Beth Cook Expands Insurance Litigation Team at Payne & Fears
September 30, 2024 —
Beth A. Cook - Payne & FearsBeth Cook has joined Payne & Fears LLP as Counsel in the firm’s Insurance Litigation Group. With 18 years of legal experience, Beth brings a wealth of knowledge to her practice, focusing on insurance coverage and litigation.
“We are excited to welcome Beth to P&F! She brings a great deal of experience to our Insurance Litigation Group as we continue to grow the practice group,” said Sarah Odia, the group’s co-chair. “We look forward to working with Beth and welcome her fresh perspectives.”
Get to Know Beth
What activities do you enjoy outside of work?
Travel, sporting events, movies, craft breweries, and wineries.
Read the court decisionRead the full story...Reprinted courtesy of
Beth A. Cook, Payne & FearsMs. Cook may be contacted at
bac@paynefears.com
Reconstructing the Francis Scott Key Bridge Utilizing the Progressive Design-Build Method
June 04, 2024 —
Lisa D. Love - The Dispute ResolverHaving awakened on the morning of March 26 to the devastating news of the collapse of Baltimore’s Francis Scott Key Bridge after being struck by the Dali, a 984 length /52 beam foot cargo container ship, I thought of the many times I crossed the bridge as a child growing up in Washington, D.C. I also recalled Montgomery Schyler’s comments on the opening of the Brooklyn Bridge, when he stated that “the work which is likely to be our most durable monument, and to convey some knowledge of us to the most remote posterity, is a work of bare utility; not a shrine, not a fortress, not a palace, but a bridge.”
I thought of the beauty of New York’s Mario Cuomo Bridge, a 3.1-mile cable-stayed twin-span bridge with eight traffic lanes, bicycle and pedestrian paths, six lookout points and room for future rapid transit. It was completed in 2018 and constructed under a design-build procurement model[i] at a cost of $3.98 billion. Accelerated bridge construction (ABC) techniques were utilized in its construction. ABC techniques employ innovative planning, design, materials, and construction methods in a safe and cost-effective manner to reduce the on-site construction time that occurs when building new bridges or replacing and rehabilitating existing ones. ABC techniques improve site constructability, total project delivery time, work-zone safety for the traveling public and traffic impacts, on-site construction time, and weather-related time delays.[ii]
I also thought of the gracefulness of Boston’s Leonard P. Zakim Bunker Hill Memorial Bridge, a 0.27-mile hybrid cable-stayed steel and concrete bridge with pedestrian and bicycle access that holds 10 lanes of traffic. The Zakim Bridge was completed in 2004 at a cost of approximately $100 million as part of the $24.3 billion Big Dig.[iii] Despite its elegant, streamlined appearance, the bridge was designed to be exceptionally strong, withstand winds over 400 miles per hour and endure a magnitude 7.9 earthquake.[iv]
Read the court decisionRead the full story...Reprinted courtesy of
Lisa D. Love, JAMS
Massachusetts Roofer Killed in Nine-story Fall
January 08, 2019 —
Johanna Knapschaefer - Engineering News-RecordA 41-year-old roofer from Haverhill, Mass. fell through a roof hole nine stories to his death on Dec. 18 while working on an apartment building project in Haverhill, a city north of Boston.
Read the court decisionRead the full story...Reprinted courtesy of
Johanna Knapschaefer, ENRENR may be contacted at
ENR.com@bnpmedia.com
Retrofitting Buildings Is the Unsexy Climate Fix the World Needs
November 19, 2021 —
Marc Champion - BloombergYou may not have noticed unless you live in London, but protesters have been gluing their hands to the asphalt of the city’s thundering eight-lane M25 ring road, to the weirdly technocratic war cry of “Insulate Britain!” Frustrated commuters and the police officers who’ve had to peel these sticky activists from the road find them irritating. Yet they have a point. Among top producers of climate-harming emissions that world leaders plan to address at COP26 in Glasgow in November, buildings are the summit’s largely ignored Cinderella.
Making homes and offices leak less heat and persuading the construction industry to give up its addiction to demolition and to energy-intensive materials such as concrete, plastics, and steel have so far proved less than appealing to governments in search of solutions to the climate challenge. Retrofitting is costly and disruptive for the voters who happen to live, in the U.K. alone, in the 28 million homes that need an upgrade. It also demands the systemic transformation of a fragmented industry that’s riddled with vested interests, says Stephen Good, chief executive of the Construction Scotland Innovation Centre along Glasgow’s southern underbelly.
