Damages to Property That is Not the Insured's Work Product Are Covered
October 27, 2016 —
Tred R. Eyerly – Insurance Law HawaiiReversing the district court, the Eighth Circuit predicted that under Iowa law, damage to property other than the insured's work product was covered. Decker Plastics Inc. v. West Bend Mut. Ins. Co., 2016 U.S. App. LEXIS 15235 (8th Cir. Aug. 19, 2016).
A 1's, Inc. packaged and sold landscaping materials. Decker Plastics Corporation sold plastic bags to A 1's. The plastic bags were filled with sand and rock, and stored outdoors for sale to customers. Because Decker failed to manufacture the bags with an ultraviolet inhibitor, the bags deteriorated in the sunlight. This caused small shreds of plastic to commingle with A 1's landscaping materials. The plastic was a contaminant that could not be inexpensively separated form A 1's products. A 1's had to clean spilled materials from customer sites, purchase replacement bags from another supplier, and pay to clean up its own property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Motions to Dismiss, Limitations of Liability, and More
January 23, 2023 —
Christopher G. Hill - Construction Law MusingsRemember BAE Sys. Ordnance Sys. V. Fluor Fed. Sols? I examined that case on two occasions previously here at Construction Law Musings. Previously the discussions were about the
mix (or lack thereof) between fraud and contract and about how
careful contract drafting is key.
In the
most recent opinion in this ongoing litigation from March of 2022, the Court examined various motions to dismiss the Complaint and Counterclaim in the matter. As a reminder, the basic facts are as follows.
The US Army Joint Munitions Command (“Army”) contracted with BAE Systems OrdnanceSystems, Inc. (“BAE”) to operate and maintain the Radford Army Ammunition Plant (“RFAAP”)under a basic ordering agreement (“BOA”). Under BOA Task Order 002, BAE contracted to replace the legacy NC facility at the RFAAP with a newer one (the “NC Project”). Initially, BAE subcontracted the NC Project to Lauren Engineers & Constructors (“Lauren”), but later terminated Lauren. Despite terminating Lauren, BAE’s timeline to complete the NC Project remained unchanged and BAE was required to use Lauren’s design for the NC Project. BAE gave interested bidders access to the Lauren design and other related documents and required the selected subcontractor to perform in accordance with the 85% complete Lauren design, that the Lauren design could be relied on for accuracy, and the selected subcontractor only had to complete the unfinished parts. Fluor Federal Solutions, LLC (“Fluor”) submitted a request for information (“RFI”) asking BAE about the standards referenced in the SOW. Fluor was unable to determine the completeness of the Lauren design but relied on BAE’s assertion that the design was 85% complete. BAE rejected Fluor’s initial bid as being too high given what BAE had already paid Lauren for its design and told Fluor to lower its bid because the design was close to complete. Fluor lowered its price and submitted another bid proposal that outlined a firm-fixed-price design/build that forecasted 32 months to complete the NC Project. BAE awarded Fluor an Undefinitized Contract Action (“UCA”) in the amount of $9 million dollars, later increased to $32 million. Under the UCA, Fluor began procuring materials and physical construction before a formal subcontract was agreed upon. On December 17, 2015, BAE and Fluor agreed to a fixed-price design and build subcontract (the “Subcontract”) in which Fluor agreed to design, construct, and partially commission the NC Project for $245,690,422.00, which included money spent already in the UCA. When this litigation began, Fluor was scheduled to complete its work by December 2020, 2.5 years beyond the originally agreed-upon completion date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
2017 Construction Outlook: Slow, Mature Growth, but No Decline, Expected
December 21, 2016 —
Garret Murai – California Construction Law BlogAs we count down the remaining days of 2016 (thank God) it’s time to think about what the new year will bring (I’m good with pretty much anything at this point).
The economists at Dodge Data & Analytics have a few predictions. According to their 2017 Dodge Construction Outlook, they predict that U.S. construction starts will increase modestly in 2017, up 5% to $713 billion, after rather anemic growth in 2016 following several years of steady growth.
According to Robert Murray, chief economist for Dodge Data & Analytics, while the first half of 2016 lagged behind construction activity in 2015, that shortfall grew smaller as the year progressed, easing concern that the construction industry might be in the early stage of a cyclical decline. Rather, according to Murray, it appears that the construction industry has now entered a more mature phase of expansion, one characterized by slower rates of growth than during the 2012-2015 period and that construction spending can be expected to see moderate gains through 2017 and beyond[.]
