Construction Contract Terms Matter. Be Careful When You Draft Them.
February 01, 2022 —
Christopher G. Hill - Construction Law MusingsIn a prior post, I discussed the case of Fluor Fed. Sols., LLC v. Bae Sys. Ordinance Sys in the context of the interplay between fraud, contract, and statutes of limitation. Some cases just keep on giving. This time the case illustrates the need for careful drafting of those
pesky, and highly important, clauses in your construction documents.
In the
current iteration of this ongoing saga, the Court considered the contractual aspects of the matter. As a reminder, the facts are as follows: In May 2011, the United States Army (“Army) awarded BAE Systems Ordnance Systems, Inc. (“BAE”) a contract to design and construct a natural gas-fired combined heating and power plant for the Radford Army Ammunition Plant (“RAAP”). On October 7, 2015, BAE issued a request for a proposal from Fluor Federal Solutions, LLC (“Fluor”) to design and build a temporary boiler facility at a specific location on the RAAP property. On October 13, 2015, the Army modified the prime contract to change the location of the boiler facility. On December 10, 2015, the Army modified the prime contract to require BAE to design and construct a permanent boiler facility. On December 30, 2015, Fluor and BAE executed a fixed-price subcontract for Fluor to design and construct the temporary boiler. Throughout 2016, BAE issued several modifications to Fluor’s subcontract to reflect the modifications BAE received from the Army on the prime contract. On March 23, 2016, BAE directed Fluor to build a permanent – rather than temporary – boiler facility. On March 28, 2016, Fluor began construction of the permanent facility and began negotiations with BAE about the cost of the permanent facility. On September 1, 2016, the parties reached an agreement on the cost for the design of the permanent facility, but not on the cost to construct the permanent facility. On November 29, 2016, the parties executed a modification to the subcontract, officially replacing the requirement to construct a temporary facility with a requirement to construct a permanent facility and agreeing to “negotiate and definitize the price to construct by December 15, 2016.” The parties were unable to reach an agreement on the construction price.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Athletic Trainers Help Workers Get Back to the Jobsite and Stay Healthy After Injury
August 12, 2024 —
Bryan Lockhart - Construction ExecutiveThere are a number of factors on an active jobsite that can lead to workplace injuries. Heavy machinery, fast-moving equipment, material handling, loud noises and more can create safety hazards and make it easy to lose focus or become distracted. Additionally, the movements workers have to do in their roles—such as lifting or pushing objects or crouching low to the ground for extended periods—can add strain to the body if not done correctly.
The goal is always to minimize the risk of injury, and yet, incidents still occur. According to 2020 Bureau of Labor Statistics data, slips, trips and falls are the most common injuries, accounting for 18% of non-fatal work injuries resulting in days away from work. When workers are injured, it can lead to downtime, lost productivity on the site and workers’ compensation claims.
Employers and site leaders can take various approaches to help workers return to the jobsite safely and effectively and keep them healthy once they return. Introducing an onsite clinic and athletic trainers can help prevent injuries, improve worker health, get people back to work effectively and keep them healthy in the long run. Here are three ways athletic trainers help workers get back to the job and improve their overall health.
Reprinted courtesy of
Bryan Lockhart, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
A Performance-Based Energy Code in Seattle: Will It Save Existing Buildings?
August 11, 2011 —
Douglas Reiser, Builders Council BlogThe City of Seattle has one of the most stringent energy codes in the nation. Based upon the Washington State Energy Code (which has been embroiled in litigation over its high standards), the code demands a lot from commercial developers. But, does it prevent developers from saving Seattle?s classic and old buildings? Perhaps.
The general compliance procedure requires buildings to be examined during the permitting process. This means that buildings are examined before they begin operating. The procedure is not malleable and is applicable to all buildings, old and new, big and small.
The downside of this procedure is that it eliminates awarding compliance to those buildings exhibiting a number of passive features, such as siting, thermal mass, and renewable energy production. This problem has prevented a number of interesting and architecturally pleasing existing building retrofits from getting off the ground. The cost of complying with the current system can be 20% more, and it might prevent builders from preserving a building?s historical integrity.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decision
Read the full story...Reprinted courtesy of
Chicago Debt Document Says $8.5B O'Hare Revamp May Be Delayed
October 26, 2020 —
Jeff Yoders - Engineering News-RecordThe $8.5-billion revamp of O'Hare International Airport may have to be delayed because of COVID-19 related economic impacts, according to documents included in paperwork to refinance existing airport debt. The city forcefully disagreed with that summation, however, and says the project will move forward and is not endangered.
