Condo Owners Suing Bank for Failing to Disclose Defects
January 17, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Option Owners Association Inc., Condo Owners in Lincoln, Nebraska, filed suit against Security First Bank, “alleging the bank failed to disclose ‘hidden defects,’” reported the Lincoln Journal Star. Alleged defects include defective siding, improperly installed siding, and defective flashing. The condo owners are seeking at least $644,000 which they claim is the “fair market value of the repairs needed to fix the alleged construction defects.”
When the Lincoln Journal Star asked Jim Wefso, general counsel for Security First Bank, to comment, he stated, “The bank doesn't feel it has any liability in the case.”
Read the court decisionRead the full story...Reprinted courtesy of
Intentionally Set Atlanta Interstate Fire Closes Artery Until June
April 05, 2017 —
Engineering News-RecordCrews from C.W. Matthews Contracting Co., Marietta, Ga., are removing debris from an Interstate 85 bridge in Atlanta that collapsed during a March 30 rush-hour fire. No injuries were reported, but the incident forced an extended closure of the highway section. Investigators say the fire was intentionally set inside a fenced Georgia Dept. of Transportation surplus equipment storage area beneath the structure, and it intensified after spreading to a stockpile of polyethylene and fiberglass conduit. Flames and high temperatures subsequently compromised the bridge’s structural integrity. Authorities have charged one individual with arson and first-degree criminal damage to property, while two others were cited for criminal trespass.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
Veterans Day – Thank You for Your Service
December 05, 2022 —
Travis Colburn - Ahlers Cressman & SleightHappy Veterans Day
[1] to our country’s servicemembers past and present! ACS would like to express its deepest gratitude and respect in saying thank you to those that have served, or are serving, in our armed forces. It undoubtedly takes incredible bravery, fortitude, integrity, respect, and a commitment to our country’s evolving ideals. Some of those same attributes that are necessary for service are also well-geared toward a post-military career in construction. As some already know, Veterans have unique construction contracting opportunities at both the state and federal level. The following is a high-level overview of the process and opportunities for veterans who are not aware or who are considering a career in construction.
There are federal and state level opportunities for Veteran-owned businesses. The initial step in accessing federal and state level contracting opportunities is different for each but begins with certification/verification.
At the federal level, effective January 1, 2023, all responsibilities for the verification of Veteran-owned small businesses (“ VSOB”) will transfer from the Department of Veterans Affairs to the Small Business Administration.
[2] Verification is the process that establishes eligibility for access to Veteran-specific benefits, including certain government contracts and the purchase of surplus government property, by confirming that VSOBs and service-disabled Veteran-owned small businesses (“SDVOSB”) are operated by Veterans.
[3] Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
Courthouse Reporter Series: The Bizarre Case That Required a 117-Year-Old Expert
December 04, 2023 —
Todd Heffner & Di'Vennci Lucas - The Dispute ResolverA recent decision by the Georgia Court of Appeals, Munro v. Georgia Department of Transportation, highlights how overly specific and inflexible rules of evidence can create peculiar results.
Munro involved a dispute over the design of a Georgia intersection. No. A23A0404, 2023 WL 4194716 (Ga. Ct. App. June 27, 2023). The plaintiff alleged that the defendant improperly designed the intersection, never corrected that improper design, and failed to properly maintain the intersection. These claims were dismissed for a very odd reason: the plaintiff’s expert witness wasn’t old enough.
The case arose from a car accident. A vehicle in which the plaintiff Munro was a passenger collided with a tractor trailer crossing an intersection. Munro sued the Georgia Department of Transportation (DOT) for negligently designing, maintaining, and inspecting the intersection. The DOT filed a motion to dismiss for lack of subject matter jurisdiction on the ground of sovereign immunity and a motion to exclude the testimony of the Munros’ expert witness, among other motions. The trial court dismissed the case in full on the sovereign immunity ground and denied the other motions as moot. The Munros appealed.
Reprinted courtesy of
Todd Heffner, Troutman Pepper and
Di'Vennci Lucas, Troutman Pepper Read the court decisionRead the full story...Reprinted courtesy of
Mr. Heffner may be contacted at
todd.heffner@troutman.com
Construction Contract Clauses Which Go Bump in the Night – Part 1
November 10, 2016 —
Garret Murai – California Construction Law BlogScope, time and cost provisions may be the most important clauses in your construction contract but they’re not the only ones which can impact your bottom line. The first in a multi-part series, here are some other important construction contract clauses you may (or may not realize you should) be losing sleep over.
