N.J. Appellate Court Applies Continuous Trigger Theory in Property Damage Case and Determines “Last Pull” for Coverage
November 15, 2017 —
K. Alexandra Byrd – Saxe Doernberger & Vita, P.C.The New Jersey Superior Court, Appellate Division, published an important decision addressing several fundamental issues regarding how a commercial general liability (CGL) policy applies to long-term property damage. The court held that: (1) a continuous trigger theory of coverage may be applied to third-party liability claims involving progressive property damage caused by an insured’s allegedly defective work; (2) the “last pull” (i.e., the cutoff point) of the continuous trigger is when the “essential nature and scope” of the property damage first becomes known or could reasonably be known; and (3) the “last pull” is not when the property damage is “attributed” to the insured’s faulty work.
The underlying action in Air Master & Cooling Inc. v. Selective Ins. Co., et al. 1 concerned property damage arising out of the construction of a seven-story, 101-unit condominium building in Montclair, New Jersey. The project’s construction manager hired Air Master & Cooling, Inc. (Air Master) to perform HVAC work on the project, including installing individual HVAC equipment in each resident’s unit from 2005 to 2008. In early 2008, unit owners began complaining about water infiltration and damage to their windows, ceilings, and other portions of their units. The general contractor and developer began assessing the damage and making repairs. Eventually, in April 2010, an expert consultant performed a moisture survey of the roof and discovered 111 areas that were damaged by water infiltration. The expert report indicated that “it [was] impossible to determine when [the] moisture infiltration occurred.”
Read the court decisionRead the full story...Reprinted courtesy of
K. Alexandra Byrd, Saxe Doernberger & Vita, P.C.Ms. Byrd may be contacted at
kab@sdvlaw.com
Senate Committee Approves Military Construction Funds
June 29, 2011 —
CDJ STAFFWith a decrease in funding, as compared to the House bill, the Military Construction and Veteran’s Affairs subcommittee of the Senate moved on a $72 billion construction bill. The House version had approved an additional half billion dollars in funding. Senator Tim Johnson, Democrat of South Carolina, said that he expected easy reconciliation with the House version. The Senate bill will move to the full Senate Appropriations Committee on June 30.
The bill, S 1255, includes funding for construction and remodeling of military housing, as well as construction and remodeling of base facilities.
Read the full story… Read S1255
Read the court decisionRead the full story...Reprinted courtesy of
Claim for Consequential Damages Survives Motion to Dismiss
November 14, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe insured's claim for consequential damages survived the insurer's motion to dismiss. Tiffany Tower Condominium, LLC v. Ins. Co. of the Greater N.Y., 2018 N.Y. App. Div. LEXIS 5783 (N.Y. App. Div. Aug. 22, 2018).
Tiffany Tower submitted a claim in November 2012 with Insurance Company of the Great New York for damages sustained by its building during Superstorm Sandy. The insurer paid the original claim in December 2012. Then, in September 2014, Tiffany Tower submitted a supplemental claim for additional losses which it asserted were caused by the storm. The insurer denied the supplemental claim.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Dispute Review Boards for Real-Time Dispute Avoidance and Resolution
August 20, 2019 —
Neal J. Sweeney, Esq. - ConsensusDocsThe use of dispute tribunals generally referred to as Dispute Review Boards or DRBs on major projects has matured. Use of a DRB cannot guarantee elimination of post-project litigation, but when used properly, a DRB can be an enormously effective tool to avoid and resolve disputes rapidly and during construction.
The modest out-of-pocket costs of a DRB can pay big dividends. DRBs offer the opportunity to shorten the life cycle of a dispute by requiring the principals to confront and address the merits of their dispute, rather than simply hunkering down and focusing on posturing and preparing for arbitration or litigation. Even when a DRB cannot immediately resolve a dispute, the process can still facilitate subsequent settlement and cost-effectively prepare both parties for formal adjudication. DRBs can also enhance communications and help the parties avoid and resolve problems before they spiral into disputes.
DRBs were first and are most widely used on big civil and infrastructure projects, but the benefits of a DRB extend equally to major building projects, particularly hospitals, and industrial projects and should be used in those sectors.