Read the court decisionRead the full story...Reprinted courtesy of
Marc Champion, Bloomberg
Late Progress Payments on Local Public Works Projects Are Not a Statutory Breach of Contract
May 10, 2022 —
Ted Senet & Christopher Trembley - Gibbs GidenCalifornia local public agencies and their contractors should take note of a recent appellate decision pertaining to late progress payments on public works projects. In Clark Bros., Inc. v. North Edwards Water Dist., 2022 Cal. App. LEXIS 331, filed on April 22, 2022, the Court of Appeal for the Fourth Appellate District held that a local agency’s late progress payments to a general contractor did not constitute breach of contract under the prompt payment penalty statute, Public Contract Code § 20104.50. Notwithstanding this holding, the contractor recovered damages, interest, fees, and costs in excess of its contract amount.
In 2013, the North Edwards Water District awarded a $6.2 million contract to Clark Bros., Inc. to construct a water treatment facility. The District’s water contained excessive levels of arsenic, and the project was sponsored by the State of California with funds earmarked to provide safe drinking water. The State agreed to disburse funds to the District during construction upon the State’s review and approval of the contractor’s progress payment applications. The contract required completion of the work within one year following the District’s issuance of a notice to proceed to the contractor.
As a result of factors arguably outside the control of the contractor, including unforeseen site conditions and the failure of the District’s equipment supplier to meet delivery deadlines, the project was significantly delayed beyond the deadline for completion. The District nonetheless terminated the contractor, which in turn filed suit against the District and the State. The contractor asserted claims for breach of contract, including breach of contract for the District’s failure to pay the contractor’s progress payment applications within the time specified under Public Contract Code § 20104.50. Subsection (b) of the statute provides:
Any local agency which fails to make any progress payment within 30 days after receipt of an undisputed and properly submitted payment request from a contractor on a construction contract shall pay interest to the contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure.
Reprinted courtesy of
Ted Senet, Gibbs Giden and
Christopher Trembley, Gibbs Giden
Mr. Senet may be contacted at tsenet@gibbsgiden.com
Mr. Trembley may be contacted at Ctrembley@gibbsgiden.com
Read the court decisionRead the full story...Reprinted courtesy of
Grupo Mexico Spill Sparks Public Scrutiny of $150 Million Mop-Up
September 17, 2014 —
Nacha Cattan – BloombergMexico is sending federal officials to Sonora state to oversee Grupo Mexico SAB (GMEXICOB)’s $150 million cleanup of a copper mine spill that the government says contaminated the water supplies of at least 24,000 people.
The special commission of environmental and agriculture ministry officials will monitor the company’s pledge to clean Mexico’s worst mining spill, which occurred Aug. 6 in the northern state that borders Arizona.
Grupo Mexico said last week it would create a $150 million trust after its Buenavista del Cobre operation dumped 11 million gallons of copper sulfate solution into two Sonora rivers. Industrias Bachoco SAB de CV and Ford Motor Co. (F) operate plants in Hermosillo, south of the contaminated waterways.
Read the court decisionRead the full story...Reprinted courtesy of
Nacha Cattan, BloombergMs. Cattan may be contacted at
ncattan@bloomberg.net
New Recommendations for Healthy and Safe Housing Conditions
May 19, 2014 —
Beverley BevenFlorez-CDJ STAFFThe National Center for Healthy Housing (NCHH) and the American Public Health Association (APHA) jointly “released the National Healthy Housing Standard, which provides recommendations for the maintenance and condition of occupied dwellings,” reported Big Builder.
According to Big Builder, “The standard's provisions aim to fill gaps where there are no property maintenance policies and to complement the International Property Maintenance Code and other federal, state, and local policies in place regarding the upkeep of existing homes.”
Some of the recommendations included room access to daylight, no or low-VOC building materials, and water management.
Read the court decisionRead the full story...Reprinted courtesy of
Eighth Circuit Rejects Retroactive Application of Construction Defect Legislation
September 17, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Eighth Circuit refused to retroactively apply an Arkansas statute establishing coverage for faulty workmanship. J-McDaniel Const. Co., Inc. v. Mid-Continent Cas. Co., 2014 U.S. App. LEXIS 14911 (8th Cir. Aug. 4, 2014).
The homeowners sued J-McDaniel for faulty workmanship in constructing their home. The defective construction work was performed by subcontractors. Mid-Continent refused to defend or indemnify J-McDaniel.
The insured sued Mid-Continent. The district court dismissed the claim pursuant to Essex Ins. Co. v. Holder, 261 S.W. 3d 456, 460 (Ark. 2008). In Essex, the Arkansas Supreme Court held that defective workmanship resulting in damages only to the work product itself was not an occurrence. Although The Arkansas legislature overruled Essex by statute, the district court found that the Arkansas case law barred retroactive application of the statute.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com