Utah Supreme Court Allows Citizens to Block Real Estate Development Project by Voter Referendum
June 10, 2019 —
Sean M. Mosman & Mark O. Morris - Snell & Wilmer Under ConstructionThe Utah Supreme Court recently decided Baker v. Carlson, 2018 UT 59, which considered a developer’s ongoing effort to build a mixed-use, part-residential and part-commercial development on the site of the long-defunct Cottonwood Mall located in Holladay, Utah. On November 28, 2018, the Supreme Court affirmed the Third District Court’s ruling that a voter referendum to block the development was valid. This ruling calls into question the certainty of investment-backed real estate decisions in Utah and thus could carry negative implications for the Utah construction and real estate development communities.
The Cottonwood Mall opened in the early 1960s, and for several decades was a popular regional shopping destination. But the mall fell on financial hard times in the mid-1990s, and since 2007 the 57-acre lot has sat vacant. Around that time, the owner of the lot made plans to redevelop it, and asked Holladay City to rezone the site to permit mixed uses. In response, the City rezoned the lot as Regional/Mixed-Use (R/M-U). The City also created a process to control the development of an R/M-U zone, requiring prospective builders to first submit a site development master plan—which sets forth guidelines for the overall development and design of the site—to the City for approval. After the City approves a master plan, the developer must enter into a development agreement with the City, giving the developer certain rights and addressing other development-related issues.
Reprinted courtesy of
Sean M. Mosman, Snell & Wilmer and
Mark O. Morris, Snell & Wilmer
Mr. Mosman may be contacted at smosman@swlaw.com
Mr. Morris may be contacted at mmorris@swlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
KB to Spend $43.2 Million on Florida Construction Defects
August 27, 2013 —
CDJ STAFFIn their second quarter filing with the SEC, KB Homes estimates that repairing damage caused by defects in framing, stucco, roofs, and sealant will cost it $43.2 million. That estimate includes homes that are yet to be identified. KB had estimated lower costs earlier, but subsequently determined it was necessary to increase the funds by $15.9. As a result, the firm showed a loss in the second quarter. The company hopes to recover some funds in insurance settlements.
Read the court decisionRead the full story...Reprinted courtesy of
Anti-Concurrent Causation Clause Bars Coverage for Pool Damage
February 23, 2016 —
Tred R. Eyerly – Insurance Law HawaiiRelying upon the policy's anti-concurrent causation clause, the Illinois Court of Appeals affirmed the trial court's ruling that there was no coverage for a pool that popped out of the ground. Bozek v. Erie Ins. Group, 2015 Ill. App. LEXIS 940 (Ill. Ct. App. Dec. 17, 2015).
Following a rainstorm, the insureds reported damage to the swimming pool to Erie. An investigation determined that the heavy rain saturated soils around the pool. This created a significant uplift hydrostatic pressure. The weight of the water in the pool typically prevented the uplift forces, but the pool had been emptied to clean debris making it susceptible to uplift. The pool had a pressure relief valve to prevent uplift, but it was not working properly.
As a result, the pool was damaged to the point that it had to be replaced in its entirety. The heaving of the pool also damaged the concrete slab around the pool, which also had to be replaced.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Supreme Court of Kentucky Holds Plaintiff Can Recover for Stigma Damages in Addition to Repair Costs Resulting From Property Damage
August 15, 2018 —
Gus Sara - The Subrogation StrategistIn Muncie v. Wiesemann, 2018 K.Y. LEXIS 257, the Supreme Court of Kentucky considered whether stigma damages[1] in a property casualty case are recoverable in addition to the costs incurred to remediate the actual damage. The court held that stigma damages are recoverable in addition to repair costs, but the total of the stigma damages and repair costs cannot exceed the diminution in the fair market value of the property. The court’s decision establishes that if the repair costs are insufficient to make the plaintiff whole, a recovery for stigma damages up to the amount of the diminution in the market value of the home is appropriate.
Appellants Cindy and Jim Muncie incurred significant property damage to their home as a result of an oil leak originating from a neighboring property owned by the Estate of Martha Magel. In 2011, Auto Owners Insurance Company (Auto Owners), the liability carrier for the Estate’s testatrix, Patricia Weisman, filed an impleader complaint in federal court to discharge its obligation to settle the third-party liability claims on behalf of Ms. Weisman. Auto Owners reached a settlement with the Muncies for $60,000 which represented the remediation costs for the actual damage to the property. The settlement release reserved the Muncies’ right to pursue a claim for stigma damages associated with the oil leak.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and Williams LLPMr. Sara may be contacted at
sarag@whiteandwilliams.com
Delays Caused When Government (Owner) Pushes Contractor’s Work Into Rainy / Adverse Weather Season
January 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesThere are a number of horizontal construction projects where a contractor’s sequence of work and schedule is predicated on avoiding the rainy season (or certain force majeure events). The reason is that the rainy season will result in delays due to the inability to work (and work efficiently) during the adverse weather (including flooding caused by the weather). If the work is pushed into the rainy season, is such delay compensable if the government (or owner) delayed the project that pushed work out into the rainy season? It very well can be.