Provision: Incorporation and Flow-Down Provisions
- Typical Provision: “The term ‘Contract Documents’ shall include, without limitation, the Prime Contract, drawings, specifications and other agreements between Contractor and Owner, insofar as they relate in any way, directly or indirectly, to Subcontractor’s Work under this Agreement, and are hereby incorporated by reference. Subcontractor agrees to be bound to Contractor in the same manner and to the same extent as Contractor is bound to Owner under the Contract Documents. Where, in the Contract Documents, reference is made to Contractor, and the work and specifications therein pertain to Subcontractor’s trade, craft, or type of work, such work or specifications shall be interpreted to apply to Subcontractor rather than Contractor.”
- What it Means: An incorporation provision literally “incorporates” another document or documents into a contract by merely referring to them by title or description and it is not uncommon for a lower-tiered contractor to never see those documents.
A flow-down provision requires a lower-tiered contractor to comply with all obligations which a higher-tiered contractor, typically a direct contractor, owes to a higher-tiered party, typically, the owner. The intent of the provision to ensure that a lower-tiered subcontractor has no greater rights against a direct contractor has against the owner.
- What You Can Do: Lower-tiered contractors should obtain a copy of all documents to be incorporated into their contract and review them to ensure that they understand the obligations and any limitations to their rights.
Lower-tiered contractors should also seek to include language requiring that a higher-tiered contractor assume toward the lower-tiered contractor all obligations and limitations on their rights that the owner assumes toward or is subject to with respect of the general contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Beth Cook Expands Insurance Litigation Team at Payne & Fears
September 30, 2024 —
Beth A. Cook - Payne & FearsBeth Cook has joined Payne & Fears LLP as Counsel in the firm’s Insurance Litigation Group. With 18 years of legal experience, Beth brings a wealth of knowledge to her practice, focusing on insurance coverage and litigation.
“We are excited to welcome Beth to P&F! She brings a great deal of experience to our Insurance Litigation Group as we continue to grow the practice group,” said Sarah Odia, the group’s co-chair. “We look forward to working with Beth and welcome her fresh perspectives.”
Get to Know Beth
What activities do you enjoy outside of work?
Travel, sporting events, movies, craft breweries, and wineries.
Read the court decisionRead the full story...Reprinted courtesy of
Beth A. Cook, Payne & FearsMs. Cook may be contacted at
bac@paynefears.com
Summary Findings of the Fourth National Climate Assessment
January 02, 2019 —
Anthony B. Cavender - Gravel2GavelOn November 23, the latest National Climate Assessment, Fourth National Climate Assessment (NCA4), was released by the U.S. Global Research Program, as required by the Clean Air Act. The Assessment, comprising three volumes and 1600 pages, contains some rather bleak findings which the Report usefully summarizes. Here’s a description of these findings.
1.
Communities. The report states that “climate change creates new risks and exacerbates existing vulnerabilities in communities across the United States.” In particular, “more frequent and intense extreme weather and climate-related events” will continue to damage infrastructure , ecosystems and social systems. However, “global action” to significantly cut greenhouse gas emissions can substantially reduce these risks.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Cameron Pledges to Double Starter Homes to Boost Supply
March 05, 2015 —
Svenja O’Donnell – Bloomberg(Bloomberg) -- Prime Minister David Cameron pledged to double the number of homes built for first-time buyers by the end of the next parliamentary term in a bid to tackle Britain’s housing shortage.
In a speech in Colchester, Essex, on Monday setting out the final part of his Tory party’s six-point campaign platform for the May 7 election, Cameron said 200,000 properties will be built by 2020 under his starter-homes plan. Prices of the homes, only available to first-time buyers under the age of 40, will be capped at 450,000 pounds ($692,000) in London and 250,000 pounds outside the capital. Reduced planning constraints will make it easier for developers to cut building costs, allowing the homes to be sold at a 20 percent discount.
Read the court decisionRead the full story...Reprinted courtesy of
Svenja O’Donnell, BloombergMs. O’Donnell may be contacted at