Read the court decisionRead the full story...Reprinted courtesy of
Neal J. Sweeney, Esq., Jones Walker LLPMr. Sweeney may be contacted at
nsweeney@joneswalker.com
Construction Contracts Need Amending Post COVID-19 Shutdowns
October 19, 2020 —
Richard P. Higgins - Construction ExecutiveNo one could have expected the coronavirus pandemic in the beginning of 2020. True, there were rumblings about a sickness in China that was highly contagious and infecting many people. Death tolls began rising as the world watched in disbelieve. After all, this is 2020. This is not supposed to happen. We should have been able to control the spread of the virus, but we could not. COVID-19 quickly spread throughout the world causing havoc and economic despair.
While some sectors of the construction industry are not as impacted as others, contractors industry-wide need to consider how COVID-19 will impact their contractual obligations. Depending on what happens and what the government decides to do to stop the spread of the coronavirus, project delays, supply chain distributions, lost productivity and work stoppages may continue for months. All of this will impact the contracts that contractors have with owners. Contractors may not be able to preform according to the terms of the contract through no fault of their own. Owners may no longer qualify for the financing needed to pay for the project.
FORCE MAJEURE
According to Investopedia, “force majeure refers to a clause that is included in contracts to remove liability for natural and unavoidable catastrophes that interrupt the expected course of events and prevent participants from fulfilling obligations.”
Reprinted courtesy of
Richard P. Higgins, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Higgins may be contacted at
Richard.Higgins@MCC-CPAs.com
Insurer Must Defend Claims of Negligence and Private Nuisance
July 10, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined there was a duty to defend negligence and private nuisance claims for dumping materials on the plaintiffs' property. Peters Heavy Construction, Inc. v. X-Pert One Tracking Corp., 2018 Wisc. App. LEXIS 358 (Wis. Ct. App. March 29, 2018).
Peters Heavy Construction sued X-Pert One for negligently depositing shingle materials, tires, and other solid materials on Peters' property, causing damage to Peters, including loss of use of portions of the property. Peters also alleged that X-Pert One's actions negligently created a private nuisance causing harm to Peters' property. X-Pert One's insurer, Northfield Insurance Company, was also sued.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
An Obligation to Provide Notice and an Opportunity to Cure May not End after Termination, and Why an Early Offer of Settlement Should Be Considered on Public Works Contracts
August 17, 2020 —
Jeff Kaatz - Ahlers Cressman & SleightIn 2015, the City of Puyallup (“City”) and Conway Construction Company (“Conway”) executed a public works contract for road improvements (“Project”). On March 9, 2016, approximately four months after work started on the Project, the City issued Conway a notice of suspension and breach of contract and identified nine defective and uncorrected work and safety concerns. Conway denied any wrongdoing, and on March 25, 2016, the City issued a notice of termination for default and withheld payments due to Conway.
Conway subsequently filed suit in Pierce County Superior Court and alleged the City’s termination for default breached the contract and sought a determination that the City’s termination for default was improper and should be deemed a termination for convenience. Conway sought approximately $1.25 million in damages and recovery of its attorney fees and costs. Following a bench trial, the Trial Court found the City breached the contract and awarded Conway damages, attorney fees, and costs. The City appealed.[1]
On appeal, after affirming the trial court’s determination that the City improperly terminated Conway, the Court of Appeals considered two other issues raised by the City. First, whether the City was entitled to a set-off for replacing defective work discovered after Conway was terminated. Second, whether Conway is entitled to attorney fees if it did not make the statutorily required offer of settlement per RCW 39.04.240.
Read the court decisionRead the full story...Reprinted courtesy of
Jeff Kaatz, Ahlers Cressman & SleightMr. Kaatz may be contacted at
Jeff.Kaatz@acslawyers.com
Unlocking the Hidden Power of Zoning, for Good or Bad
October 21, 2024 —
David Zipper - BloombergNo longer dismissed as an insomnia-curing corner of local governance, zoning is having a moment. It’s at the heart of the pro-housing Yes In My Backyard — or YIMBY — movement, which seeks to reform the rules that mandate the construction of single-family homes across much of the US, and the arcane details of land use policy are being debated in national outlets and city councils across the US. In much of this discourse, zoning is the clear villain, blamed for feeding societal ills ranging from housing costs to racial discrimination to greenhouse gas emissions.
In her new book Key to the City, Sara Bronin examines zoning with a critical but sympathetic eye. Bronin brings deep experience to the topic, having studied zoning as an architect and lawyer before overhauling the land use regulations of Hartford, Connecticut. A professor of architecture and planning at Cornell University (and an occasional Bloomberg CityLab contributor), she is currently on leave to chair the federal Advisory Council on Historic Preservation.