Should I Pull the Pin? Contractor and Subcontractor Termination for Cause
January 26, 2017 —
Patrick McNamara - Porter Law GroupAny owner or general contractor who has a few projects under his or her belt has likely had this thought: “My contractor (or subcontractor) is not performing the way I expected; should I replace him?” The other side of the termination coin is: “This project is not going the way I expected; should I get out?”
While there may be an emotional high that immediately comes from terminating a contractor or subcontractor (or leaving a project, in mid-stream), there are many factors to be weighed, before making that decision.
Project Delay. Replacing a contractor or subcontractor that has already begun performance always results in delays to the project. Assessing the work in place, interviewing replacement contractors, and negotiating the terms of the new relationship can easily consume weeks, if not months of project time.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at
pmcnamara@porterlaw.com
Roof Mounted Solar Panels: Lower Your Risk of Fire
September 25, 2023 —
The Hartford Staff - The Hartford InsightsAs the federal government, individual states, businesses and consumers take steps to address climate change, the use of renewable energy – including roof-mounted solar panels – has steadily increased. Over the past decade, the use of solar energy solutions has grown by 33% annually. This is driven by tax-based incentives for clean energy, combined with installation costs that are down more than 50% from 10 years ago.1
As more companies execute climate-focused goals to limit greenhouse emissions, reduce their carbon-footprint and lower energy costs, the use of solar power for commercial buildings is likely to increase. Currently, it's estimated that only 3.5% of commercial buildings have rooftop solar panels, but 70% are potential targets for solar.2
We know the use of solar power can have positive impacts on the environment and generate long-term energy cost savings. However, there are several considerations and potential risks that commercial property owners and facilities managers should consider prior to investing in solar, says Tracey Greene, underwriting director for Middle and Large Commercial Real Estate at The Hartford.
Read the court decisionRead the full story...Reprinted courtesy of
The Hartford Staff, The Hartford Insights
Brown Orders Mandatory Water Curbs for California Drought
April 01, 2015 —
Michael B. Marois – BloombergGovernor Jerry Brown ordered California’s first mandatory water restrictions as the drought gripping the state enters a fourth year.
Brown issued an executive order seeking a mandatory 25 percent reduction in use and a requirement that new homes feature water-efficient irrigation if the builder plans to use potable water for landscaping. He also called for 50 million square feet of lawns to be replaced with drought-tolerant landscaping and required campuses, golf courses and cemeteries to cut back on water.
Read the court decisionRead the full story...Reprinted courtesy of
Michael B. Marois, BloombergMr. Marois may be contacted at
mmarois@bloomberg.net
The Administrative Procedure Act and the Evolution of Environmental Law
September 19, 2022 —
Anthony B. Cavender - Gravel2GavelEnacted in 1946, the Administrative Procedure Act (APA) has provided a lasting framework for federal agency rulemaking and adjudication, as well as establishing the power of the federal courts to exercise judicial review over these actions of the federal bureaucracy. The APA is codified at 5 U.S.C. §§ 551–559, and §§ 701-706. There have been very few amendments made to the APA over these years, which indicates that Congress is reasonably satisfied with its administration and implementation.
What follows is an overview of how the APA has been used by the courts to resolve disputes involving the federal agencies, with particular attention being paid to the development of environmental law and practice. While there have been very few amendments to the statute, the courts have been free to enlarge upon the sometimes-opaque text of the APA to, in effect, change the law, even in an era when “textual fidelity” to the language of the statute is the prevalent approach.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
“A No-Lose Proposition?”
October 07, 2024 —
Daniel Lund III - LexologyA Miller Act payment bond surety and its principal general contractor both sued in federal court in New Orleans by a project subcontractor sought to compel arbitration the claims against both contractor and surety based on an indisputably enforceable arbitration clause in the subcontract. This was urged to avoid separate actions against the contractor (arbitration) and its surety (litigation), even though the surety was not a party to the subcontract and, therefore, not a party to the arbitration clause.
