Risky Business: Contractual Protections in the 'New Normal'
January 04, 2023 —
Daniel Lund III - Construction ExecutiveThe point of contracts is to create certainty to avoid litigated or arbitrated disputes. Still, the various parties in the construction process may have different risk tolerances. For example, general contractors are often characterized as “risk-tolerant.” That risk, though, is usually calculated by the contractor internally, outside the terms of the written contract, based on an assumption that the contractor can get the work done more cheaply and more quickly than the owner anticipated. Project owners typically want and expect close-to-absolute certitude—absolutely as to cost—in their construction contracts. The standard fixed-price or lump-sum construction contract is geared toward protecting that interest.
Post-COVID-19, however, the discussion in the industry suggests that all bets are off when pricing and agreeing to construction work. Labor and materials shortages have sent owners and their design consultants backpedaling when general contractors pursuing a fixed-price contract seek contractual concessions that “un-fix” the price.
Reprinted courtesy of
Daniel Lund III , Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
A Chicago Skyscraper Cements the Legacy of a Visionary Postmodern Architect
December 31, 2024 —
Mark Byrnes - BloombergA handsome and eclectic stretch of buildings along Michigan Avenue known as “Chicago’s Front Door” offers a view that reflects the city’s status as a destination for serious architecture. Louis Sullivan and Dankmar Adler’s Auditorium Building, where a young Frank Lloyd Wright designed interiors, is right there on Grant Park; so is Daniel Burnham’s Railway Exchange, where he drew up the 1909
Plan of Chicago.
Now a glass-and-aluminum apartment tower anchors the southern end of this scene, filling in a rare gap within this landmarked
streetwall and putting a bow on the career of another heroic figure in Chicago’s architectural history: Helmut Jahn.
Read the court decisionRead the full story...Reprinted courtesy of
Mark Byrnes, Bloomberg
In All Fairness: Illinois Appellate Court Finds That Arbitration Clause in a Residential Construction Contract Was Unconscionable and Unenforceable
August 22, 2022 —
Gus Sara - The Subrogation StrategistIn Bain v. Airoom, LLC, No. 1-21-001, 2022 Ill. App. LEXIS 241, the Appellate Court of Illinois (Appellate Court) considered whether the lower court erred in enforcing an arbitration clause in a construction contract between the parties and, as a result, dismissing the plaintiff’s lawsuit. The Appellate Court found that even if the arbitration clause was enforceable, the appropriate action would have been for the court to stay the lawsuit, as opposed to dismissing the case entirely. The Appellate Court then considered the language of the arbitration clause and found that several provisions were substantively unconscionable, which rendered the entire arbitration clause unenforceable. The Appellate Court reversed the lower court’s decision compelling arbitration and reinstated the plaintiff’s complaint.
In 2018, the plaintiff, Ms. Bain, a disabled senior citizen, hired the defendant, Airoom, LLC (Airoom), to renovate her home. Airoom provided its “Cash Sales Contract,” which included a binding arbitration clause. The clause required that any dispute arising or relating to the contract be resolved by binding arbitration through the American Arbitration Association (AAA), using the Construction Industry Arbitration Rules and Mediation Procedures (Construction Industry Rules).
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Top 10 Lessons Learned from a Construction Attorney
February 18, 2015 —
Craig Martin – Construction Contractor AdvisorI have had the pleasure of working with
Cordell Parvin, who in his earlier career was a preeminent construction attorney, and now,
coaches attorneys. Cordell has shared countless construction guides and presentations with me over the years, for which I am extremely grateful. Below is Cordell’s Lesson’s Learned list, that is as true today as when he drafted it years ago.
1. Contracts and owners are not all alike. Some are fairer than others. Some create greater risks of making the budget if we encounter changes, delays and impacts. We should appreciate the risks before bidding and not underestimate indirect costs of staff to deal with these situations.
2. It is important to have a thorough understanding of the Contract Administration requirements of complex contracts. Identifying specifically what must be done when changes, delays and differing site conditions are encountered is one way to establish the understanding.
3. If a project ever ends up in court, every letter, note, e-mail and memo is evidence and will be taken out of context by the opposing lawyer. Recording every mistake, miscalculation, problem or lesson learned during construction of the project will come back to haunt you.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Baltimore Bridge Collapse Occurred After Ship Lost Power Multiple Times
May 28, 2024 —
Allyson Versprille - BloombergThe container ship that rammed into Baltimore’s Francis Scott Key Bridge in March lost power multiple times on both the day of the fatal accident and the day before, according to a preliminary report.
