Can Baltimore Get a Great Bridge?
June 21, 2024 —
James S. Russell - BloombergWhen the Francis Scott Key Bridge collapsed
after being struck by a massive container ship early in the morning on March 26, six highway workers were killed, a segment of the Baltimore Beltway was severed, the Port of Baltimore was largely shut down for two months — and the city lost an important piece of its identity.
Before its destruction made it famous, the Key Bridge was not really a landmark like San Francisco’s Golden Gate Bridge or other charismatic spans that serve as symbols for their host cities. Built in 1977, it was a more utilitarian structure, with brawny trusswork that evoked the city’s industrial past, and an important job to do: It could carry the fuel-hauling tanker trucks that are prohibited from traveling through two nearby tunnels. Its visibility at the mouth of Baltimore’s harbor marked it as a prominent link between the modest communities that line the blue-collar waterfront and the glass apartment and office towers that now define the downtown skyline.
Read the court decisionRead the full story...Reprinted courtesy of
James S. Russell, Bloomberg
U.S. Supreme Court Allows Climate Change Lawsuits to Proceed in State Court
May 01, 2023 —
George Leahy - Lewis BrisboisWashington, D.C. (April 25, 2023) - On Monday, April 24, the U.S. Supreme Court refused to hear appeals by several major energy companies that sought to remove lawsuits filed by state and local governments from state court into federal court. The Court’s
certiorari denials reject companies’ appeals in five separate cases, which involved claims brought by municipalities in Colorado, Maryland, California, Hawaii, and Rhode Island. Each municipality claims that it has been harmed by the effects of climate change, allegedly attributed to the companies’ carbon emissions.
The Court’s denials effectively allow the lawsuits to continue in state court, often seen as favorable for plaintiffs due to a greater potential for jury trials and associated damages awards than might be available in federal court. Following a
2021 Supreme Court ruling in a related case that granted the companies an additional chance to argue that their cases should be heard in federal court, the lower federal appeals courts in each of the five cases concluded that the companies had not established sufficient grounds to establish proper venue and jurisdiction in federal court. The Supreme Court’s April 24 denial leaves those decisions unaltered, allowing the lawsuits to continue in state court for further consideration.
Read the court decisionRead the full story...Reprinted courtesy of
George Leahy, Lewis Brisbois
Are You a Construction Lienor?
November 15, 2017 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to construction lien rights, not everyone that touches the project is a proper lienor. Forget about timely serving a Notice to Owner or recording a claim of lien, if you are not a proper lienor, it does not matter if you properly perfected your lien rights. If you are not a proper lienor, you have NO lien rights under the law!
Florida Statue s. 713.01(18) defines a lienor as follows:
(18) “Lienor” means a person who is:
(a) A contractor;
(b) A subcontractor;
(c) A sub-subcontractor;
(d) A laborer;
(e) A materialman who contracts with the owner, a contractor, a subcontractor, or a sub-subcontractor; or
(f) A professional lienor under s. 713.03;
and who has a lien or prospective lien upon real property under this part, and includes his or her successor in interest. No other person may have a lien under this part.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
A Homeowner’s Subsequent Action is Barred as a Matter of Law by way of a Prior “Right to Repair Act” Claim Resolved by Cash Settlement for Waiver of all Known or Unknown Claims
February 26, 2015 —
Richard H. Glucksman, Esq., Jon A. Turigliatto, Esq., and David A. Napper, Esq. – Chapman Glucksman Dean Roeb & Barger BulletinDavid Belasco v. Gary Loren Wells et al. (2015) B254525
OVERVIEW
In a decision published on February 17, 2015, the Second District Court of Appeal made clear that settlement agreements containing waivers of unknown claims in connection with a construction of a property, absent fraud or misrepresentation, will be upheld. In brief, the homeowner plaintiff had made a claim against the builder pursuant to California Code of Civil Procedure Section 896 (“Right to Repair”) and settled for a cash payment and obtained a Release of all Claims including for all known and unknown claims. The court held that homeowner’s subsequent construction defect claim was barred pursuant to the terms and conditions of the earlier release.
