Texas Supreme Court Cements Exception to “Eight-Corners” Rule Through Two Recent Rulings
March 06, 2022 —
Jeremy S. Macklin - Traub Lieberman Insurance Law BlogThe Texas “eight corners” rule precludes insurers from disclaiming a defense obligation based on facts not alleged in the underlying pleadings. Texas federal and appellate courts have been issuing rulings addressing exceptions to the eight corners rule and recently sought guidance from the Texas Supreme Court on whether Texas law recognizes such exceptions to the “eight corners” rule. The Texas Supreme Court has now spoken on the issue.
Monroe Guar. Ins. Co. v. BITCO Gen. Ins. Corp., 65 Tex. Sup. Ct. J. 440 (2022).
In Monroe, David Jones contracted with 5D Drilling & Pump Services in the summer of 2014 to drill a 3,600-foot commercial irrigation well on his farmland. In 2016, Jones sued 5D for breach of contract and negligence relating to 5D’s drilling operations on Jones’s property. Jones’s pleading was silent as to when the damage flowing from 5D’s alleged acts of misconduct occurred. BITCO and Monroe stipulated that 5D’s drill struck a bore hole during 5D’s drilling operations in or around November 2014.
Read the court decisionRead the full story...Reprinted courtesy of
Jeremy S. Macklin, Traub LiebermanMr. Macklin may be contacted at
jmacklin@tlsslaw.com
Party Loses Additional Insured Argument by Improper Pleading
September 20, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe Archdiocese failed to plead breach of contract against the County for failure to name the Archdiocese as an additional insured under the liability policy. Pachella v. Archdiocese of Philadelphia, 2017 Pa. Commw. Unpub. LEXIS 595 (Pa. Commw. Ct. Aug. 14, 2017).
Richard and Pachella filed a complaint against the Archdiocese, alleging that Mrs. Pachella was injured when she tripped and fell on the sidewalk outside of St. Patrick's Parish. At the time, the County was leasing St. Patrick's premises for use as an election polling place. The Archdiocese filed a third party complaint alleging negligence and breach of contract claims under a Lease Agreement between St. Patrick's and the County.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Vacation Rentals: Liability of the Owner for Injury Suffered by the Renter
May 13, 2019 —
Kevin J. Parker - Snell & Wilmer Real Estate Litigation BlogWith the explosion of the “private” rental business wherein residential property owners rent their house or condo on a short-term basis to third-parties, certain legal issues have arisen with regard to the duties owed by the property owner to the renter.
A recent Virginia Supreme Court case, Haynes-Garrett v. Dunn, 818 S.E.2d 798 (Va. 2018), addressed that issue. In that case, the property owners owned a rental house in Virginia Beach. The property was not the owners’ main residence, but rather a vacation home that was sometimes used by the owners, but mostly used as a rental. The issue addressed by the court was whether – for the purpose of evaluating the owners’ duty of care to the renter – the relationship should be classified as a “landlord-tenant” relationship or an “innkeeper-guest” relationship. This classification was important because the duties of the owner to the renter were significantly different depending on the category. In the landlord-tenant arena, under Virginia law, the landlord has no duty to maintain the property in a safe condition because the property is deemed to be under the tenant’s exclusive control. (An exception being concealment or fraud by the landlord as to some defect in the premises that is known to the landlord but unknown to the tenant.) Assuming that exception does not apply, the tenant takes the premises in whatever condition they may be in, thus assuming all risk of personal injury from defects or dangerous conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin J. Parker, Snell & WilmerMr. Parker may be contacted at
kparker@swlaw.com
Building a Case: Document Management for Construction Litigation
October 07, 2019 —
Robert A. Gallagher, Jane Fox Lehman, & Michael I. Frankel, Pepper Hamilton LLP - ConsensusDocsSuccess in construction litigation often turns less on counsel’s ability to craft legal arguments and more on counsel’s ability to gather, master and present the often complex set of facts underlying the case. In construction matters, most of the key facts are found in documents: contract documents, drawings, plans and specifications, schedules, submittals, progress reports, daily logs, change orders, invoices and payment records. Nowadays, these documents will almost certainly be created, exchanged and stored electronically; many will never exist in hard copy. As such, timely collection, organization and analysis of electronically stored information (ESI) is crucially important in construction litigation.
The construction industry has always involved a large quantity of records. Today, the majority of those records exist only as ESI: Design professionals use computer-aided design (CAD) software to create construction plans. Construction managers use Primavera or similar software to create schedules and workflows. Estimators use job cost control programs. Innovative firms capture digital photos of the project, from mobilization through the punch process.
Because ESI is created and exchanged at a higher rate than hard-copy documents, ESI has facilitated a dramatic increase in the volume of records associated with construction projects. Further compounding the increase is the proliferation of mobile devices. With a smartphone in every pocket, ESI creation has moved out of the home office and the site trailer and onto the site itself. As the volume of ESI expands, so too does the time and expense associated with storing, processing, reviewing and producing these records. This article will cover strategies for balancing time and expense with the requirements of the rules and the needs of the case.
Reprinted courtesy of Pepper Hamilton LLP attorneys
Robert A. Gallagher,
Jane Fox Lehman and
Michael I. Frankel
Mr. Gallagher may be contacted at gallagherr@pepperlaw.com
Ms. Lehman may be contacted at lehmanj@pepperlaw.com
Mr. Frankel may be contacted at frankelm@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Brenda Radmacher to Speak at Construction Super Conference 2024
November 05, 2024 —
Brenda Radmacher - The Construction SeytBrenda Radmacher, partner in Seyfarth’s Construction group, will present and moderate panels at the 38thAnnual Construction Super Conference 2024 on December 9-11. The conference is recognized as the preeminent construction conference developed for mid to senior-level professionals working in legal and commercial construction markets.
