Michigan Court Waives Goodbye to Subrogation Claims, Except as to Gross Negligence
March 13, 2023 —
Lian Skaf - The Subrogation StrategistIn Ace American Insurance Company, et. al. v. Toledo Engineering Co., Inc., et. al., No. 18-11503, 2023 U.S. Dist. LEXIS 15222 (Ace American), the United States District Court for the Eastern District of Michigan determined whether insurers could pursue their subrogation claims against the defendants despite a waiver of subrogation in each of the contracts the insured had with the respective defendants. Based on the language of the contracts and the circumstances leading up to the loss, the court held that the insurers could not pursue their subrogation claims – other than their claims for gross negligence – due to waivers of subrogation in the applicable contracts.
In Ace American, the insured, Guardian Industries, LLC (Guardian), retained Toledo Engineer Co., Inc. (TECO) and Dreicor, Inc. (Dreicor) to renovate a glass furnace in the insured’s glass manufacturing plant. Guardian and TECO entered into a contract on December 6, 2016. Guardian and Dreicor entered into a contract on September 29, 2013, that the parties later updated on June 3, 2016. Both defendants began work on the project in the spring of 2017 and were finished with the portion of the work known as the “Cold Tank Repair” prior to the loss.
On June 3, 2017, there was an explosion and fire at the plant that caused significant property damage. The plaintiff insurers (Plaintiffs) made payments in the amount of $80 million and became subrogated to its insured’s rights. Plaintiffs then initiated this action.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
Lumber Liquidators’ Home-Testing Methods Get EPA Scrutiny
June 10, 2015 —
Matthew Townsend – BloombergThe home testing method Lumber Liquidators Holdings Inc. is using to reassure customers that their floors are safe is being questioned by the U.S. Environmental Protection Agency.
In response to allegations that its Chinese-made laminate flooring emitted excessive levels of formaldehyde, a known carcinogen, Lumber Liquidators sent thousands of do-it-yourself tests to people who’d purchased the products. Customers use a device in the kit to measure the air in their homes for 24 hours, then send the package back to have the results evaluated.
While the EPA didn’t take a position on the specifics of Lumber Liquidators’ test program, the agency said on its website that home air testing “may not provide useful information due to the uncertainties” of the method. Air tests don’t pinpoint the specific source of a contaminant, and there are no widely accepted standards for indoor formaldehyde levels, the agency said.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew Townsend, Bloomberg
Paul Tetzloff Elected As Newmeyer & Dillion Managing Partner
June 03, 2019 —
Newmeyer & Dillion LLPNewmeyer & Dillion LLP, a prominent business and real estate law firm, selected Paul Tetzloff as the firm's Managing Partner. His term began on January 1, 2019. A business litigator, Tetzloff will now oversee the firm's strategic plan and manage the firm's day-to-day business affairs.
"The Firm is incredibly fortunate to have Paul stepping into the role as Managing Partner. His energy, intelligence, leadership, and drive make him uniquely qualified to lead this Firm for years to come," said former Managing Partner Jeff Dennis. "I am excited to watch where the Firm is headed – we have such an amazing opportunity to continue to develop to even greater heights, and Paul will be a huge part of making that happen."
Active in his community, Tetzloff sits on the board for HomeAid Orange County and the Marine Raider Association.
Tetzloff is succeeding Dennis, who served in the role from 2012 to 2018. "Jeff was our managing partner for seven years and he did an outstanding job. We owe Jeff a debt of gratitude for his service," said Tetzloff of his predecessor. "I'm looking forward to continuing to build on the groundwork laid to help the firm reach new levels in the years to come."
Dennis' leadership allowed the firm to grow substantially under his tenure, including opening a Las Vegas, Nevada office and establishing thriving practice areas throughout various industries. Dennis will focus his energy on overseeing the firm's growing Privacy and Data Security practice.
Paul Tetzloff
paul.tetzloff@ndlf.com
Practice Areas
Business Litigation
Construction Litigation
Real Estate Litigation
About Newmeyer & Dillion
For almost 35 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, privacy & data security and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client's needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Wisconsin Court of Appeals Re-affirms American Girl To Find Coverage for Damage Caused by Subcontractors
September 20, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe trial court's finding of no occurrence and no property damage due to faulty workmanship was reversed by the appellate court. No. 5 Walworth v. Engerman Contracting, Inc., 2021 Wis. App. LEXIS 401 (Wis. Ct. App, July 30, 2021).
Engerman was the general contractor on a construction project at a residence. Engerman was hired to build a poll complex. Engerman subcontracted the project to Downes Swimming Pool Co., Inc. Downes purchased shotcrete (sprayed concrete) from Otto Jacobs Company LLC for the swimming poll walls and base.
