Wyncrest Commons: Commonly Used Progress Payments in Construction Contracts Do Not Render Them Installment Contracts
December 11, 2023 —
Benjamin J. Hochberg - Peckar & Abramson, P.C.In BIL-JIM Construction Company, Inc. v. Wyncrest Commons, LP, 2023 WL 7276637 (Unpublished, decided November 3, 2023), the New Jersey Appellate Division was asked to consider two issues regarding the interpretation and application of a construction contract that utilized the standard form American Institute of Architects owner/contractor agreement (AIA Document A101-2007) (the “AIA Contract”). Specifically, it was asked to consider: 1) whether a modified AIA Contract was an “installment contract,” whereby each progress payment was subject to its own statute of limitations; and 2) whether and when work had been approved in the context of New Jersey’s Municipal Land Use Law. While the decision is presently unpublished, it provides guidance as to how form contracts utilizing the same or similar terms will be treated by New Jersey’s courts and is a reminder that the potential for future claims must be considered during contract negotiations.
Discussion
The primary issue in Wyncrest was whether an AIA Contract was an “installment contract,” and the remaining issues turned on the resolution of this question. Wyncrest, the owner for the project at issue, did not dispute that its contractor, BIL-JIM Construction Company, Inc., had not been fully paid for work that it had performed in connection with a construction project located in Ocean County, New Jersey. Instead, Wyncrest argued that because its AIA Contract with BIL-JIM required that invoices be presented and paid monthly, it constituted an “installment contract.” As such, older payments would be treated as individual transactions and were time barred by the applicable statute of limitations. The trial court agreed with Wyncrest’s characterization of the AIA Contract as an “installment contract,” and found that BIL-JIM’s invoices were each subject to their own statute of limitations. However, the trial court disagreed with Wyncrest’s argument that BIL-JIM’s claim for retainage—which was submitted at the end of its work at the project—was time barred.
Read the court decisionRead the full story...Reprinted courtesy of
Benjamin J. Hochberg, Peckar & Abramson, P.C.Mr. Hochberg may be contacted at
bhochberg@pecklaw.com
How to Lose Your Contractor’s License in 90 Days (or Less): California and Louisiana
November 15, 2021 —
Rafael Boza - Gravel2Gavel Construction & Real Estate Law BlogHaving your Contractor’s License up and running to perform work when needed, where needed, is an indispensable compliance matter that contractors face every year. However, this indispensable process may also be cumbersome and time consuming. Knowing the regulations applicable to your business in each state and what to do, how to do it, and when to do it, is of critical importance to maintain compliance and your ability to work in different states.
In this post we will do a high-level review of reporting obligations in California and Louisiana.
California’s
Contractors’ State License Law, Bus. & Prof. Code §§ 7000 et seq., requires licensees to report various information to the Contractors State License Board (CSLB) “within 90 days” of the effective date or event. Louisiana State
Licensing Laws and Regulations, R.S. §§ 37:24 et seq. and La. Admin. Code tit. 46, XXIX, §§ 101 et seq. also require similar reporting to the Louisiana State Licensing Board for Contractors (LSLBC), sometimes “within 15 days” of the event.
Read the court decisionRead the full story...Reprinted courtesy of
Rafael Boza, PillsburyMr. Boza may be contacted at
rafael.boza@pillsburylaw.com
UK Construction Defect Suit Lost over One Word
October 16, 2013 —
CDJ STAFFIn the UK, be careful what you tell your insurer; the Court of Appeal has upheld the legality of basis clauses. As Paul Lewis and Janetta Gibbs of Herbert Smith Freehills LLP explain, “a basis clause is a provision set out in the proposal form or in the insurance contract itself, to the effect that all or any of the answers to the questions in the proposal shall form the basis of the contract of insurance.” The catch, as they point out, is that “should any of those answers — whether material to the risk or not — prove to be untrue, the insurer may repudiate the policy and treat itself as never having been on risk.” There is a move in the UK to abolish the use of basis clauses in business insurance, but currently they are still legal.
This came up in a construction defect case covering latent defects in a public housing project. The contract between the owner, Genesis Housing Association Limited, and the contractor, Time and Tide (Bedford) Ltd, required TT Bedford to indemnify Genesis if it became insolvent. In the contract with the insurer, representatives of Bedford and Genesis referred to the contractor as “TT Construction.”
While the courts concluded that Bedford and Genesis were not guilty of misrepresentation or intent to defraud, they did note that neither party thought the firm’s name was “TT Construction.” Therefore, over the failure to name the builder correctly, the court found that the insurance contract was invalid.
Read the court decisionRead the full story...Reprinted courtesy of
Damages to Property That is Not the Insured's Work Product Are Covered
October 27, 2016 —
Tred R. Eyerly – Insurance Law HawaiiReversing the district court, the Eighth Circuit predicted that under Iowa law, damage to property other than the insured's work product was covered. Decker Plastics Inc. v. West Bend Mut. Ins. Co., 2016 U.S. App. LEXIS 15235 (8th Cir. Aug. 19, 2016).