Panel – Looking Around Corners: Emerging Trends and Proactive Solutions
Brenda will co-present a panel on innovative ways to engage experts in construction disputes, focusing on early expert involvement to aid in risk management, issue analysis, mitigation, and documentation for potential litigation.
Panel – Top 10 Issues to Address in Your ADR Process for a Better Solution in Construction Disputes
Read the court decisionRead the full story...Reprinted courtesy of
Brenda Radmacher, SeyfarthMs. Radmacher may be contacted at
bradmacher@seyfarth.com
Appeals Court Upholds Decision by Referee in Trial Court for Antagan v Shea Homes
May 10, 2012 —
CDJ STAFFIn the case Antangan v. Shea Homes Ltd. Partnership (Cal. App., 2012), Plaintiffs appealed “an order vacating a judgment and entering a modified judgment in their construction defect action against defendants Shea Homes, Inc. and Shea Homes Limited Partnership,” while the Defendant, Shea Homes Limited Partnership (Shea Homes) appealed “an order of the judicial referee denying its motion to strike and tax costs.”
On the Antagon issue, the appeals court concluded that “the trial court did not err by vacating and modifying its judgment so that the cost of referee’s fees would be equally divided by the parties and consistent with a prior stipulation they filed in court.”
On the Shea Homes issue, the appeals court concluded: “1) the judicial referee did not err by ruling that plaintiffs’ offers to compromise (§ 998) were validly served on Shea Homes’ counsel, 2) the offers substantially complied with statutory requirements, 3) the offers were not required to be apportioned, and 4) the referee’s award of $5,000 as costs for a person assisting plaintiffs’ counsel was not an abuse of discretion.” The appeals court affirmed the judgment.
Here is a brief history of the trial case: “Plaintiffs Chito Antangan, Jimmy Alcova and other homeowners brought an action against defendants Shea Homes, Inc. and Shea Homes Limited Partnership for damages alleging that the properties they purchased from these ‘developer defendants’ were defective. Plaintiffs claimed numerous construction defects required them ‘to incur expenses’ for ‘restoration and repairs’ and the value of their homes had been diminished.”
In response, Shea Homes filed a motion for an order to appoint a judicial referee. The motion was granted and it was ruled that “a referee would ‘try all issues’ and ‘report a statement of decision to this court.’”
On May 10, 2010 the judicial referee (Thompson) “awarded plaintiffs damages and various costs, and ruled that ‘Shea Homes shall bear all of the Referee’s fees.’” The latter ruling would become a matter for contention later on.
In July of 2010, the plaintiffs “sought, among other things, $54,409.90 for expert fees, and $14,812.50 for the services of Melissa Fox for ‘exhibit preparation & trial presentation.’ Shea Homes filed a motion to strike and/or tax costs claiming: 1) Fox was a paralegal, 2) plaintiffs were not entitled to attorney’s fees, and 3) the fees for Fox’s services were an indirect and improper method to obtain attorney’s fees. The referee disagreed and awarded $5,000 for Fox’s services. The referee also ruled that plaintiffs had properly served valid offers to compromise (§ 998) on Shea Homes’ counsel in 2009. He said those offers to defendants in the case at that time did not have to be apportioned.”
“Antangan contends the trial court erred when it vacated and modified its original judgment, which ordered Shea Homes to pay all the referee’s fees. We disagree.”
Antagon contended that the trial court erred when it vacated and modified its original judgment regarding Shea Homes paying the referee’s fees. The appeals court disagreed: “A trial court has inherent authority to vacate or correct a judgment that is void on its face, incorrect, or entered by mistake. (§ 473; Rochin v. Pat Johnson Manufacturing Co. (1998),67 Cal.App.4th 1228; Olivera
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
A Glimpse Into Post-Judgment Collections and Perhaps the Near Future?
July 13, 2020 —
Garret Murai - California Construction Law BlogAccording to a recent study conducted by the Harvard University, the University of Chicago, and the University of Illinois, more than 100,000 small businesses (firms with fewer than 500 employees) representing 2% of small businesses in the America have closed their doors permanently due to the coronavirus. The next case, although about events occurring before COVID-19, provides a glimpse of what litigation may look like in the intervening months and years as companies struggle to keep their doors open.
The Wanke Case
Waterproofing company Wanke, Industrial, Commercial, Residential, Inc. sued a former employee, Scott Keck, and his competing company, WP Solutions, Inc., for trade secret misappropriation and obtained a judgment for $1,190,929.
At the time, general contractor AV Builder Corp. had hired WP Solutions as a waterproofing subcontractor on fire residential and commercial projects. In the face of the judgment obtained by Wanke, Keck declared bankruptcy and dissolved WP Solutions.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Florida Condo Collapse Victims Reach $1 Billion Settlement
May 23, 2022 —
Erik Larson - BloombergVictims of the South Florida condominium collapse that killed 98 people last year reached settlements totaling almost $1 billion with defendants including the developer of an adjacent luxury tower, engineers and a law firm for the condo association.
The massive deal was cobbled together through multiple agreements before a state court hearing Wednesday in Miami, according to Harley S. Tropin, one of the lead plaintiffs’ lawyers who had sued on behalf of survivors and victims’ families. He said he disclosed the settlements in court.
“We are pleased to have resolved this case with the defendants to get what we think is a very fair recovery to help end the litigation and allow the victims to attain some means of attempting to move forward from this horrific tragedy,” Tropin said in an emailed statement.
The 12-story Champlain Towers South condominium building in Surfside, Florida, collapsed June 24, triggering multiple lawsuits and prompting state and federal probes. A focus was the development of the Renzo Piano-designed Eighty Seven Park high-rise next door to the Champlain Towers.
Read the court decisionRead the full story...Reprinted courtesy of