Changing Course Midstream Did Not Work in River Dredging Project
December 10, 2015 —
Craig Martin – Construction Contractor AdvisorA contractor learned a $12M lesson when it tried to change course on a Corps of Engineer river dredging project. The case also illustrates the importance of documenting problems on a project and providing notice of those problems to the owner.
In Weston/Bean Joint Venture v U.S., Weston/Bean was awarded a Corps of Engineers project to provide maintenance dredging on the Miami River to a depth of 15 feet. The contract noted that the contractor may experience sediment, debris and rock, including soft to moderately hard limestone.
The contractor encountered rocks early on in the project, but consistently submitted reports to the Corps of Engineers that nothing was experienced on the project that would lead to a change order or claim. And, for the first year of operations, the contractor made no claim for differing site conditions. Instead, the contractor terminated the subcontractor for not being able to process the rock uncovered during the dredging process.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Is Everybody Single? More Than Half the U.S. Now, Up From 37% in '76
September 10, 2014 —
Rich Miller – BloombergSingle Americans make up more than half of the adult population for the first time since the government began compiling such statistics in 1976.
Some 124.6 million Americans were single in August, 50.2 percent of those who were 16 years or older, according to data used by the Bureau of Labor Statistics in its monthly job-market report. That percentage had been hovering just below 50 percent since about the beginning of 2013 before edging above it in July and August. In 1976, it was 37.4 percent and has been trending upward since.
In a report to clients entitled “Selfies,” economist Edward Yardeni flagged the increase in the proportion of singles to more than 50 percent, calling it “remarkable.” The president of Yardeni Research Inc. in New York said the rise has “implications for our economy, society and politics.”
Singles, particularly younger ones, are more likely to rent than to own their dwellings. Never-married young singles are less likely to have children and previously married older ones, many of whom have adult children, are unlikely to have young kids, Yardeni wrote. That will influence how much money they spend and what they buy.
Read the court decisionRead the full story...Reprinted courtesy of
Rich Miller, BloombergMr. Miller may be contacted at
rmiller28@bloomberg.net
The Prompt Payment Act Obligation is Not Triggered When the Owner Holds Less Retention from the General Contractor
October 27, 2016 —
John P. Ahlers – Ahlers & Cressman PLLCMost states have laws known as “prompt payment” statutes which govern the timing of payments on public works projects[i] from project owners to general contractors, and from general contractors to subcontractors.[ii] The purpose of these statutes is to ensure that contractors and subcontractors who may have less leverage than the project owners and prime contractors, respectively, are paid for their work on a timely basis.
Prompt Payment Act cases are rare, and, since many of the prompt payment statutes are founded on the same principles, when we come across a Prompt Payment Act case, it is “blog worthy.” This dispute arose from the construction of the Exposition Light Rail Line Project connecting downtown Los Angeles with Culver City on which FCI/Fluor/Parsons (“FFP”) was the prime contractor, and Bloise Construction, Inc. (“Bloise”) was the excavation subcontractor to FFP. Under the prime contract, Expo,[iii] the owner, was permitted to withhold ten percent of the payments owed to FFP, and FFP, pursuant to its subcontract with Bloise, was entitled to also withhold ten percent of the payments to Bloise as retention.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman, PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Contractor Liable for Soils Settlement in Construction Defect Suit
February 10, 2012 —
CDJ STAFFThe California Court of Appeals ruled on January 9 in Burrow v. JTL Dev. Corp., a construction defect case in which houses suffered damage due to improperly compacted soil, upholding the decision of the lower court.
Turf Construction entered into a deal with JTL to develop a parcel they acquired. A third firm, Griffin Homes, withdrew from the agreement “when a geotechnical and soils engineering firm reported significant problems with soil stability on 14 of the lots.” Turf Construction then took over compacting and grading the lots. Turf “had never compacted or graded a residential tract before.” Robert Taylor, the owner of Turf, “testified he knew there was a significant problem with unstable soils.”
After homes were built, the plaintiffs bought homes on the site. Shortly thereafter, the homes suffered damage from soil settlement “and the damage progressively worsened.” They separately filed complaints which the court consolidated.
During trial, the plaintiff’s expert said that there had been an inch and a half in both homes and three to five inches in the backyard and pool areas. “He also testified that there would be four to eight inches of future settlement in the next fifteen to twenty years.” The expert for Turf and JTL “testified that soil consolidation was complete and there would be no further settlement.”
Turf and JTL objected to projections made by the plaintiffs’ soil expert, William LaChappelle. Further, they called into question whether it was permissible for him to rely on work by a non-testifying expert, Mark Russell. The court upheld this noting that LaChappelle “said that they arrived at the opinion together, through a cycle of ‘back and forth’ and peer review, and that the opinion that the soil would settle four to eight inches in fifteen to twenty years was his own.”
Turf and JTL contended that the court relied on speculative damage. The appeals court disagreed, stating that the lower court based its award “on evidence of reasonably certain damage.”
