The Uncertain Future of the IECC
January 11, 2021 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday, I welcome an old friend and past Guest Post Friday contributor, Mike Collignon. Mike is the Co-Founder and Executive Director of the Green Builder® Coalition. He engages in national and state-level advocacy and publishes regular content for Green Builder® Media. Mike is also the Chair of the WERS Development Group and has served as the moderator or host for Green Builder® Media’s Impact Series webinars from 2012–present.
The following is an op-ed based on the author’s attendance at public meetings and conversations with inside sources.
“I think that you will all agree that we are living in most interesting times.” – Joseph Chamberlain, 1898
2020 was a historic year, both for reasons we currently comprehend and for reasons we may only understand in retrospect. Depending on how an upcoming ICC Board decision goes, it may prove to be the year the IECC met its demise.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
WATCH: 2023 Construction Economic Update and Forecast
January 09, 2023 —
Construction ExecutiveConstruction Executive presented its "2023 Construction Economic Update and Forecast" webinar with
Associated Builders and Contractors Chief Economist Anirban Basu on Dec. 14, sponsored by
Aerotek,
Bluebeam,
CMiC and
Raken.
Basu started by announcing the Federal Reserve’s rate increase of 0.5%, the latest in a series of increases aimed at combating inflation. Calling 2022 a “year of tumult and a year of surprise,” Basu further noted that the Russian invasion of Ukraine surprised many, further disrupting global supply chains and causing a shockwave to ripple through global energy prices.
Citing the U.S. Consumer Price Index, with 7.1% year-over-year inflation in November, Basu believes we’ve “peaked in terms of inflation for this cycle”; while inflation hit higher-than-expected levels throughout 2022, it leveled off at lower-than-expected rates by the end of the year. Basu predicted inflation will continue to be problematic through 2023 as it has shifted from transitory inflation due to supply-chain disruptions in 2020 and 2022 to broader inflation due to the labor market, noting that the worst of the supply-chain issues seem to be over, reaching a high point in late 2021.
Blaming the injection of fiscal stimulus coming from the federal government, monetary stimulus from the Federal Reserve and the fact that inflation has now become ingrained in the economy and in people’s expectations, leading to wage and price increases, Basu calls the economy “overheated.”
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
New York Appeals Court Rekindles the Spark
March 16, 2017 —
Lian Skaf - White and Williams LLPIn John Trimble, et al. v. City of Albany, et al., 2016, 144 A.D.3d 1484; 42 N.Y.S. 3d 432 (N.Y. App. Div.), the Supreme Court of New York, Appellate Division, addressed the issue of governmental immunity for municipal fire companies. The court held that the plaintiff, John Trimble (Trimble), had sufficient evidence related to the four-pronged test for establishing a “special relationship” between a municipality and a citizen for liability to attach. In addition, the court held that the defendants were not entitled to summary judgment on the issue of governmental immunity. Specifically, regarding the latter holding, the court stated that, when there is no actual choice made on the part of the government, the government’s actions cannot be considered discretionary and immunity will not apply.
In the case at hand, a fire occurred at Trimble’s home on the evening of February 2, 2013. Trimble called 911 and the Department of Fire and Emergency Services for the City of Albany (the Department) responded. After extinguishing the fire, the Department conducted an investigation and cleared the home. The Department’s investigators then told Trimble that the fire was extinguished and it was safe to enter the home. Trimble did so, removing some items so that he could stay with relatives that night. Several hours later, there was a rekindle and the rekindled fire destroyed the home.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
No Coverage for Additional Insured for Construction Defect Claim
July 02, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Seventh Circuit affirmed the district court's grant of summary judgment to the insurers, finding there was no coverage for the additional insured on a construction defect claim. St. Paul Guardian Ins. Co. v. Walsh Construction. Co., 2024 U.S. App. LEXIS 10285 (7th Cir. April 29, 2024).
