Failure to Consider Safety Element in Design Does Not Preclude Public Entity’s Discretionary Authority Under Design Immunity Defense
May 16, 2018 —
Garret Murai - California Construction Law BlogIn Rodriguez v. Department of Transportation, Case No. F074027 (March 27, 2018), the Court of Appeals for the Fifth District considered the following mind-twister: Can you knowingly approve something (which does not include something else) if you never considered the absence of that “something else?” Think about that for a moment . . . or, better yet, just read on.
Rodriguez v. Department of Transportation
In 2013, a pickup truck traveling westbound on State Route 152 toward Los Banos, California, ran off the road injuring Erik Rodriguez and the driver and killing another passenger. Rodriguez sued the California Department of Transportation (Caltrans) on the ground that the accident was caused by a dangerous condition on public property.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Transportation Officials Make the Best of a Bumpy 2020
January 18, 2021 —
Jim Parsons & Aileen Cho - Engineering News-RecordThe year 2020 provided a bumpy budgetary ride for all modes of transportation, and some industry insiders don’t expect airport and transit ridership to return to pre-pandemic levels for years. Agencies are taking lessons learned, coupled with hopes for the new Biden administration, to carry on as best they can.
Reprinted courtesy of
Jim Parsons, Engineering News-Record and
Aileen Cho, Engineering News-Record
Ms. Cho may be contacted at choa@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Penalty for Failure to Release Expired Liens
April 02, 2024 —
William L. Porter - Porter Law GroupI was recently contacted by a commercial building owner in the process of trying to sell his building. Two years prior to this, a subcontractor had recorded a mechanics’ lien with the local County Recorder’s office in relation to the owner’s property. The subcontractor recorded the mechanics lien after the subcontractor was not paid by a prime contractor for work the subcontractor had performed on the property. Unfortunately, the subcontractor then failed to file a lawsuit to foreclose on the lien within the requisite ninety (90) day time period for filing a lawsuit to foreclose on the mechanics’ lien. Since the subcontractor missed this 90 day deadline to file the mechanics lien foreclosure lawsuit, the mechanics lien expired and became unenforceable.
Subject to certain exceptions, under California Civil Code Section 8460, a lawsuit to foreclose on a mechanics lien must be filed within ninety (90) days after the mechanics lien is recorded or the mechanics lien expires. Although the mechanics lien had expired, the title company and intended purchaser of the building and property were perhaps understandably insistent that the mechanics lien constituted a cloud on title to the property and must be removed from the official records for the property. The prospective purchaser would not buy the property unless the mechanics’ lien was removed.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Continuing Breach Doctrine
May 28, 2024 —
David Adelstein - Florida Construction Legal UpdatesHave you ever heard of the “continuing breach” doctrine? Probably not. It is not a doctrine commonly discussed. It’s a doctrine used to try to argue around the statute of limitations.
In an older Southern District Court of Florida case, Allapattah Services, Inc. v. Exxon Corp., 188 F.R.Ed. 667, 679 (S.D.Fla. 1999), the court explained: “Under this [continuing breach] doctrine, a cause of action for breach of a contract does not begin to accrue upon the initial breach; rather, on contracts providing serial performance by the parties, accrual of a breach of contract cause of action commences upon the occurrence of the last breach or upon termination of the contract.”
Recently, this doctrine came up in an opinion by Florida’s Fifth District Court of Appeal. In Hernando County, Florida v. Hernando County Fair Association, Inc., 49 Fla.L.Weekly D947b (Fla. 5th DCA 2024), a plaintiff appealed the trial court’s dismissal with prejudice of its breach of contract claim based on the statute of limitations. The plaintiff claimed the defendant breached the contract by its failure to substantially redevelop property. The trial court dismissed based on the statute of limitations. However, the complaint alleged the defendant’s failure to comply “with numerous other intertwined, ongoing, and continuing contractual duties and obligations.” Hernando County, supra. The Fifth District reversed based on the continuing breach doctrine: “Where the nature of the contract is continuous, statutes of limitations do not typically begin to run until termination of the entire contract.” Id. quoting and citing Allapattah Servs., Inc.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
PA Supreme Court to Rule on Scope of Judges' Credibility Determinations
April 20, 2016 —
Max Kimbrough – White and Williams LLPIn IA Construction v. WCAB (Rhodes), the Commonwealth Court reversed the WCJ’s decision to deny the employer’s Modification Petition on the basis that the employer’s medical expert was not credible. In the underlying case, the claimant was determined to have sustained compensable work injuries to his head, neck and back. The employer subsequently filed a Modification Petition, seeking to modify benefits to Partial Disability based on an Impairment Rating Evaluation (IRE) which found that the claimant had a 34% whole body impairment. The WCJ ultimately denied the employer’s Modification Petition, finding that the IRE physician's categorization of the claimant's injuries and interpretation of the claimant's impairment level from his brain injury was not credible.
