can credibly prove.
Most, if not all, jurisdictions interpret actionable delays from the contract documents for the project. The contract is definitely where you should start before pursuing any delay remedies. Delay remedies may be a time extension only, or a time extension plus your additional general conditions. Some delay remedies may be barred by the contract’s express terms and may be enforced adversely by the courts when such contract terms are indisputable. See Quinn Constr. v. Skanska USA Bldg., Inc., 730 F. Supp. 2d 401, 411 (D.C. Pa. 2010) (enforcing the subcontractor’s contractual waiver of claims for delay and disruption damages). On the other hand, delay damages that are expressly allowed by the contract—like overtime necessitated by the delays—are usually actionable and recoverable. Id. However, not only the contract terms, but applicable law, may affect the outcome.
Read the court decisionRead the full story...Reprinted courtesy of
Rick Erickson, Snell & WilmerMr. Erickson may be contacted at
rerickson@swlaw.com
Construction Litigation Roundup: “A Close Call?”
August 05, 2024 —
Daniel Lund III - LexologyNot really, said a Florida state appellate court when a public construction project owner sued a defaulted general contractor after recovering from the general contractor’s surety.
The general contractor, Close Construction, entered into a contract for a lift station rehabilitation construction project with the City of Riviera Beach in Florida. During the course of the work the public owner terminated the contract, whereupon the GC and the owner brought claims against each other in court. A jury ultimately held against the general contractor and in favor of the public owner in the amount of approximately $1.9 million. The general contractor appealed.
On appeal, the general contractor noted that the public works surety which it was required by the contract to obtain for the project had hired another company to complete the work when the general contractor was terminated and had otherwise “settled with the District under its bond for $1,000,000.” Based on that settlement, the general contractor had moved, unsuccessfully, in the trial court for a post-trial setoff because the “settlement covered the same damages that the jury assessed” against the GC, and because the surety was “jointly and severally liable” with the GC – pursuant to the terms of the bond – for those damages. In essence, the general contractor sought to avoid having the public owner “obtain a double recovery.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
What Should Be in Every Construction Agreement
November 04, 2019 —
Patrick Barthet - Construction ExecutiveA detailed and coherent construction agreement in place on every job minimizes confusion, makes clear everyone’s respective responsibilities and reduces disputes. There are six things that should be addressed in every construction agreement.
DEFINE THE SCOPE
Define what the scope of work is that will be provided. Will it be only materials; will it be materials and labor; or will it be just labor? Be very clear and specific in how the scope of work is spelled out. Many contracts state that the contractor is responsible for all work that’s shown on the plans and specifications, as well as that which is reasonably inferable. While subjective—even if not actually on the plans or specifications, someone may believe that something should be part of the contractor’s work. This could expand what has to be done beyond what was understood or priced.
LIST ALL THE EXCLUSIONS
Do the parties each have the same understanding as to what is covered in the contract? How often are contractors faced with customers thinking something was included as part of the work? The contractor may have believed that task, or that material, or that specially fabricated item was excluded. But was it? Did the contractor articulate what was and was not in the scope and price? Specifically listing what is excluded can obviate this problem. Articulate what is not in the price or scope and reduce the chance of one party believing that something is to be done when it isn't.
Reprinted courtesy of
Patrick Barthet, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Barthet may be contacted at
pbarthet@barthet.com
Companies Move to Houston Area and Spur Home Building
December 30, 2013 —
CDJ STAFFA number of companies are developing commercial properties in the Kingwood area of the Houston metropolitan region and that’s spurring residential development as well. According to the Houston Chronicle, a number of key industries will be moving the area. And it’s leading to a lot of residential and commercial development.
The 4,000-acre mixed-use development Generation Park will include offices, hotels, shops, and other amenities. But an important part of its success is expected to come from the adjacent master-planned community, Summerwood. Another development, Kingwood Parc City Center will include retail, restaurants, a movie theater, and office space. Other development in the Kingwood area includes a $71 million addition to the Kingwood Medical Center. The new tower will specialize in services for women and infants.
Read the court decisionRead the full story...Reprinted courtesy of
Minneapolis Condo Shortage Blamed on Construction Defect Law
November 20, 2013 —
CDJ STAFFDemand for condos in the Minneapolis, Minnesota area is outstripping demand. Currently inventory of available condos represents less than four months’ worth of sales. But despite the demand, only three condominium buildings are under construction in the Minneapolis metropolitan area.
Some blame this on difficulty in finding financing, where some lenders are looking for projects to be sold before the builders get the money to build what they’ve just sold. Another problem is Minnesota construction defect law. “There are law firms in this town that have filed lawsuit after lawsuit on behalf of homeowners associations alleging construction defects,” said one builder, Kelly Doran, who now builds luxury apartment buildings. “”With that 10-year warranty, there’s no way I would build condos.”
Read the court decisionRead the full story...Reprinted courtesy of
Final Thoughts on New Pay If Paid Legislation in VA
August 15, 2022 —
Christopher G. Hill - Construction Law MusingsThis past General Assembly session, and after a governor’s amendment and with the convening of a study group, a new statute banning so-called “pay-if-paid” clauses from enforcement was passed. Some of the key features of the legislation are as follows:
It does not take effect until January 1, 2023, and,
For those construction contracts in which there is at least one general contractor and one subcontractor:
- It requires payment within 60 days of receipt of an invoice following the satisfactory performance of the work or within 7 days of receipt of payment by the Owner
- It allows for retainage
- It allows the higher-tier contractor to withhold money for improper performance
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com