After completion, the pool immediately began leaking. An investigation determined that the shotcrete material was not installed correctly, contributing to cracking in the pool walls and the steel reinforcing bars were not sufficient to prevent cracks in the pool walls. The owner demolished the pool and constructed a new one. Thereafter, the owner sued Engerman, its insurers (General Casualty Company of Wisconsin and West Bend Mutual Insurance Company) and Downes and its insurer. Downes filed a third-party complaint against Jacobs and its insurer (Acuity Mutual Insurance Company) alleging Jacobs negligently provided inferior shotcrete to Downes.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Times Square Alteration Opened Up a Can of Worms
January 26, 2017 —
Nadine M. Post – Engineering News-RecordCompared with some of its Manhattan neighbors, a high-rise on the corner of Seventh Avenue and West 47th Street looks standard. Like many buildings in Times Square, the 41-story retail-entertainment-hotel development, nearly topped out, has a tower springing from a boxy base that will sport a flashy billboard.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, Engineering News-RecordMs. Post may be contacted at
postn@enr.com
Insurance Policies Broadly Defining “Suits” May Prompt an Insurer’s Duty to Defend and Indemnify During the Chapter 558 Pre-Suit Notice Process
May 30, 2018 —
Daniel Garcia - Gordon & Rees Construction Law BlogIn Altman Contractors, Inc. v. Crum & Forster Specialty Insurance Company, No. SC16-1420, 2017 WL 6379535 (Fla. Dec. 14, 2017), the Florida Supreme Court addressed whether the notice and repair process set forth in chapter 558, Florida Statutes, constitutes a “suit” within the meaning of a commercial liability policy issued by Crum & Forster Specialty Insurance Company (“C&F”) to Altman Contractors, Inc. (“Altman”). The Court found that because the chapter 558 pre-suit process is an “alternative dispute resolution proceeding” as included in the definition of “suit” in the policy by C&F to Altman, C&F had a duty to defend Altman during the chapter 558 process, prior to the filing of a formal lawsuit.
Chapter 558, titled “Construction Defects,” sets forth procedural requirements before a claimant may file a construction defect action. It requires a claimant to serve a written notice of claim on the applicable contractor, subcontractor, supplier, and/or design professional prior to filing a construction defect lawsuit. The legislature intended for Chapter 558 to be an alternative dispute resolution mechanism in certain construction defect matters allowing an opportunity to resolve the claim without further legal process.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Garcia, Gordon & Rees Scully MansukhaniMr. Garcia may be contacted at
daniel.garcia@grsm.com
Chimney Collapses at South African Utility’s Unfinished $13 Billion Power Plant
November 21, 2022 —
Paul Burkhardt - BloombergSouth Africa’s newest coal-fired power plant, which has been under construction since 2008 and will cost an estimated 232 billion rand ($12.7 billion), shut one of its six generating units after a duct collapsed.
The unit at the Kusile plant could remain offline “for a few months” although a clearer estimate will be known over coming weeks, state-owned utility Eskom Holdings SOC Ltd. said in a statement late Wednesday. The outage comes as the country endures record blackouts -- locally known as loadshedding.
The duct appeared to have sheared off from the unit’s main structure, a photo posted on Twitter by Anton Eberhard, a professor at the University of Cape Town’s Graduate School of Business, showed.
Read the court decisionRead the full story...Reprinted courtesy of
Paul Burkhardt, Bloomberg
Las Vegas, Back From the Bust, Revives Dead Projects
June 11, 2014 —
Brian Louis – BloombergFor almost five years, the desert plot at the western edge of the Las Vegas valley was home to hulking steel skeletons -- ghostly ruins of a construction project halted by the recession.
Now the 106-acre (43-hectare) site bustles with hundreds of workers building the first phase of Downtown Summerlin, an office, entertainment and retail complex that’s scheduled to open in October. Howard Hughes Corp. (HHC) revived the development last year after the previous owner, General Growth Properties Inc., shut it down in 2008.
The commercial real estate market in Las Vegas, littered with vacant buildings and abandoned construction sites by overreaching developers during the U.S. property crash, is coming back to life as the local economy improves and tourists return to the nation’s gambling capital. Blackstone Group LP’s deal to buy the Cosmopolitan resort and Genting Bhd. (GENT)’s proposed resurrection of an abandoned project on Las Vegas Boulevard are further signs of investor confidence in the nascent recovery.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Louis, BloombergMr. Louis may be contacted at
blouis1@bloomberg.net