Pennsylvania Sues Firms to Recoup Harrisburg Incinerator Losses
June 06, 2018 —
Jonathan Barnes - Engineering News-RecordThe state of Pennsylvania continues to try to recover funds from professional firms involved in the city of Harrisburg’s disastrous incinerator project in the early 2000’s and has named, Buchart Horn, Inc., an engineering, architecture and planning firm based in York, Pa. as a defendant.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan Barnes, ENRENR staff may be contacted at
ENR.com@bnpmedia.com
Construction Venture Sues LAX for Nonpayment
February 05, 2014 —
Beverley BevenFlorez-CDJ STAFFConstruction joint venture Walsh/Austin filed suit against the Los Angeles International Airport, claiming that “the airport failed to properly pay more than $2.4 million to an electrical subcontractor,” according to The Daily Breeze. Furthermore, SASCO, the electrical firm, alleged that they were “given inaccurate design documents that made it impossible for the company to carry out the work at the agreed-upon rate.”
The complaint, as reported by The Daily Breeze, cited “other lawsuits brought by an Orange County plastering firm and a Buena Park door company” and suggested that “eventually, all the litigation tied to nonpayment at LAX will end up in the same courtroom.”
Nancy Castles, a spokeswoman for Los Angeles World Airports, told The Daily Breeze that “the agency does not comment on pending litigation.”
Read the court decisionRead the full story...Reprinted courtesy of
Five Keys to Driving Digital Transformation in Engineering and Construction
January 02, 2019 —
Rob Phillpot - Construction ExecutiveEngineering and construction companies increasingly find themselves navigating an era of disruptive and transformative change driven by technology. And with the industry going strong and construction employment recently reaching a 10-year high, more companies recognize that it is time to embrace the efficiencies digital transformation brings, in large part to protect or enhance their competitive position.
A report from the Global Industry Council notes that modern technology is moving to the strategic center of E&C business models as part of an evolutionary process.
Reprinted courtesy of
Rob Phillpot, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
ASCE Statement on Senate Passage of the Water Resources Development Act of 2024
August 12, 2024 —
Marsia Geldert-Murphey, President of the American Society of Civil EngineersWASHINGTON — The
American Society of Civil Engineers (ASCE) commends the Senate for passing S. 4367, the Thomas R. Carper Water Resources Development Act (WRDA) of 2024. Both the House and Senate versions of WRDA will help improve America's ports and inland waterways, enhance flood risk management and storm risk reduction programs, and prioritize ecosystem restoration. ASCE now urges Congress to swiftly conference and pass a final WRDA bill in the upcoming months.
The Senate version of WRDA includes key provisions that will help ensure the ongoing operation of America's inland waterways systems, which received a 'D+' on the
2021 Report Card for America's Infrastructure, including adjustments to the cost share requirements for rehabilitation projects that receive funding the Inland Waterways Trust Fund (IWTF). These changes will ensure the IWTF remains available for future projects to help reduce the backlog of inland waterways projects. This bill also creates a Levee Owners Advisory Board, which has the potential to improve communication between the U.S. Army Corps of Engineers, other federal agencies, and levee owners and operators.
Now that the House and Senate have passed their versions of WRDA, we encourage lawmakers to include several provisions included in the House version in their final conference bill. This includes the reauthorization of the National Dam Safety Program through 2028, provisions that reduce restrictions on the amount of funds states can receive in National Dam Safety Program State Assistance Grants; improves access to the High Hazard Potential Dam Rehabilitation Grant Program; and requires the incorporation of low-head dams into the National Inventory of Dams, and an extension of the National Levee Safety program through 2033.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 160,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
Don’t Get Caught Holding the Bag: Hold the State Liable When General Contractor Fails to Pay on a Public Project.
January 31, 2018 —
Sean Minahan – Construction Contract AdvisorAccording to a quick Google search the term
“holding the bag” comes from the mid eighteenth century and means be left with the onus of what was originally another’s responsibility. Nobody wants to be left holding the bag. But that is the situation our client (subcontractor) found themselves in when upon completion of a public project the general contractor went out of business before paying the remaining amount due and owing to our client.