DISCUSSION
Plaintiff and Appellant, David Belasco ("Belasco"), purchased a newly construction home in Manhattan Beach from builder Gary Loren Wells ("Wells"). Two years after purchasing the property, Belasco filed a Complaint for construction defects, which eventually resulted in settlement between the parties. The settlement agreement included a California Civil Code Section 1524 waiver of all known or unknown claims with the word "claims" defined in part as “any and all known and unknown construction defects." Six years later in 2012, Belasco filed a Complaint alleging a claim, amongst others, that the defective and leaky roof breached the statutory warranty on new construction under California Civil Code section 896 ("Right to Repair Act").
Relying on San Diego Hospice v. County of San Diego (1995) 31 Cal.App.4th 1048, Wells and Wells' surety, American Contractors Indemnity Company (collectively "Wells"), filed a motion for summary judgment contending that the 2012 action was barred by the settlement of Belasco’s prior Complaint against Wells for construction defects to his home. When the trial court ruled in favor of Wells, Belasco appealed. Belasco, a patent attorney, made the following contentions:(1) the general release and section 1542 wavier in the settlement agreement for patent construction defects is not a "reasonable release" of a subsequent claim for latent construction defects within the meaning of section 929 and the “Right to Repair” Act; (2) a reasonable release can only apply to a "particular violation" and not to a latest defect under the language of section945.5, subdivision (f), and the settlement was too vague to be valid because it does not reference a "particular violation;" (3) section 932 of the California Civil Code specifically authorizes an action on "[s]subsequently discovered claims of unmet standards;" (4) public policy prohibits use of a general release and section 1542 waiver to bar a subsequent claim for latent residential construction defects; and (5) a genuine issue of material fact exists concerning Belasco's fraud and negligence claims that would have voided the settlement pursuant to section 1668.
Pursuant to the "Right to Repair Act" Section 929 subsection (a), a builder can make a cash offer in lieu of a repair and the homeowner is free to accept or reject such offer. Section 929subsection (b) goes on to state that
"[t]he builder may obtain a reasonable release in exchange for the cash payment. The builder may negotiate the terms and conditions of any reasonable release in terms of scope and consideration in conjunction with a cash payment under this chapter."
The Second District Court of Appeal ruled that the prior cash settlement, with a release and section 1524 wavier, was a "reasonable release" under the language of California Civil Code Section 929.
On multiple occasions, the Court noted that Belasco is an attorney and was represented by an attorney during the negotiation of the settlement agreement. By executing the agreement with express language regarding what claims were to be release, Belasco released Wells of "any and all claims" due to "any and all known and unknown construction defects." The Court reasoned that because Belasco is an attorney in his own right, he should have understood the import of the Section 1542 waiver and had the opportunity to reject or revise the settlement agreement prior to binding himself to it. The Court further found that the agreement "could not have been more clear" regarding the waiver of all unknown and known construction defect claims and therefore was not vague. Belasco's additional contentions were found to be without merit because Belasco availed himself of the statutory remedy of a cash settlement in lieu of repairs and voluntarily entered into a negotiated settlement agreement. Lastly, Belasco failed to present any evidence regarding his misrepresentation claim.
When a homeowner files a "Right to Repair Act" claim, often it seems that only two options exist: either repair the alleged defects or go to court. However, Belasco is a reminder to builders that the "Right to Repair Act" does offer an avenue for settlement. The Second District Court of Appeal presented a clear, unqualified opinion regarding the validity and enforceability of settlement agreements releasing all known or unknown construction defects in a single family home case. The Court will hold parties to the settlements they agree to. This is especially so when one of the parties is an attorney and provides deposition testimony expressly acknowledging that he understood the scope of the agreement. Attorneys for builders should always include a waiver of all known and unknown claims, which pursuant to Belasco and San Diego Hospice, will ensure that any future claims at the property will be effectively barred by the terms of the settlement agreement.
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard H. Glucksman,
Jon A. Turigliatto and
David A. Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Turigliatto may be contacted at jturigliatto@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Cyber Security Insurance and Design Professionals
March 29, 2017 —
David Adelstein – Florida Construction Legal UpdatesCyber security insurance is a relatively new insurance product that has probably become more popular and important in today’s digital age. Think about it. Almost everything is created, transmitted, shared, and stored digitally. Companies utilize cloud-based platforms to store documents, share documents, and transmit documents. Documents are transmitted via e-mail. Documents are created electronically with various software programs. And, finally, technology has made it convenient to create, access, store, share, and transmit documentation digitally through smartphones, tablets, or laptops (and various applications) – so technology enables things to be done remotely in the moment to maximize efficiency and production.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Housing in U.S. Cools as Rate Rise Hits Sales: Mortgages
April 28, 2014 —
John Gittelsohn and Prashant Gopal – BloombergAfter a roller-coaster decade of boom-bust-boom, the U.S. housing market is going downhill just when many economists thought annual sales would be heading up.
