Illinois Supreme Court Holds That the Implied Warranty of Habitability Does Not Extend to Subcontractors
March 04, 2019 —
Michael J. Ciamaichelo - The Subrogation StrategistThe implied warranty of habitability allows a homeowner to recover damages for latent defects that interfere with the intended use of a home. In Sienna Court Condo. Ass’n v. Champion Aluminum Corp., 2018 IL 122022, 2018 Ill. LEXIS 1244 (2018), the Supreme Court of Illinois held that buyers of new homes cannot assert claims for breach of the implied warranty of habitability against subcontractors involved in the construction of the homes because the subcontractors have no contractual relationship with the homeowners and the damages are purely economic. As the court explained, the implied warranty of habitability is a creature of contract (not tort) and, therefore, only exists when there is contractual privity between the defendants and the homeowners.
In Sienna, a group of condominium unit owners alleged that their new homes contained latent construction defects and asserted claims against the various parties involved in the construction and sale of the homes, including claims against the defendant subcontractors for breach of the implied warranty of habitability. The plaintiffs contracted with the property developer to purchase the homes, but the plaintiffs had no contractual relationship with the subcontractors involved in the construction of the homes. The Sienna court, overturning the decisions of the trial court and the appellate court, granted the subcontractors’ joint motion to dismiss the plaintiff’s claims for the implied warranty of habitability because the plaintiffs had no contractual relationship with the subcontractors and the damages were purely economic.
Read the court decisionRead the full story...Reprinted courtesy of
Michael J. Ciamaichelo, White and Williams LLPMr. Ciamaichelo may be contacted at
ciamaichelom@whiteandwilliams.com
Make Sure to Properly Perfect and Preserve Construction Lien Rights
December 07, 2020 —
David Adelstein - Florida Construction Legal UpdatesIf you recording a construction lien (referred to as a claim of lien) and looking to perfect your construction lien foreclosure rights, it is imperative that you work with counsel to ensure your rights are properly preserved. This is good practice!
A claim of lien must be served on an owner within 15 days after recording. Florida Statute s. 713.08(4)(c) says: “The claim of lien shall be served on the owner. Failure to serve any claim of lien in the manner provided in s. 713.18 before recording or within 15 days after recording shall render the claim of lien voidable to the extent that the failure or delay is shown to have been prejudicial to any person entitled to rely on the service.”
Florida Statute s. 713.18, hyperlinked for your review, includes the statutory ways to serve “notices, claims of lien, affidavits, assignments, and other instruments permitted or required under [Florida Statutes Chapter 713].”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Significant Issues Test Applies to Fraudulent Claims to Determine Attorney’s Fees
January 13, 2017 —
David Adelstein - Florida Construction Legal UpdatesConstruction lienors need to appreciate on the frontend that recovering statutory attorney’s fees in a construction lien action is NOT automatic—far from it. This is because the prevailing party for purposes of attorney’s fees in a construction lien action is determined by the “significant issues test,” a subjective test with no bright line standards based on who the trial court finds prevailed on the significant issues in the case. If you want to talk about the subjective and convoluted nature of recovering attorney’s fees in a construction lien action under the significant issues test, a recent opinion by the Fourth District Court of Appeal is unfortunately another nail in the coffin.
In Newman v. Guerra, 2017 WL 33702 (Fla. 4th DCA 2017), a contractor recorded a construction lien on a residential renovation project and filed a lien foreclosure lawsuit. The homeowner countersued the contractor and asserted a fraudulent lien claim pursuant to Florida Statute s. 713.31. An evidentiary hearing was held on whether the lien was a fraudulent lien and the trial court held that the lien was fraudulent (therefore unenforceable) because it included amounts that were not lienable under the law. The remaining claims including both parties’ breach of contract claims proceeded to trial. There was no attorney’s fees provision in the contract. At the conclusion of the trial, the court found that the contractor was entitled a monetary judgment on its breach of contract claim.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Yes, Indeedy. Competitive Bidding Not Required for School District Lease-Leasebacks
October 01, 2014 —
Garret Murai – California Construction Law BlogRemember when you discovered that the tooth fairy wasn’t real?
