Melissa Dewey Brumback – Construction Law in North CarolinaAnyone recognize the photo to the left [Photo of Pay Phone]? If you are of the Millennial generation, this is a quaint thing called a public pay phone. They used to be everywhere. Imagine, not having a cell phone to keep you in constant contact with Big Brother…………. [the good old days].
As you may be able to tell from the fact that the receiver is hanging down, this phone has seen better days.
What does this have to do with construction? Everything. Just because something is done one way– even for years, or decades– doesn’t mean it should stay that way. Just as you learn new technical skills and change your designs, you should also update and modernize your office practices.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Insurer's Late Notice Defense Fails on Summary Judgment
December 13, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's motion for summary judgment to dismiss the claim because the insurer did not provide notice "as soon as practicable" was denied. Vintage Hospitality Group LLC v. Nat'l Trust Ins. Co., 2021 U.S. Dist. LEXIS 192651 (M.D. Ga. Oct. 6, 2021).
Vintage owned hotels, one of which was struck by a severe hailstorm on July 21, 2018. Vintage was not aware of roof damage until two months after the storm, and did not make the connection between the hailstorm and roof damage until February 2020, when it reported the damage to National. The claim was denied because it was not reported "as soon as practicable" as required by the policy.
Vintage sued and National moved for summary judgment.
Vintage did not notice the leaks until September 2018. The focus was on fixing the leaks, and connection to the hailstorm did not register. The leaks persisted over the next year and a half. A construction company was called in to evaluate the leaking roof. The construction company advised that the roof had experienced previous hail damage which was causing the leaks. At this point, Vintage connected the damage to the hailstorm. A claim was promptly submitted to National, which denied the claim.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Five Types of Structural Systems in High Rise Buildings
November 02, 2020 —
Chris Jackson - Construction ExecutiveToday, many cities in different countries have high-rise buildings or more popularly known as skyscrapers. The concept of skyscraper was first used to define the more than 137-foot-high buildings constructed in Chicago in 1885. It is generally defined as one that is taller than the maximum height that requires mechanical vertical transportation for people. Usually, these buildings only have limited uses and are primarily focused on functioning as residential apartments, hotels and office buildings, though they occasionally include retail and educational facilities. Because high-rise buildings are among the largest buildings built, it is necessary that their commercial and office functions require a high degree of flexibility.
That’s why it is important for high-rise buildings to have structural systems or structural frames—the assembly of interrelated or interdependent elements that forms a complex structure. These structural systems are built and designed for resisting different loads. To further understand how structural systems work, take the human body as a comparison. If human bones are weak and not properly aligned, the human body as a whole will not be able to perform or work well. Structural systems, in the same way, would not be able to take loads if not built properly. After all, no one wants a toppling skyscraper. To give the readers more information about structural systems in high-rise buildings, this article will discuss some of them.
Reprinted courtesy of
Chris Jackson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Reaffirming the Importance of Appeal Deadlines Under the Contract Disputes Act
January 26, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPA recent United States Court of Federal Claims (“COFC”) decision emphasizes the importance of deadlines for appealing a contracting officer’s (“CO”) decision under the Contract Disputes Act (“CDA”). On July 22, 2016, the COFC granted the consolidation of two naval contract dispute appeals totaling nearly $12.4 million in response to Nova Group/Tutor-Saliba’s (“NTS”) motion to resolve two Requests for Equitable Adjustment (“REA”) in the same forum. See Nova Group/Tutor-Saliba v. United States, No. 15-885C, 2016 WL 4009886, at *5 (Fed. Cl. July 22, 2016). NTS’s motion before the COFC sought to transfer an appeal of a REA before the COFC to the Armed Services Board of Contract Appeals (“ASBCA”), where another appeal of a REA arising under the same contract was presently on appeal. The COFC rejected NTS’s appeal to transfer the REA to the ASBCA because NTS did not appeal the REA within the 90-day limit under the CDA. Instead, the COFC allowed NTS to transfer the REA before the ASBCA to the COFC because timeliness was not an issue.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com
Late Progress Payments on Local Public Works Projects Are Not a Statutory Breach of Contract
May 10, 2022 —
Ted Senet & Christopher Trembley - Gibbs GidenCalifornia local public agencies and their contractors should take note of a recent appellate decision pertaining to late progress payments on public works projects. In Clark Bros., Inc. v. North Edwards Water Dist., 2022 Cal. App. LEXIS 331, filed on April 22, 2022, the Court of Appeal for the Fourth Appellate District held that a local agency’s late progress payments to a general contractor did not constitute breach of contract under the prompt payment penalty statute, Public Contract Code § 20104.50. Notwithstanding this holding, the contractor recovered damages, interest, fees, and costs in excess of its contract amount.