Read the court decisionRead the full story...Reprinted courtesy of
Max Kimbrough, White and Williams LLPMr. Kimbrough may be contacted at
kimbroughm@whiteandwilliams.com
Wheaton to Require Sprinklers in New Homes
November 06, 2013 —
CDJ STAFFThe town of Wheaton, Illinois is considering a change to its building codes, based on the recommendations made in the 2012 building code, released by the International Code Council. Eighty-two towns in Illinois already require new homes to have fire sprinklers. Wheaton did not adopt any changes from the 2006 or 2009 building code; they are currently using the standards of the 2003 edition.
Read the court decisionRead the full story...Reprinted courtesy of
Unpredictable Opinion Regarding Construction Lien (Reinstatement??)
January 17, 2023 —
David Adelstein - Florida Construction Legal UpdatesHere comes the discussion of an appeal I was intimately involved in dealing with a construction lien. See Suntech Plumbing and Mechanical Corp. v. Bella Isla, LLC, 2022 WL 14672765 (Fla. 3d DCA 2022). Unfortunately, it was a losing result on my end but not a losing result to the issue at-hand. You should ask what in the world does this mean. I will tell you.
Here is the fact pattern. A subcontractor files a construction lien foreclosure lawsuit against an owner for unpaid contract balance. In the same lawsuit, the subcontractor sues the general contractor for breach of contract and unjust enrichment associated with an approximate three-year delay on a construction project. The project was scheduled to be completed in 2019. It was not. The project was pushed into COVID and into 2022. (The subcontractor did not sue the general contractor for amounts subject to the lien foreclosure claim.) The general contractor, assuming the defense of the owner, moved to stay the lawsuit pending the outcome of arbitration based on an arbitration provision in the subcontract. The subcontractor did not dispute the arbitration provision, but argued that arbitration provision should not extend to the owner that was (a) not bound by the subcontract, (b) would not be a party to the arbitration, and (c) the amounts pled against the general contractor did not include the amounts subject of the lien foreclosure lawsuit. At a minimum, the lawsuit should be stayed, not dismissed. Nevertheless, the trial court dismissed the entire lawsuit in an order that states that it is a final order with language that the lien may be “reinstated” after the outcome of the arbitration (that the owner is not a party to).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Dispute Over Exhaustion of Primary Policy
May 20, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn a dispute between the excess and primary carriers, the Fifth Circuit determined the primary policy was exhausted, triggering coverage under the excess policy. Amerisure Mut. Ins. Co. v. Arch Spec. Ins. Co., 2015 U.S. App. LEXIS 6627 (5th Cir. April 21, 2015).
Amerisure issued a CGL policy to Admiral Glass & Mirror Co. The policy provided excess over any coverage under a controlled insurance program policy. Arch issued an Owner Controlled Insurance Program (OCIP) policy to Endeavor Highrise, LP and to its contrators and subcontractors for bodily injury and property damage arising out of the construction of the Endeavor Highrise. Admiral was a subcontractor insured under the OCIP.
The OCIP had combined bodily injury and property damage limits of $2,000,000 per occurrence, a general aggregate limit of $2,000,000 and a products-completed operations aggregate limit of $2,000,000. The OCIP contained a Supplementary Payments provision which provided that Arch would pay "[a]ll expenses we incur" in connection with any covered claim, and that "[t]hese payments will not reduce the limits of insurance." Endorsement 16, however, expressly deleted and replaced this statement with: "[supplementary payments] will reduce the limits of insurance." The OCIP also provided that Arch's duty to defend ended "when we have used up the applicable limit of insurance in the payment of judgments or settlements."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com