A 1's, Inc. packaged and sold landscaping materials. Decker Plastics Corporation sold plastic bags to A 1's. The plastic bags were filled with sand and rock, and stored outdoors for sale to customers. Because Decker failed to manufacture the bags with an ultraviolet inhibitor, the bags deteriorated in the sunlight. This caused small shreds of plastic to commingle with A 1's landscaping materials. The plastic was a contaminant that could not be inexpensively separated form A 1's products. A 1's had to clean spilled materials from customer sites, purchase replacement bags from another supplier, and pay to clean up its own property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Another Reminder that Contracts are Powerful in Virginia
February 08, 2021 —
Christopher G. Hill - Construction Law MusingsRegular readers of this construction law blog are likely tired of my refrain that the contract is king here in Virginia. With few exceptions, some of which have been passed in the last few years, the contract can and does essentially set the “law” for the transaction. A recent opinion from the 4th Circuit Court of Appeals confirms this principle.
In Bracey v. Lancaster Foods, LLC, the Court looked at the question as to whether parties can contractually limit the statute of limitations in which a plaintiff or arbitration claimant can file its claim for relief. In Bracey, Michael Bracey, a truck driver, sued his former employer, Lancaster Foods, asserting various employment law claims. Lancaster moved to dismiss and compel arbitration based on the terms of an alternative dispute resolution agreement Bracey signed when he was hired, under which he consented to arbitration of any employment-related claim and waived all rights he may otherwise have had to a trial. Bracey challenged the arbitration clause, one that also included a 1-year limitation on the time in which Bracey was allowed to file any claim, as unconscionable. A federal judge in Maryland agreed and granted the motion to dismiss.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Construction Defect Dispute Governed by Contract Disputes Act not yet Suited to being a "Suit"
June 25, 2019 —
William S. Bennett - Saxe Doernberger & Vita, P.C.The Southern District of California recently held that a series of demands for a general contractor to investigate and repair several construction defects at a U.S. Army facility did not constitute a “suit” within the meaning of the general contractor’s commercial general liability (“CGL”) policy.
In Harper Construction Co., Inc. v. Nat’l Union Fire Ins. Co. of Pittsburgh, Pa., the U.S. Government hired Harper Construction Company (“Harper”) to construct a U.S. Army training facility for the Patriot Missile System in Fort Sill, Oklahoma. No. 18-cv-00471-BAS-NLS (S.D. Cal. Mar. 28, 2019). During the project, Harper hired Harper Mechanical Contractors (“Harper Mechanical”), an independent company, as a subcontractor “to perform demolition, grading, and other work at the Project.”
After Harper completed the project, the government informed Harper of property damage at the project, “including, but not limited to, gypsum wallboard cracks and binding doors.” Harper attempted to repair the issues, but the problems continued. The issues were apparently the result of Harper Mechanical’s grading work. Subsequently, the government sent two letters requesting an investigation and asking Harper to “propose a plan to correct the issues.” As Harper undertook an investigation spanning multiple years, the government became increasingly frustrated with the delays. The government threatened to initiate “formal administrative recourse” and to demolish the project, forcing Harper to re-build from the ground up. It also sent Harper another letter requesting Harper submit a formal proposal to correct the issues.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com
Condominium Construction Defect Resolution in the District of Columbia
October 26, 2017 —
Nicholas D. Cowie - Maryland Condo Construction Defect Law BlogNewly constructed and newly converted condominiums in the District of Columbia often contain concealed or “latent” construction defects. Left undetected and unrepaired, defects in the construction of a condominium can cause extensive damage over time, requiring associations to assess their members substantial repair costs that could have been avoided by making timely developer warranty claims.
This article provides a general overview of how Washington DC condominium associations transitioning from developer control can proactively and successfully identify defects and resolve construction defect claims with condominium developers and builders.
Condominium Association Responsibility for Timely Evaluation of Common Element Construction
Condominium associations are charged with the responsibility of overseeing and maintaining condominium common element facilities, typically consisting of building roofs, exterior walls, foundations, lobbies, common hallways, elevators, surrounding grounds, and the common structural mechanical, electrical, and plumbing systems. Following the period of developer control, it is incumbent upon a condominium association’s first unit owner elected board of directors to evaluate the construction of the condominium common element facilities and determine whether the existing, developer-created, budget and reserve fund are adequate to cover the cost of maintaining, repairing, and ultimately replacing the condominium facilities over time.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas D. Cowie, Cowie & Mott, P.A.Mr. Cowie may be contacted at
ndc@cowiemott.com
Washington Court Denies Subcontractor’s Claim Based on Contractual Change and Notice Provisions
January 29, 2024 —
Wendy Rosenstein - Ahlers Cressman & Sleight PLLCThe recent unpublished case, Cascade Civil Construction, LLC v. Jackson Dean Construction, Inc., et al.,[1] provides a legal justification for contractors to require a directive or change order in advance of performing changed work—thereby preventing the party who requested the changed work from later arguing that notice provisions were not complied with.
In the case, Jackson Dean, the prime contractor, hired Cascade to perform excavation work on a project to build a new Costco Corporate headquarters. Due to the Covid-19 pandemic and other issues, Jackson Dean directed resequencing, which required Cascade to perform excavation concurrent to dewatering. Jackson Dean also required deeper-than-planned excavation under one of the buildings.
Read the court decisionRead the full story...Reprinted courtesy of
Wendy Rosenstein, Ahlers Cressman & Sleight PLLCMs. Rosenstein may be contacted at
wendy.rosenstein@acslawyers.com