Turf also that it was not strictly liable, since it did not own or sell the properties. The court wrote that they “disagree because Turf’s grading activities rendered it strictly liable as a manufacturer of the lots.” The court concluded that “Turf is strictly liable as a manufacturer of the lots.”
Judge Coffee upheld the decision of the lower court with Judges Yegan and Perren concurring.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Be Careful with Continuous Breach and Statute of Limitations
January 21, 2019 —
Christopher G. Hill - Construction Law MusingsIf you are a construction attorney like me (or anyone that takes cases to court), you deal with statutes of limitation on a daily basis. These statutes seem pretty simple. A party has “X” amount of time in which to file its lawsuit after accural of the cause of action. In a breach of contract suit, the accrual is the date of breach. Easy, right? Wrong, at least in some circumstances.
Take for example, the case of Fluor Fed. Sols., LLC v. PAE Applied Techs., LLC out of the 4th Circuit Court of Appeals. In this unpublished opinion the Court looked at “continuous breach” versus “series of separate breaches.” The basic facts are that in 2000 Flour entered into a contract with PAE whereby PAE requested and claims to have received consent from Flour to a 2.3% administrative cost cap on Flour’s work on an Air Force contract. Flour claimed that it did not agree to this cap. In 2002, Flour begain billing PAE for its costs plus the 2.3% administrative markup and billed in this fashion for the first full year. However, in subsequent years and for the next 11 years, Flour billed PAE at a higher markup rate than the 2.3%. PAE disputed the increased markup and paid Flour at the 2.3% rate. Flour periodically protested but made no move to court until it filed suit in March of 2016. After a bench trial, the district court found that Flour had agreed to the cap and found for PAE.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Hawaiian Electric Finalizes $2 Billion Maui Fire Settlement
November 18, 2024 —
Mark Chediak - BloombergHawaiian Electric Industries formalized a $2 billion agreement to settle damage claims from a wildfire that razed the historic town of Lahaina and killed more than 100 people.
The utility-owner had reached a tentative agreement in August in which it, along with other defendants including the state of Hawaii, Maui County and landowners, would pay $4 billion to resolve hundreds of lawsuits stemming from last year’s wildfire, according to a filing Tuesday.
The settlements don’t resolve claims with insurers that are part of separate lawsuits.
Read the court decisionRead the full story...Reprinted courtesy of
Mark Chediak, Bloomberg
U.S. Department of Defense Institutes New Cybersecurity Maturity Model Certification
July 13, 2020 —
Joseph N. Frost - Peckar & AbramsonContractors doing business with the Federal Government, particularly with the Department of Defense (“DoD”), commonly handle sensitive information that is not intended to be disseminated. Controlled Unclassified Information (“CUI”) is one such type and is more specifically defined as “information that requires safeguarding or dissemination controls pursuant to and consistent with laws, regulations and government-wide policies.”1 Because some DoD contracts require contractors to handle CUI, certain safeguards have been put in place to ensure its security. This article briefly touches on the current cybersecurity protocols, followed by a discussion of the new system being developed by the DoD, and what contractors most need to know about the new system.
The Defense Federal Acquisition Regulation Supplement (“DFARS”) has long required contractors to comply with certain cybersecurity standards, as published by the National Institute of Standards and Technology (“NIST”). Specifically, DFARS sought to implement the cybersecurity framework found in NIST Special Publication (“SP”) 800-171, entitled “Protecting Controlled Unclassified Information in Nonfederal Systems and Organizations.” NIST SP 800-171 sets forth fourteen (14) families of recommended security requirements for protecting the confidentiality of CUI in nonfederal systems and organizations, including, among others, access control, audit and accountability, incident response, personnel security, and system and information integrity. However, after a series of data breaches, the DoD reassessed the efficacy of the continued use of NIST SP 800-171 and ultimately decided to institute a new methodology to ensure the security of CUI.
Read the court decisionRead the full story...Reprinted courtesy of
Joseph N. Frost, Peckar & AbramsonMr. Frost may be contacted at
jfrost@pecklaw.com
Lockton Expands Construction and Design Team
July 19, 2011 —
CDJ STAFFLockton Companies, LLC, the largest privately held independent insurance broker, has announced that it is expanding its construction and design team with the hiring of Karen Erger and Tom Miller.
Ms. Erger will provide professional liability practice management, loss prevention, contract and complex claims management consulting services to Lockton's architectural, engineering and construction clients in her role as Vice President, Director of Practice Management. Her background includes construction litigation at a leading construction law firm, professional liability claims defense and claims consulting for major professional liability underwriters.
Miller joins Lockton as a Senior Vice President within the Design and Construction Unit. His role will be dedicated to serving the needs of engineering, architecture and construction firms performing services around the globe. He has spent more than 15 years concentrating on professional liability for design professionals and contractors in multiple roles. He previously managed the professional liability underwriting of one of the largest construction insurers and has developed numerous manuscript insurance products as well as focused on strategic planning to enhance business unit opportunities.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of