The Dali, which sails under the flag of Singapore, lost power twice on March 26 before hitting the bridge and causing it to collapse, killing six construction workers who were on the structure at the time. The first blackout was caused when electrical breakers powering most of the vessel’s equipment and lighting unexpectedly tripped, the National Transportation Safety Board said in a report Tuesday.
The crew eventually was able to restore electrical power, but then a second blackout occurred only 0.2 miles from the bridge. They regained power, but the ship lacked the propulsion needed to avoid striking the bridge, safety inspectors found.
Read the court decisionRead the full story...Reprinted courtesy of
Allyson Versprille, Bloomberg
Developer Africa Israel Wins a Round in New York Condominium Battle
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFIn Manhattan, New York, a “Supreme Court judge partially granted a temporary restraining order to Africa Israel,” which “means the developer does not at this time have to cede control of the Downtown Condominium board to unit owners, following a February lawsuit against the developers by state Attorney General Eric Schneiderman,” according to The Real Deal.
The condominium battle began after Schneiderman filed suit against the developers, claiming that they did not fix construction defects, which in turn caused them to fail to obtain a certificate of occupancy, reported The Real Deal. The attorney general “also alleged that the pair misappropriated more than $9 million placed in an escrow account to finance those repairs.”
However, according to The Real Deal, Africa Israel has claimed not to be a sponsor of the building. “Attorney Aaron Abraham, representing both Africa Israel and the sponsor of 15 Broad, claimed …that Africa Israel, an Israeli development firm led by billionaire Lev Leviev, never signed any documents claiming to be a sponsor of the building, noting that the sponsor principals were Boymelgreen and Pinchas Cohen.”
Steve Sladkus, attorney for the condominium unit owners, told The Real Deal, “They partnered up with Boymelgreen — they need to deal with the fallout of that.”
Read the court decisionRead the full story...Reprinted courtesy of
Modernist Houses Galore! [visual candy for architects]
February 25, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaDo you like modern architecture? Is Frank Lloyd Wright someone you wish you could have met?
If so, then you’ll want to check out the new “Masters Gallery” of the North Carolina Modernist Houses (NCMH) group. With changes and additions announced this week, it’s Gallery is America’s largest open digital archive of Modernist houses, as well as the internationally known Modernist architects who designed them.
Currently, the Gallery showcases over 30 architects with extensive house histories and over 10,000 photos. The Gallery is extensive and searchable and includes, among many other notables, Frank Gehry and, of course, Frank Lloyd Wright.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback can be contacted at
mbrumback@rl-law.com
Who Says You Can’t Choose between Liquidated Damages or Actual Damages?
October 11, 2017 —
Kevin Walton - Snell & Wilmer Real Estate Litigation BlogIn Colorado, courts enforce liquidated damages provisions if three elements are satisfied: (1) the parties intended to liquidate damages; (2) the amount of liquidated damages was a reasonable estimate of the presumed actual damages caused by a breach; and (3) at the time of contracting, it was difficult to ascertain the amount of actual damages that would result from a breach. But what happens when a contract gives a party a right to choose between liquidated damages or actual damages? This seems troublesome because it allows a party to set the floor for their damages without limitation if actual damages exceed the contractual amount. As a matter of first impression, the Colorado Supreme Court addressed this issue in Ravenstar, LLC v. One Ski Hill Place, LLC, 401 P.3d 552 (Colo. 2017).
In Ravenstar, plaintiffs contracted to buy condominiums from a developer. As part of their contracts, plaintiffs deposited earnest money and construction deposits equal to 15% of each unit’s purchase price. Plaintiffs breached their contract by failing to obtain financing and failing to close by the closing date. Each contract’s damages provision provided that if a purchaser defaulted, the developer had the option to retain all or some of the deposits as liquidated damages or, alternatively, to pursue actual damages and apply the deposits to that award. After plaintiffs defaulted, the developer chose to keep plaintiffs’ deposits as liquidated damages. Plaintiffs sued for return of their deposits.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin Walton, Snell & WilmerMr. Walton may be contacted at
kwalton@swlaw.com