It was kind of a bummer on one hand learning that it wasn’t a fairy that magically appeared to swap your tooth for cold hard cash, but rather your mom or, visual horrors, dad.
At the same time, it was, to your nearly-halfway-to-a-decade-on-this-planet-wizened-six-year-old mind, confirmation of what you had a sneaking suspicion was the case in any event.
And, so it is with the next case.
Lease-Leasebacks
In California, most public school construction projects are built using the traditional design-bid-build project delivery method in which a design professional designs the project, the project is put out for competitive bid and the selected contractor builds the project.
But not all school construction projects are built this way.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Kronick Moskovitz Tiedemann & GirardMr. Murai may be contacted at
gmurai@kmtg.com
Construction Site Blamed for Flooding
November 08, 2013 —
CDJ STAFFA neighborhood in Pflugerville, Texas was during some recent heavy rains, and the residents blame the nearby construction of a new elementary school. During the rains, a retention wall around the site collapsed, leading to the water discharging to their neighborhood.
One resident noted that he had about $16,000 worth of damage to his home and it has also cost him work. “I fix computers for a living, but I don’t have internet right now, and a lot of my stuff is wet,” said Erik Goeser, one of the Shallow Creek neighborhood residents.
The county is looking into the situation but notes that “the construction site in question had recently been inspected and met all Travis County expectations, requirements and codes.”
Read the court decisionRead the full story...Reprinted courtesy of
SEC Proposes Rule Requiring Public Firms to Report Climate Risks
April 11, 2022 —
Debra K. Rubin - Engineering News-RecordThe U.S. Securities and Exchange Commission issued a proposal March 21—both anticipated and feared—that would require publicly-traded companies to standardize disclosure for the first time of climate-related business risks such as those related to severe weather and decarbonization. Exchange-listed firms would also have to report greenhouse gas emissions, their own and in the supply chain, creating a major reporting mandate. The rules also apply to firms listed on overseas exchanges that operate in the U.S.
Reprinted courtesy of
Debra K. Rubin, Engineering News-Record
Ms. Rubin may be contacted at rubind@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
CA Court of Appeal Reinstates Class Action Construction Defect Claims Against Homebuilder
September 03, 2015 —
Beverley BevenFlorez-CDJ STAFFLaurence R. Phillips, Andrew S. Azarmi, and Stefani Warren of Dentons reported that “on August 19, the California Court of Appeal, Fourth District, reinstated a class action asserting construction defect claims against a nationwide homebuilder.” According to the article, the decision is significant because “it effectively opens the door to class claims against homebuilders (and potentially other service providers employed in the homebuilding industry) arising out of alleged construction defects on California residential development and construction projects.”
The decision is unpublished, but “could signal a troubling trend for companies involved in the homebuilding industry in California. It is not yet clear whether the decision will be appealed to the California Supreme Court.”
Read the court decisionRead the full story...Reprinted courtesy of
Florida’s Construction Defect Statute of Repose
August 24, 2017 —
David Suggs – Bert L. Howe & Associates, Inc.Butler Weihmuller of Katz Craig LLP discussed Florida’s 10-year statute of repose law: “Under § 95.11(3)(c), the action must commence within 10 years after the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his or her employer, whichever date is latest.”
However, Weihmuller explains that parties may disagree on the specific date For instance, in Busch v. Lennar Homes, LLC, Florida’s 5th DCA recently “reversed a trial court’s dismissal of a homeowner’s construction defect claim that was filed just beyond 10 years after the closing date on the property.” The previous decision had been based on the notion that the contract had been completed upon the date of closing. The 5th DCA declared that “a contract is not completed until both sides of a contract have been performed” and “pointed to the ‘inspection and punch-list clause’ of the contract.” The clause indicated that “[a]ny remaining items that Seller has agreed to correct will be corrected by Seller at Seller’s sole cost and expense prior to closing or at Seller’s option within a reasonable time after closing.” Since not all punch-list items had been completed prior to closing, the 5th DCA held that the contract had not been completed at closing, and therefore the statute of repose did not begin until the punch-items had been accomplished.
Read the court decisionRead the full story...Reprinted courtesy of