Reprinted courtesy of
Jeff Yoders, Engineering News-Record
Mr. Yoders may be contacted at yodersj@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Colorado Abandons the “Completed and Accepted Rule” in Favor of the “Foreseeability Rule” in Determining a Contractor’s Duty to a Third Party After Work Has Been Completed
January 17, 2013 —
Brady Iandiorio, Higgins, Hopkins, McLain & Roswell, LLCIn a recent case, the Colorado Court of Appeals found that a contractor had a duty to a third party to warn it of a dangerous condition, even after the contractor had completed its work and the owner had accepted the contractor’s work. Collard v. Vista Paving Corp., -- P.3d --, 2012 WL 5871446 (Colo. App. 2012). While not an earth shattering or entirely new concept, the decision rendered in Collard directly accepted the foreseeability rule at the expense of the completed and accepted rule. Id.
In Collard, the City of Grand Junction (“the City”) hired Vista Paving Corp. (“Vista”) to construct two road medians according to the City’s plans and designs. On July 9, 2007, Vista began work on the medians. According to its contract with the City, Vista was responsible for traffic control during construction of the medians. On July 19, 2007, Vista completed its construction of both medians. On that date, the City’s project inspector conducted his final inspection of Vista’s work. The City’s inspector then told Vista that its work had been completed and that Vista was authorized to leave the site. Vista requested permission to remove the traffic control devices to which the City’s inspector agreed. Vista removed all of its traffic control devices.
Read the court decisionRead the full story...Reprinted courtesy of
Brady IandiorioMr. Iandiorio can be contacted at
iandiorio@hhmrlaw.com
You Are on Notice: Failure to Comply With Contractual Notice Provisions Can Be Fatal to Your Claim
September 26, 2022 —
Jenifer B. Minsky - ConsensusDocsImagine your firm is the construction manager on a multi-million-dollar project. At the end of the project you are five million dollars out-of-pocket. You have a stack of claims for additional and extended work which led to the overrun, payment for which will easily cover the shortfall. However, the owner refuses to compensate you until you can satisfactorily answer their inquiry: “Where are the notices that are expressly required under the terms of the contract?” You had a good relationship with the owner’s field representative who was aware you were performing the work and understood that your company was compiling claims. The once cooperative owner, now suffering financial restraints of their own, is resolute in their refusal leaving you no choice but to expend substantial sums of money to litigate the claims, the success of which is far from assured.
What Contract Language Can Be A Trap For An Unwary Contractor?
While courts are generally hesitant to order a forfeiture and some courts disfavor condition precedents, a judge’s hands may be tied by particular contract language requiring the strict enforcement of notice requirements. Such provisions may include: (1) an explicit clause that there be precise compliance with notice requirements; (2) express consequences for noncompliance (e.g., if the required notice is not provided the claim will be waived, forfeited or abandoned); (3) a statement that the notice requirements are a condition precedent to recovery; (4) language such as “if,” “provided that,” “or else” or “on condition that” (e.g., the owner shall review the claim, “provided such claim” was received within the applicable notice period) or (5) prohibition of any waiver of the notice requirement. To the extent the notice provision includes such language, a contractor can be without recourse even when the owner has actual knowledge of the claims or cannot show prejudice by the lack of notice.
Read the court decisionRead the full story...Reprinted courtesy of
Jenifer B. Minsky, Peckar & Abramson, P.C.Ms. Minsky may be contacted at
jminsky@pecklaw.com
Thanks for My 6th Year Running as a Construction Litigation Super Lawyer
May 16, 2022 —
Christopher G. Hill - Construction Law MusingsIt is with humility and a sense of accomplishment that I announce that I have been selected for the sixth straight year to the Virginia Super Lawyers in the Construction Litigation category for 2022. Add this to my recent election to the Virginia Legal Elite in Construction and I’ve had a pretty good year. As always, I am thrilled to be included on these peer-elected lists.
So without further ado, thank you to my peers and those on the panel at Virginia Super Lawyers for the great honor. I feel quite proud to be part of the
5% of Virginia attorneys that made this list for 2020.
The full lists of Virginia Super Lawyers will appear in the May edition of Richmond Magazine. Please check it out.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Warranty Reform Legislation for Condominiums – Unfair Practices used by Developers and Builders to avoid Warranty Responsibility for Construction Defects in Newly Constructed Condominiums
June 09, 2016 —
Nicholas D. Cowie – Maryland Condo Construction Defect Law BlogThis article pertains to needed condominium construction defect warranty reform legislation that the Maryland Legislature has been reluctant to enact into law. Below is an explanation of the legislation and a list of practical steps CAI members can take to support the legislation during the upcoming 2017 legislative session.
Background
The warranty reform legislation was unsuccessfully introduced during the 2016 legislative session as “Senate Bill 250” (“SB 250”) and “House Bill 1170” (“HB 1170”). Both bills were identical, one being filed in the Senate and the other in the House of Delegates.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas D. Cowie, Cowie & Mott, P.A.Mr. Cowie may be contacted at