The City of Chicago hired Walsh Construction Company as general contractor for the Facade and Circulation Enhancement (FACE) project at O'Hare International Airport. The FACE project involved building and installing a new canopy for Terminals 1, 2 and 3. The project also called for the construction of a steel and glass curtain wall that would be integrated with the curtain wall at Terminals 2 and 3. Walsh contracted with Carlo Steel Corporation to manufacture the steel and curtain wall. Carlo, in turn, subcontracted with LB Steel, LLC to manufacture and install the steel elements of the wall, which included steel columns, hammer heads and box girders. The subcontract between Carlo and LB Steel included an indemnity provision that required LB Steel to indemnify Carlo and Walsh for any property damage resulting from LB Steel's negligent performance.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Estimate Tops $5.5B for Cost of Rebuilding After Maui Fires
August 21, 2023 —
James Leggate - Engineering News-RecordRebuilding after wildfires on the island of Maui in Hawaii could cost more than $5.5 billion, according to a preliminary assessment prepared by the University of Hawaii Pacific Disaster Center and local officials.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
"On Second Thought"
October 28, 2024 —
Daniel Lund III - LexologyRehearing requests are seldom granted by courts, and when they are, there’s usually something uniquely compelling in the request and the granting.
So is the case in a matter involving monies deposited in the registry of the federal court in New Orleans related to work performed on cleanup after Hurricanes Maria and Irma in the U.S. Virgin Islands. The party depositing monies – which represented subcontract sums paid to it by the general contractor – held back several hundred thousand dollars based on withholding provisions in the various contracts in play. The Court was tasked with evaluating not only a pay-when-paid provision in the subcontract of the claiming party, but also incorporation of the terms of a higher tiered contract which allowed for the withholding.
The Court initially granted summary judgment allowing the monies to be withheld. However, on request for rehearing, it was pointed up that while monies could be retained for purposes of covering attorney’s fees and costs related to litigation initiated by the plaintiff subcontractor’s vendors, there was a particular process for that withholding – and an assertion that the process was not followed.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Insured's Complaint Against Flood Insurer Survives Motion to Dismiss
May 07, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe insurer's attempt to dismiss the insured's multi-count complaint for failure to provide full coverage for flood damage failed. Ragusa Corp. v. Standard Fire Ins. Co., 2014 U.S. Dist. LEXIS 40812 (D. Conn. March 27, 2014).
The insureds' house suffered significant damage due to flood associated with Hurricane Irene. The insureds submitted a claim. Standard Fire paid $35,216.75, well below what the insureds thought they were owed. The insureds returned the check and demanded what they believed was full payment. The insureds demanded an appraisal because the parties did not agree on the amount being paid under the policy, including disagreement about the amount owed for items that both sides agreed were covered under the policy. Standard Fire refused to participate in an appraisal.
The insureds ended up suing Standard Fire, alleging, among other things, breach of contract, negligent misrepresentation, and breach of the implied covenant of good faith and fair dealing.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Is Solar the Next Focus of Construction Defect Suits?
June 28, 2013 —
CDJ STAFFThere’s been a rapid growth in the sale of solar panels, and that’s lead some industry observers to wonder if manufacturers have been cutting back on quality. Current use of solar is six times what it was in 2008, with more than forty percent of that in the last year. The growth shows no sign of stopping, either. The Solar Energy Industry Association expects the amount of power generated by solar to increase by more than two-thirds in 2013.
With the oversupply, some fear that companies are relaxing their quality control. The New York Times found that there were widespread problems of defective units in solar cells, chiefly those manufactured in China. The Times article noted that at two solar plants in Spain, defect rates reached 34.5 percent.
Some industry observers disagree. The Insurance Journal quoted Andy Klump, the CEO of Clean Energy Associates, a Shanghai firm that provides quality assurance in the solar industry, who said that if a business had a 34 percent failure rate, “they would be out of business in a heartbeat.” Mr. Klump described the Times article as “not realistic.”
If the Times is right, Scott Turner, a construction insurance attorney, feels that the industry should ready itself for “a wave of large lawsuits.” Turner feels that “this litigation wave could make the battles over liability and insurance coverage for Chinese drywall seem like a small claims dispute.”
Read the court decisionRead the full story...Reprinted courtesy of