For example, in Meridian Engineering Co. v. U.S., 2019 WL 4594233 (Fed. Cl. 2019), a contractor was hired by the Army Corps of Engineers to construct a flood control project for a channel in Arizona. Due to delays, including those caused by the government, the project was pushed into the monsoon season, which caused additional delays largely due to flooding caused by the heavy rain. One issue was whether such delays were compensable to the contractor – the government raised the argument that the contractor assumed the risk of potential flooding from the rainy season. The Court found this argument unconvincing:
[The contractor’s] initial construction schedule planned for a completion of the channel invert work, a necessary step in protecting the site from flooding, to be completed by late June 2008…[M]any issues arose in the project’s early stages that led to cumulative substantial delay, including those caused by the government’s failure….The government cannot now claim that [the contractor] assumed the risk of flooding from monsoon season when the government was largely responsible for [the contractor’s] inability to complete the project prior to the beginning of the monsoon season. Simply put, the government cannot escape liability for flood damages when the government is responsible for causing the contractor to be working during the flood-prone season.
Meridian Engineering, 2019 WL at *7 (internal citations omitted)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Illinois Appellate Court Finds That Damages in Excess of Policy Limits Do Not Trigger Right to Independent Counsel
June 22, 2020 —
Jason Taylor - Traub LiebermanUnder Illinois law, an insurer’s duty to defend includes the right to control the defense, which allows insurers to protect their financial interest in the outcome of the litigation. However, where a conflict of interest exists, the insured, rather than the insurer, is entitled to assume control of the defense of the underlying action. If this occurs, the insurer satisfies its obligation to defend by reimbursing the insured for the cost of defense provided by independent counsel selected by the insured. What circumstances and situations arise to the level of an actual conflict of interest between the insurer and insured are often grounds for dispute.
In Joseph T. Ryerson & Son, Inc. v. Travelers Indemnity Co. of America, 2020 IL App (1st) 182491 (Apr. 7, 2020), the Illinois Appellate Court addressed whether damages awarded by a jury in excess of the policy limits were sufficient to trigger a right to independent counsel for post-trial and appellate proceedings. According to the Illinois Appellate Court, at least under the facts of the Ryerson case, the answer is “no.”
In Ryerson, Nancy Hoffman sued Ryerson for injuries sustained in a tractor-trailer accident. Ryerson tendered the suit to its primary insurer, Travelers, and its umbrella insurer, Illinois National. The policy limits were $2 million and $25 million, respectively. A jury found in favor of Hoffman for over $27.6 million in damages, and Ryerson appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Buyers Are Flocking to NYC’s Suburbs. Too Bad There Aren’t Many Homes to Sell.
February 20, 2023 —
Jennifer Epstein & Prashant Gopal - BloombergIn the midst of the worst US housing slump in a decade, a wave of finance and tech layoffs and drumbeats of a potential recession, open houses in affluent New York suburbs are packed.
Offers come in fast — sometimes for hundreds of thousands over asking.
A typical scene played out on a cloudy Sunday last month in Scarsdale, a suburb about 20 miles (32 kilometers) north of Manhattan known for its bucolic setting and high-rated schools. At the tail end of an open house, a dozen people were still wandering in and around a 1926 Tudor-style house listed for about $1.93 million.
An older couple took video on their iPhone for their offspring too busy to attend, while a younger man walked around with his infant in a chest carrier. The house was in need of some touch-ups. Somebody whispered that the hardwood floors were scratched, another said that the refrigerator looked warped, and a pair of kitchen cabinet doors was missing. It hardly mattered.
Reprinted courtesy of
Jennifer Epstein, Bloomberg and
Prashant Gopal, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Building Stagnant in Las Cruces Region
November 20, 2013 —
CDJ STAFFThere was an increase in the number of building permits issued in Las Cruces, New Mexico through the first ten months of 2013, but the 2,162 permits represent only a minimal increase over last year’s 2,158 permits. To make matters worse for building suppliers and workers, builders can “pull all the permits for a subdivision at one time but might not start some of those for six months,” said Lee Rawson, the owner of Rawson Builders Supply.
For a comparison, during the building boom of 2006, Las Cruces issued 3,529 building permits. The values are down too. Although fewer permits were issued in 2012, their valuation was $147 million, while the marginally larger number in 2013 is worth only $128 million.
As a result, the area is losing skilled labor. After 25 consecutive months of declining construction, workers are leaving the construction industry. Mr. Rawson noted that “you can’t just go find that skilled labor, it doesn’t exist.”
Read the court decisionRead the full story...Reprinted courtesy of