In 2013, the North Edwards Water District awarded a $6.2 million contract to Clark Bros., Inc. to construct a water treatment facility. The District’s water contained excessive levels of arsenic, and the project was sponsored by the State of California with funds earmarked to provide safe drinking water. The State agreed to disburse funds to the District during construction upon the State’s review and approval of the contractor’s progress payment applications. The contract required completion of the work within one year following the District’s issuance of a notice to proceed to the contractor.
As a result of factors arguably outside the control of the contractor, including unforeseen site conditions and the failure of the District’s equipment supplier to meet delivery deadlines, the project was significantly delayed beyond the deadline for completion. The District nonetheless terminated the contractor, which in turn filed suit against the District and the State. The contractor asserted claims for breach of contract, including breach of contract for the District’s failure to pay the contractor’s progress payment applications within the time specified under Public Contract Code § 20104.50. Subsection (b) of the statute provides:
Any local agency which fails to make any progress payment within 30 days after receipt of an undisputed and properly submitted payment request from a contractor on a construction contract shall pay interest to the contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure.
Reprinted courtesy of
Ted Senet, Gibbs Giden and
Christopher Trembley, Gibbs Giden
Mr. Senet may be contacted at tsenet@gibbsgiden.com
Mr. Trembley may be contacted at Ctrembley@gibbsgiden.com
Read the court decisionRead the full story...Reprinted courtesy of
How AI and Machine Learning Are Helping Construction Reduce Risk and Improve Margins
November 28, 2018 —
Manu Venugopal - Construction ExecutiveThe construction industry is often characterized as high risk and low margin. According to a McKinsey report, almost 98 percent of projects incur cost overruns or delays. Meanwhile, the construction productivity curve has remained flat when compared to other industries.
In the last decade, with the advent of cloud and mobile technologies, industry leaders have been focused on digitizing construction workflows. This has resulted in improved efficiencies, but also has created an explosion of new data sources in the construction industry. Project teams are now capturing and documenting data on mobile devices, site progress is documented via drones and sensors are used to create a connected jobsite.
Reprinted courtesy of
Manu Venugopal, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defects Lead to Demolition
May 26, 2011 —
CDJ STAFFTen years after it was built, demolition of Seattle’s McGuire Building has begun, as Jeanne Lang Jones reports in the Puget Sound Business Journal. Construction defects had rendered the 25-story apartment building uninhabitable. The major problem was corroded steel cabling. According to the report, “the building’s owners reached an undisclosed settlement last year with St. Louis-based contractor McCarthy Building Companies.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Insured’s Bad Faith Insurance Claim Evaporates Before its Eyes
August 03, 2020 —
Garret Murai - California Construction Law BlogSometimes it’s right there before your eyes. Then, poof, it’s gone. This was the experience of one insured, who brought a bad faith insurance denial claim against his insurer thinking that the facts were in his favor, only to discover they were not.
The 501 E .51st Street Case
The Water Main Break and AGI’s Report
The owner of a 10-unit apartment building built in 1963, 501 East 51st Street, Long Beach-10 LLC (just rolls off the tongue doesn’t it?), filed a bad faith action against its insurer Kookmin Best Insurance Co., Ltd., after it denied 501 East’s insurance tender following a water main break that caused the building’s foundation to subside.
The water main break occurred sometimes between December 31, 2015 and January 2, 2016 next to the southwest side of the building. 501 East tendered its insurance claim to Kookmin on March 8, 2016, and in April 2016, presented a report prepared by American Geotechnical, Inc. (“AGI”) concerning damage to the building. According to the report prepared by AGI, AGI conducted a “limited geotechnical investigation” to “evaluate site conditions relating to the reported building distress following a waterline breach near the south end of the building.” The scope of AGI’s investigation was limited to “observation, photo documentation of the site conditions, [and[ floor-level survey of the interior of the first level units.” AGI’s investigation did not involve any subsurface investigation or soil testing.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at