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Jury Instruction That Fails to Utilize Concurrent Cause for Property Loss is Erroneous
March 22, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe Florida District Court reversed erroneous jury instructions that adopted the efficient proximate cause doctrine in determining whether the insurer was responsible for the insureds’ collapsed roof. Jones v. Federated National Ins. Co., 2018 Fla. App. LEXIS 561 (Fla. Ct. App. Jan. 17, 2018).
The insureds filed a claim for their damaged roof, contending that the damage was caused by a hailstorm. Federal National Insurance Company denied the claim based upon exclusions for “wear and tear, marring, deterioration;” “faulty, inadequate or defective design;” “neglect;” “existing damage;” or “weather conditions.”
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Don’t Kick the Claim Until the End of the Project: Timely Give Notice and Preserve Your Claims on Construction Projects
December 10, 2015 —
Christopher G. Hill – Construction Law MusingsFor this week’s Guest Post Friday, we welcome
Tara L. Chadbourn. Tara is an attorney with
ReavesColey PLLC in Chesapeake, VA, where she concentrates her practice on construction law, litigation and commercial litigation. Tara counsels owners, contractors, subcontractors and materials suppliers in various government and commercial construction matters. Tara can be reached at tara.chadbourn@reavescoley.com.
You may have experienced and have certainly heard of the scenario in which a contractor waits to address a claim as part of project closeout, only to realize the applicable deadline has already passed. While there may have been discussions about claims during the course of the project, contractors cannot rely upon oral conversations about outstanding claims. Instead, contractors must be vigilant in satisfying notice requirements and preserving claims. While entitlement must still be proven, a contractor’s chances of recovery increase greatly if the contractor abides by notice requirements and consciously preserves claims in the following ways.
Contractors Must Acquaint Themselves with Contractual Notice Provisions:
Many prime and subcontract agreements contain stringent notice provisions that require the contractor to give notice within a certain time period or else the claim is expressly waived. The deadline for notice is often only a few days after the occurrence giving rise to the claim or the contractor becoming aware of the claim. To avoid waiver, contractors must carefully review their contracts for provisions requiring notice of a claims for adjustment for a variety of situations to include unforeseen site conditions, trade sequencing changes, project delay or scope of work changes.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Calling Hurricanes a Category 6 Risks Creating Deadly Confusion
March 25, 2024 —
Brian K Sullivan - BloombergCategory 5 has become part of the world’s lexicon to describe a disaster of monumental proportion.
Now, thanks to climate change, a pair of scientists don’t think that is a dire enough level to describe hurricanes. They raise the possibility, on a “hypothetical” basis, for a Category 6.
Global warming has increased the energy available for storms to grow stronger, according to a paper by Michael Wehner, senior scientist at the Lawrence Berkeley National Lab, and James Kossin, climate and atmospheric professor at the University of Wisconsin. Their work was published in Proceedings of the National Academy of Sciences of the US.
The scientists make a case for adjusting the five-step, Saffir-Simpson Hurricane Wind Scale, which is used to describe hurricane power. A Category 5 is assigned when storm winds reach 157 miles per hour, and today that goes up to the limit of physics. Wehner and Kossin suggest considering anything over 192 mph a Category 6.
Read the court decisionRead the full story...Reprinted courtesy of
Brian K Sullivan, Bloomberg
Another Worker Dies in Boston's Latest Construction Accident
June 20, 2022 —
Scott Van Voorhis - Engineering News-RecordBoston Police and the US Occupational Safety and Health Administration are investigating a June 9 early morning construction accident that killed a worker in Boston’s Seaport district— the latest in a spate of fatalities at worksites across the city's metro area during the past 18 months.
Reprinted courtesy of
Scott Van Voorhis, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Confirms the Right to Repair Act as the Exclusive Remedy for Seeking Relief for Defects in New Residential Construction
February 22, 2018 —
Brenda Radmacher – Construction Law BlogThe California Supreme Court recently issued its decision on a critical issue in the residential construction industry – the claims for construction defects that a California homeowner can bring against a builder or seller of new residential properties in California.
Holding
In McMillin Albany v. The Superior Court of Kern County, the Court held that California’s Right to Repair Act (California Civil Code, sections 895, et seq.) (the “Act”) is the exclusive remedy for homeowners claiming defective construction of new residences in California.
Read the court decisionRead the full story...Reprinted courtesy of
Brenda Radmacher, Gordon & ReesMs. Radmacher may be contacted at
bradmacher@grsm.com