Sales of previously owned properties in March tumbled 7.5 percent from a year earlier to the slowest pace in 20 months, while purchases of new houses sank 14.5 percent from February, according to reports this week. Mortgage applications to buy homes plunged 19 percent from a year earlier, indicating slowing demand during what is typically the busiest season for deals.
The housing market’s underlying fragility is emerging as outside influences that fueled a two-year rebound are receding. Mortgage interest rates are rising from record lows as the central bank withdraws its stimulus, and investors, who had helped drive national prices up more than 20 percent as they went on a buying spree, are now retreating.
Mr. Gittelsohn may be contacted at johngitt@bloomberg.net; Mr. Gopal may be contacted at pgopal2@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn and Prashant Gopal, Bloomberg
Consider Manner In Which Loan Agreement (Promissory Note) Is Drafted
March 02, 2020 —
David Adelstein - Florida Construction Legal UpdatesConsider who you loan money too and, perhaps more importantly, the manner in which your loan agreements (promissory notes) are drafted. By way of example, in what appears to be a failed construction project in Conrad FLB Management, LLC v. Diamond Blue International, Inc., 44 Fla. L. Weekly D2897a (Fla. 3d DCA 2019), a group of lenders lent money to a limited liability company (“Company”) in connection with the development of a project. Promissory notes were executed by Company and executed by its managing member as a representative of Company, and not in a personal capacity. Company, however, did not own the project. Rather, an affiliated entity owned the project (“Affiliated Entity”). Affiliated Entity had the same managing member as Company. Once the Company received the loan proceeds, it transferred the money to Affiliated Entity, presumably for purposes of the project.
The loans were not repaid and the lenders sued Company, Affiliated Entity, and its managing member, in a personal capacity. The lenders claimed they were all jointly liable under the promissory notes. Although the trial court granted summary judgment in favor of the lenders, this was reversed on appeal as to the Affiliated Entity and the managing member because there was a factual issue as to whether they should be bound by the note executed on behalf of Company.
First, Florida Statute s. 673.4011(1) provides that “a person is not liable on a promissory note unless either (a) the person signed the note, or (b) the person is represented by an agent who signed the note.” Conrad FLB Management, LLC, supra. Affiliated Entity is a separate entity and did not execute the note.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Guarantor’s Liability on Partially Secured Debts – The Impacts of Pay Down Provisions in Serpanok Construction Inc. v. Point Ruston, LLC et al.
October 24, 2021 —
Margarita Kutsin - Ahlers Cressman & SleightIn
Serpanok Construction, Inc. v. Point Ruston, LLC, Division Two of the Washington Court of Appeals decided an issue of first impression in Washington—whether a guarantor of a partially secured debt remains liable until the last dollar of the entire debt is paid off. After examining cases from other jurisdictions, the court held that that a guarantor is liable until the underlying debt is paid in full unless the agreement contains an express pay down provision. A pay down provision sets forth the guarantor’s right to reduce its obligation to the extent of any payment toward the debt, and it establishes that the guaranty applies only until an amount equivalent to the guaranteed amount is paid off.
The Serpanok decision addressed several other issues, but the published portion of this part-published case focused on whether an entity involved in a real estate development, Point Ruston LLC, was discharged from its guaranty obligation following a foreclosure sale where the proceeds did not cover the entire debt owed to a subcontractor. Point Ruston LLC, Point Ruston Phase II LLC (“Phase II”), and Century Condominiums (“Century”) were affiliated entities (collectively “Point Ruston parties”) that constructed retail and residential structures on a site in Point Ruston. Serpanok Construction Inc. (“Serpanok”) entered into subcontract agreements with Phase II and Century to perform concrete and steel work on a parking garage and movie theater for the project. Point Ruston LLC was not a party to either subcontract.
Read the court decisionRead the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & SleightMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com