Nondelegable Duties
June 04, 2024 —
David Adelstein - Florida Construction Legal UpdatesHave you heard the expression “nondelegable duty”? The issue of a nondelegable duty comes into play when a party hires an independent contractor and the independent contractor commits negligence, primarily in the personal injury context. In other words, a plaintiff wants to hold a defendant liable for the injuries caused by the defendant’s independent contractor.
A nondelegable duty is one that “may be imposed by statute, contract, or the common law. In determining whether a duty is nondelegable, the question is whether the responsibility at issue is so important to the community that an employer should not be allowed to transfer it to a third party.” Garcia v. Southern Cleaning Service, Inc., 360 So.3d 1209, 1211 (Fla. 3d DCA 2023) (internal citation omitted).
When it comes to CONTRACTUAL duties:
[S]pecifically the principle that one who undertakes by contract to do for another a given thing cannot excuse himself to the other for a faulty performance by showing that he hired someone else to perform the task and that other person was the one at fault. In other words, where the contracting party makes it her or his duty to perform a task, that party cannot escape liability for the damage caused to the other contracting party by the negligence of independent contractors hired to carry out the task.
Gordon v. Sanders, 692 So.2d 939, 941 (Fla. 3d DCA 1997).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
US Appeals Court Slams FERC on Long-Muddled State Environmental Permits
March 27, 2019 —
Mary B. Powers and Debra K. Rubin - Engineering News-RecordWhat may be the nation’s largest dam removal project—delayed for years by regulatory and legal disputes of a utility, stakeholders and states over licensing and environmental permits—now may have new momentum after a hard-hitting January federal appeals court ruling.
Reprinted courtesy of
Mary B. Powers, ENR and
Debra K. Rubin, ENR
Ms. Rubin may be contacted at rubind@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
How To Lock Disputes Out Of Your Project In Construction
July 22, 2019 —
Anastasios Koutsogiannis – LetsBuildDisputes are seen as one of the main threats for the successful completion of a project in construction. There is a plethora of factors which could lead to a construction dispute (e.g. contracts, behavior, environment) but, strangely enough, the industry seems to invest more attention on the resolution of a conflict instead of its prevention.
Thanks to the progress that digital technologies have witnessed during the last few years, there is a good chance that things in construction will change for the better soon. The ability to exchange crucial updates in real time, while keeping a detailed record of everything that happens on the field adds an extra level of protection to your project and ensures that all agents are on the same page.
In an effort to shed some light on the issue of construction disputes, we present below four tips that could help your team to lock conflicts out of your project:
1. Standardize your processes
Before you kickstart your project, it is of paramount importance that you standardize all your systems and processes. In that way, you will be able to add extra clarity to your workflow and eliminate misunderstandings.
Once you have achieved that, you can replicate the same process to your future projects. The more you manage to repeat the same project structure the better your team will become in completing their tasks without ending up in any kind of conflict.
In that sense, standardization could be a long-term investment for your organization.
2. Go digital
As soon as your processes are defined, it is time for the digital journey to begin. Finding the right tool for your project will result in a streamlined construction process where all the members of the team are on the same page without any room for costly mistakes or disagreements.
Furthermore, with the help of digital solutions it becomes easier for project managers to measure the performance on site and monitor the completion of the set benchmarks. Like that, all payments will be on time and the program of the project will reflect reality.
3. Be extra careful with the contracts
A poorly-written contract can have a big impact on the effort to lock disputes out of your construction project. While putting together a new contract, you should always make sure that you have taken into account all the different scenarios for your project.
Either that is a delay due to weather conditions or an accident on site everything should be described in detail in the contracts and be well understood by those in charge.
In any other case, things can get a bit risky and a costly dispute might wait to happen.
4. Hold regular meetings with all stakeholders
Last but certainly not least, meet regularly with all project stakeholders. The frequent contact with the different members of your team will allow you to discuss and resolve any problematic situations before they grow out of proportion.
What is more, regular meetings will help both your field teams and the people in the office to remain aligned and will eliminate the possibility of having people working on outdated versions of the program.
Of course, these meetings don’t need to be time-consuming or even in person. With the help of technology, you can keep these meetings short and to the point. In that manner, everybody involved will be able to get the most out of them.
Final word
All in all, it becomes clear that locking disputes out of your project in construction requires continuous work and a carefully-elaborated plan. Thankfully, the emergence and progress of digital solutions have made this process much easier contributing significantly to the development of the industry far from disputes and project misunderstandings.
About the author: Anastasios Koutsogiannis is Content Marketing Manager at LetsBuild.
Read the court decisionRead the full story...Reprinted courtesy of
Anastasios Koutsogiannis, LetsBuild
Sierra Pacific v. Bradbury Goes Unchallenged: Colorado’s Six-Year Statute of Repose Begins When a Subcontractor’s Scope of Work Ends
November 03, 2016 —
Luke Mecklenburg – Snell & Wilmer Real Estate Litigation BlogIt’s official: the October 20, 2016 deadline to petition for certiorari to the Colorado Court of Appeals on its decision in Sierra Pacific Industries, Inc. v. Bradbury has passed, so it appears that decision will stand.