Under Nebraska law, liens are not allowed against public projects. Instead the subcontractor is to make a claim on the payment and performance bond secured by the general contractor at the start of the project. In our case, the general contractor never secured a bond on which to make a claim; consequently, leaving our client holding the bag.
Read the court decisionRead the full story...Reprinted courtesy of
Sean Minaham, Lamson, Dugan and Murrary, LLPMr. Minahan may be contacted at
sminahan@ldmlaw.com
Courthouse Reporter Series: The Travails of Statutory Construction...Defining “Labor” under the Miller Act
August 01, 2023 —
Brendan J. Witry - The Dispute ResolverIn a recent case—United States ex rel. Dickson v. Fidelity & Deposit Co. of Maryland (“Dickson”)—the U.S. Court of Appeals for the Fourth Circuit recently re-examined and defined what work qualifies as “labor” under the Miller Act.
United States ex rel. Dickson v. Fidelity & Deposit Co. of Maryland, No. 21-160, 67 F.4th 182 (4th Cir. April 26, 2023) (slip op.).
Unlike private projects, unpaid subcontractors cannot encumber the federal government’s property with mechanics liens. Instead, the Miller Act provides a remedy for subcontractors in the form of a payment bond on all federal public works contracts exceeding $100,000. 40 U.S.C. § 3131(b).
In the Dickson case, Claimant Elliot Dickson served as a subcontractor to Forney Enterprises (“Forney”), with whom the Department of Defense (the “DOD”) contracted to renovate several staircases and the fire suppression systems at the Pentagon.
Read the court decisionRead the full story...Reprinted courtesy of
Brendan J. Witry, Conway & Mrowiec Attorneys LLLPMr. Witry may be contacted at
bjw@cmcontractors.com
Everyone’s Working From Home Due to the Coronavirus – Is There Insurance Coverage for a Data Breach?
May 18, 2020 —
Heather Whitehead & Jeff Dennis - Newmeyer DillionMost organizations are now requiring that their employees work from home (“WFH”) with the ongoing COVID-19 (commonly referred to as the Coronavirus) pandemic. These remote working arrangements provide new opportunities for hackers to infiltrate computer systems, and not surprisingly, attempted cyber attacks are on the rise. Given the rapid deployment of employees being forced to work from home, many employees are using their personal laptops, tablets and other devices to complete their work. The use of such personal devices increases the risk to network systems, including a potential breach or data loss.
However, in the event of a breach or other incident, there may be limitations in your cyber liability insurance policy based upon the type of hardware being used. Businesses need to be proactive to protect themselves from attacks by practicing vigilant cyber safety, and also reviewing their insurance policies in detail for coverage considerations prior to the occurrence of any cyber incident.
Reprinted courtesy of
Heather H. Whitehead, Newmeyer Dillion and
Jeffrey M. Dennis, Newmeyer Dillion
Ms. Whitehead may be contacted at heather.whitehead@ndlf.com
Mr. Dennis may be contacted at jeff.dennis@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Homeowner may pursue negligence claim for construction defect, Oregon Supreme Court holds
March 01, 2011 —
Lori Bauman, Ater Wynne LLPIn Abraham v. T. Henry, Oregon’s court of appeals held that a Oregon’s court of appeals holds that a homeowner may sue builder for common law negligence absent a contractual provision that forecloses such a claim. Plaintiff homeowners hired defendant contractors to build a house. When plaintiffs discovered defects in the construction years later, they sued for negligence.
The Court of Appeals held that the parties’ contractual relationship did not prevent a negligence claim, and that plaintiffs were entitled to pursue a negligence per se claim based on a violation of the Oregon Building Code.
The Supreme Court affirmed, but on a somewhat different basis. First, according to the Court, a construction defect claim concerns damage to property — and not mere economic losses — and thus is not barred by the economic loss doctrine. Second, the existence
Read Full Story...
Read the court decisionRead the full story...Reprinted courtesy of