In the face of the lack of an express agreement to arbitrate, the contractor and contractor argued that “no federal statute or policy prohibits all of Plaintiff’s claims from proceeding to arbitration….” Additionally, those parties urged that the surety should be allowed to affirmatively compel arbitration because the surety “would otherwise have the ability to assert the right to compel arbitration as a defense….”
The New Orleans federal district court was unpersuaded:
“[D]istrict courts within this circuit have recognized that ‘Miller Act claims by a subcontractor for unpaid labor and materials are separate and distinct from those for general breach of contract… [and] arbitration and Miller Act suits, are not, per se, inconsistent with one another.’…[A]bsent express contractual intent to subject Miller Act claims to arbitration, the court [will] not force the parties to arbitrate claims against nonparties to the contract at issue…. [C]laims against a surety, which was a non-signatory to the contract, would not be subject to arbitration without any contractual basis to do so.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
VOSH Jumps Into the Employee Misclassification Pool
July 30, 2015 —
Christopher G. Hill – Construction Law MusingsThe proper classification of workers by construction companies has been on the radar of the Department of Labor for both the US and Virginia governments for quite a while. While most of the misclassification is innocent and not done to create issues, there have been enough instances of purposeful misclassification of certain workers as independent contractors (thus avoiding workers comp and other payroll expenses) that innocent contractors have born the brunt of these issues through increased payroll costs over those that misclassify (in the form of necessarily higher bids, higher overhead, etc.).
As an additional deterrent to improper classification of workers, the Virginia Department of Labor and Industry has issued guidelines for what will occur in Virginia Department of Safety and Health (VOSH) cases.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Can You Really Be Liable For a Product You Didn’t Make? In New Jersey, the Answer is Yes
December 14, 2020 —
James Burger & Robert Devine - White and Williams LLPNew Jersey has recently expanded liability for product distributors and manufacturers to products that the distributor/manufacturer did not make or sell. This alert discusses this new law and steps that distributors and manufacturers may consider to reduce their potential liability.
In Whelan v. Armstrong International, Inc., the New Jersey Supreme Court held that distributors and manufacturers can be strictly liable for injuries caused by replacement parts added after the point of sale which had not been manufactured or sold by any of the defendants in the case. In Whelan, the defendants’ products had originally been sold with asbestos-containing parts. Mr. Whelan, the plaintiff, argued that asbestos-containing replacement parts were required to repair and maintain the products. The court found that because the products were designed with asbestos-containing parts, “[d]efendants had a duty to provide warnings given the foreseeability that third parties would be the source of asbestos-containing replacement components.” (Emphasis added).
This reasoning, based on “foreseeability,” should give pause to all product distributors and manufacturers—even those who do not make or sell products that contain asbestos. Certainly distributors and manufacturers of products with asbestos-containing parts must take heed that they may now be liable for replacement parts that they neither manufactured nor sold. This alone is a significant holding that expands potential liability.
Reprinted courtesy of
James Burger, White and Williams LLP and
Robert Devine, White and Williams LLP
Mr. Burger may be contacted at burgerj@whiteandwilliams.com
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Sometimes You Just Need to Call it a Day: Court Finds That Contractor Not Entitled to Recover Costs After Public Works Contract is Invalidated
June 29, 2020 —
Garret Murai - California Construction Law BlogJanuary was a tough month in the courts for Hensel Phelps Construction Company. Hot off the heels of Hensel Phelps Construction Co. v. Superior Court, a case concerning the 10-year statute of limitations under Civil Code section 941, comes Hensel Phelps Construction Co. v. California Department of Corrections and Rehabilitation, Case No. B293427 (January 28, 2020), a bid dispute case . . .
The Tale of a Bid, a Bid Protest, and Two Cases
A. The Bid and Bid Protest
On March 15, 2015, the California Department of Corrections and Rehabilitation (CDCR) issues an Invitation for Bid for the HVAC project at the Ironwood State Prison. The deadline to submit bids was April 30, 2015. Hensel Phelps Construction Co. submitted a timely bid and was determined to be the “apparent low bidder” with a bid of $88,160,000.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at