In Sierra Pacific, the Court of Appeals held as a matter of first impression that the statute of repose for a general contractor to sue a subcontractor begins to run when a subcontractor’s scope of work is substantially complete, regardless of the status of the overall project. Sierra Pac. Indus., Inc. v. Bradbury, 2016 COA 132, ¶ 28, ___ P.3d ___. The Court of Appeals interpreted the statute of repose in C.R.S. section 13-80-104, which requires that “all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of any improvement to real property” must be brought within six years of substantial completion of that improvement. C.R.S. § 13-80-104(1)(a). Recognizing that “an improvement may be [to] a discrete component of an entire project” under Shaw Construction, LLC v. United Builder Services, Inc., 296 P.3d 145 (Colo. App. 2012), the Court of Appeals determined that “a subcontractor has substantially completed its role in the improvement at issue when it finishes working on the improvement.” Sierra Pac., 2016 COA at ¶¶ 20, 28. In doing so, it rejected Sierra Pacific’s argument that the statute could be tolled under the repair doctrine “while others worked to repair [the subcontractor’s] ‘improper installation work and flawed repair work.’” Id. at ¶ 29. Because six years had undisputedly passed since the subcontractor completed its scope of work when Sierra Pacific filed suit against it, the Court of Appeals affirmed the trial court’s order granting the subcontractor’s motion for summary judgment under Section 13-80-104(1)(a).
Read the court decisionRead the full story...Reprinted courtesy of
Luke Mecklenburg, Snell & Wilmer Real Estate Litigation BlogMr. Mecklenburg may be contacted at
lmecklenburg@swlaw.com
School System Settles Design Defect Suit for $5.2Million
October 01, 2013 —
CDJ STAFFA school district in New York State has settled a dispute with its architectural and engineering firm for $5.2 million. Greece School District alleged that the multi-million dollar remodel lead to a variety of problems due to design defects. The problems included leaking roofs, malfunctioning drainage systems, and problems with heating systems. Tetra Tech had one work at 20 schools in the district.
The state Comptroller audited the $119.5 million renovation project and concluded that haste in the planning resulted in costly changes. Prior to the lawsuit, the architectural and engineering firm managed to recoup about $200,000 on behalf of the school district for work that was defective.
Read the court decisionRead the full story...Reprinted courtesy of
Pennsylvania Supreme Court Dismisses Appeal of Attorney Fee Award Under the Contractor and Subcontractor Payment Act
February 16, 2016 —
William J. Taylor – White and Williams LLPIn late December, the Supreme Court of Pennsylvania dismissed, as improvidently granted, the appeal in Waller Corporation v. Warren Plaza, Inc., No. 6 WAP 2015 (December 21, 2015). As a result, the Superior Court’s holding in that case that there is no good faith exception to the attorney fee provision of the Pennsylvania Contractor and Subcontractor Payment Act (CASPA), 73 P.S. §§ 501-516, remains intact.
In its decision in Waller, 95 A.3d 313 (Pa. Super. 2014), the Superior Court considered if there was a “good faith” exception to the interest and penalties provision of CASPA, 73 P.S. § 512(a), and whether there was a similar good faith exception to the attorney fee provision of the statute, 73 P.S. § 512(b). The court held that while an award of interest and penalties under § 512(a) could be denied if a party had a good faith basis for withholding payments due under a construction contract, no such exception exists for an award of attorney fees under § 512(b). Rather, an award of attorney fees is appropriate for the “substantially prevailing party” under a CASPA claim, and a claimant can be the substantially prevailing party even if the other party withheld payments in good faith.
Read the court decisionRead the full story...Reprinted courtesy of
William J. Taylor, White and Williams LLPMr. Taylor may be contacted at
taylorw@whiteandwilliams.com
Court Exclaims “Enough!” To Homeowner Who Kept Raising Wrongful Foreclosure Claims
April 01, 2015 —
Krsto Mijanovic and Annette F. Mijanovic – Haight Brown & Bonesteel LLP“There are no free houses,” began the decision issued by the Court of Appeal on March 23, 2015 in Boyce v. T.D. Service Company (B255958). Examining three years of litigation in bankruptcy court, unlawful detainer court, and the superior court, and each of their respective appellate courts, the Court of Appeal held that the plaintiff’s wrongful foreclosure claims were barred by res judicata and collateral estoppel.
Plaintiff was a borrower who purchased a home subject to a deed of trust. After plaintiff defaulted on the loan, nonjudicial foreclosure proceedings were initiated. To avoid foreclosure, plaintiff engaged in a series of stall tactics, including filing an emergency bankruptcy petition, appealing the bankruptcy court’s decision to grant the trustee relief of stay, refusing to leave the property following the trustee’s sale thereby causing an unlawful detainer action to be filed, and appealing the granting of summary judgment in favor of the defendants in the unlawful detainer action. Once evicted, plaintiff sued all the entities involved in the foreclosure process for wrongful foreclosure, declaratory relief, violation of Unfair Practices Act, and quiet title. When the trial court sustained the defendants’ demurrers on the grounds of res judicata/collateral estoppel, plaintiff naturally appealed.
Reprinted courtesy of
Krsto Mijanovic, Haight Brown & Bonesteel LLP and
Annette F. Mijanovic, Haight Brown & Bonesteel LLP
Mr. Mijanovic may be contacted at kmijanovic@hbblaw.com
Ms. Mijanovic may be contacted at amijanovic@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
XL Group Pairs with America Contractor’s Insurance Group to Improve Quality of Construction
November 13, 2013 —
CDJ STAFFInsurers XL Group and America Contractor’s Insurance Group have teamed up to use “Big Data” to help their clients maintain quality in construction. “Quality is the second leading cause of subcontractor defaults, and one of the biggest areas of profit loss for a General Contractor,” said Jason LaMonica, the profit center head for XL Group’s Subcontractor Default business.
ACIG says that their methods “allow us to correlate their quality assurance programs with actual claims results.” ACIG will be adding XL Group’s data to their own, which will allow contractors to “implement best practices leading to continuous improvement in their quality assurance program.”
Read the court decisionRead the full story...Reprinted courtesy of